SC and HC Judgments Online at MyNation

Judgments of Supreme Court of India and High Courts

Bombay Salesian Soc. Through … vs The State Of Maharashtra And Ors on 10 October, 2019

Nitin 1 / 30 WP-5347-2018-F.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 5347 OF 2018

Bombay Salesian Society, ]
a Society registered under Societies ]
SectionRegistration Act; and a public trust ]
registered under Bombay Public Trust Act, ]
1950, through Secretary, Fr. Manuel ]
Murzullo, having ofce at Don Bosco ]
Provincial House, Nathalal Parekh Marg, ]
Matunga, Mumbai – 400 019. ] … Petitioner
Versus
1) The State of Maharashtra ]
2) Municipal Corporation of Nashik, ]
Rajiv Gandhi Bhavan, Gangapur ]
Road, Nashik. ]
3) Municipal Commissioner of Nashik ]
Municipal Corporation, Rajiv Gandhi ]
Bhavan, Sharanpur Road, Nashik. ]
4) Maharashtra State Road Transport ]
Corporation, Maharashtra Vahatuk ]
Bhavan, Dr. A. Naik Marg, Mumbai ]
Central, Mumbai – 400 008. ] … Respondents

Dr. Virendra Tulzapurkar, Senior Advocate instructed by Mr. Suneet Moholkar for the
Petitioner.
Ms. Shruti Vyas, ‘B’ Panel Counsel for Respondent No.1.
Mr. Murlidhar L. Patil for Respondent Nos.2 and 3.
Mr. Nitesh Bhutekar for Respondent No.4.

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 2 / 30 WP-5347-2018-F.doc

CORAM :AKIL KURESHI AND
S.J. KATHAWALLA, JJ.

JUDGMENT RESERVED ON : 7th AUGUST, 2019
JUDGMENT PRONOUNCED ON : 10th OCTOBER, 2019.

JUDGMENT ( PER S.J. KATHAWALLA, J. ) :-

1. The Petitioner – Bombay Salesian Society is a public trust formed and

registered under the Bombay Public Trusts Act, 1950 vide Registration No.F-

903(Bom) dated 20th October, 1961. The Petitioner is carrying out educational and

other charitable activities. Respondent No.1 is the State of Maharashtra. Respondent

No.2 is the Nashik Municipal Corporation constituted under the Maharashtra

Municipal Corporation Act, 1949, and is designated as the ‘Planning Authority’

under section 2(19) of the Maharashtra Regional and Town Planning Act, 1966

(MRTP Act). Respondent No.3 is the Municipal Commissioner of Nashik Municipal

Corporation. Respondent No.4 – Maharashtra State Road Transport Corporation

(MSRTC) is incorporated under Section 3 of the Road Transport Corporation Act,

1950, and is designated as the ‘Acquiring Authority’ under the provisions of the

MRTP Act.

2. By the above Writ Petition, the Petitioner has sought the following reliefs :

“(a) That the Hon’ble Court be pleased to issue writ of mandamus
directing the Respondent No.1 to notify in the ofcial gazette within
one month that the reservation for bus terminus made on the
Petitioner’s plot admeasuring around 5000 sq. mtrs. bearing FP
No.454 of Town Planning Scheme-II (Plan), Survey No.713 714
of Nashik, as site no.321 under Final Development Plan, Nashik, which
came in force vide TPS-1191/35(A)/CR-88/UD-9 dated 28 thJune, 1993
and which was further modifed vide TPS-1193/2124/

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 3 / 30 WP-5347-2018-F.doc

CR-126/95/UD-9 dated 19th February, 1996, has lapsed u/s.127(1)
of MRTP Act and consequently, reservation made for bus stand on
the said Petitioner’s plot as site no.231 under Revised Development
Plan, Nashik, which has come in force vide TPS-116/CR-140(A) /2016/
UD-9 dated 9th January, 2017 stands lapsed under regulation no.14(2)
of the DCPR.

(b) That this Hon’ble Court be pleased to issue writ of mandamus
directing the Respondent no.2 to grant permissions within 1 month to the
Petitioner to develop the Petitioner’s plot admeasuring around 5000 sq.
mtrs. bearing FP No.454 of Town Planning Scheme-II (Plan), Survey
No.713 714 of Nashik, as per Plans submitted on 16 th March, 2018 in
accordance with law by considering the said plot in Residential zone as
free from any reservation under Revised Development Plan, 2017.”

3. The facts and circumstances giving rise to the present Petition are briefy set

out hereunder :-

3.1 The Petitioner is the owner and in possession of piece of land bearing FP

No.454 of TPS-II (Final), Survey Nos.713 and 714-F.P. No.454-TPS-II, Nashik (trust

property).

3.2 Out of the said trust property, a plot of land admeasuring around 5000 sq. mtrs.

bearing FP No.454 of TPS (Final), Survey No. 713 714 – F.P. No.454-T.P.S.-II,

Nashik (the said plot) was reserved for City Bus Terminus in the Sanctioned

Development Plan of Nashik, 1993 as site No.321. The said plot was reserved for the

benefit of Respondent No.4 – MSRTC (the Acquiring Authority). The said

Development Plan was sanctioned by the Respondent No.1 vide No.TPS 1191/35(A)

CR-88/UD-9 dated 28th June, 1993.

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::

Nitin 4 / 30 WP-5347-2018-F.doc

3.3 The Final Development Plan, 1993 was subsequently modified and sanction

thereto was given by the Respondent No.1 vide TPS 1193/2124/CR-126/95/UD-9

dated 19th February, 1996.

3.4 The Respondent No.2 – Municipal Corporation of Nashik neither acquired the

said plot nor took any steps for acquisition of the said plot within 10 years from the

date on which the Final Development Plan became operative. In view thereof, the

Petitioner served a notice dated 30th September, 2013 as contemplated under Section

127(1) of the MRTP Act (the said Notice) on Respondent No.3 – Municipal

Commissioner of Nashik and the Divisional Controller of Respondent No.4 –

MSRTC.

3.5 The Petitioners have clearly stated in the said Notice that the Reservation

No.321 for City Bus Terminus made in the Nashik Development Plan, sanctioned by

the Urban Development Department vide No.TPS-1191/35(A) CR-88/UD-9 dated

28th June, 1993 and subsequently modified and sanctioned by Respondent No. 1 vide

No.TPS-1193/2124/CR-126/95/UD-9 dated 19th February, 1996 has lapsed since no

acquisition proceedings have been initiated within the stipulated period of 10 years as

per the provisions of the MRTP Act; that the society urgently needs the said reserved

land for the development and expansion of its charitable and educational activities;

that with the serving of the notice, the Petitioners are initiating the process of getting

the said land dereserved and making it available to the Petitioner for the purpose of

urgent development and expansion needs; and that the necessary documents are

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 5 / 30 WP-5347-2018-F.doc

attached to the said notice.

3.6 After the receipt of statutory notice under Section 127(1) of the MRTP Act

from the Petitioner, neither the said plot was acquired nor any steps for acquisition of

the said plot were taken for more than twelve months. Also no notification was

published in the ofcial gazette under Section 127(2) of the MRTP Act, notifying that

the reservation for bus terminus made on the said plot in the Final Development Plan,

1993 as site No.321 had lapsed under Section 127(1) of the MRTP Act.

3.7 The Petitioner ultimately addressed a letter dated 12 th June, 2015 to the

Respondent No.2 – Municipal Corporation of Nashik, wherein after referring to the

notice dated 30th September, 2013 addressed by the Petitioner to the Respondent No.2

under Section 127(1) of the MRTP Act, the Respondent No.2 requested the Petitioner

to take necessary steps to remove the reservation on the said plot from its record as

well as the proposed Development Plan in future.

3.8 In response to the Petitioner’s said letter dated 12 th June, 2015, the Respondent

No.1 addressed a letter dated 21st August, 2015 to the Petitioner. By the said letter, the

Petitioner was asked to remain present with necessary documents before the Planning

Committee of Respondent No.1 on 4th September, 2015 at 3.00 p.m. Accordingly, the

Petitioner remained present before the Planning Committee on 4 th September, 2015

and submitted necessary documents. According to the Petitioner, though the

Respondent No.2 was supposed to intimate the decision of the Planning Committee

on the Petitioner’s request to remove reservation on the said plot from the

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 6 / 30 WP-5347-2018-F.doc

Government records, no such decision was taken or conveyed to the Petitioner by the

Planning Committee of Respondent No.1.

3.9 According to the Petitioner when the matter regarding Petitioner’s request to

de-reserve the said plot in Government records was pending before the Planning

Committee, the Revised Development Plan of Nashik came into force in 2017. The

Respondent No.1 gave its sanction to the said plan vide

TPS-116/CR-140(A)/2016/UD-9 dated 9th January, 2017. In the revised Development

Plan, 2017, the reservation for bus stand on the said plot continued as site No.231.

3.10 According to the Petitioner, the Respondent No.1 framed and notified

Development Control Promotion Regulations (DC PR) for Nashik Municipal

Corporation which form part of the Revised Development Plan, 2017. It is provided in

Regulation 14(2) of DCPR that if the reservation in the earlier sanctioned

Development Plan is lapsed in pursuance of notice under Section 127 of the MRTP

Act, then the corresponding reservation shall stand lapsed in the revised Development

Plan, 2017 to the extent of area covered in the said notice; and the Municipal

Commissioner shall take decision on such matters. According to the Petitioner, by

virtue of Regulation 14(2) of DCPR, the reservation site No.231 on the said plot

made for bus stand under revised Development Plan of 2017 stands lapsed since

corresponding reservation No.321 on the said plot made for city bus terminus under

final Development Plan of 1993 is already lapsed under Section 127(1) of the MRTP

Act.

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::

Nitin 7 / 30 WP-5347-2018-F.doc

3.11 According to the Petitioner, in the year 2017, the Planning Committee of

Respondent No.1 finally took a decision on Petitioner’s request to de-reserve the said

plot in the Government records which was made by the Petitioner vide letter dated 12 th

June, 2015. The Planning Department vide its letter dated 22 nd August, 2017 decided

that as necessary provision is made in DCPR, there is no necessity to change the

records.

3.12 The Petitioner, by its letter dated 20th February, 2018 requested the

Respondent No.1 to notify in the ofcial gazette that reservation of bus terminus on

the said plot site No.321 under Final Development Plan, 1993 and reservation for the

bus stand on the said plot under Revised Development Plan, 2017 as site No. 231

stands lapsed, with efect from 29th September, 2014. The Petitioner has also recorded

in the said letter that in case the Respondent No.1 failed to issue the said notification

within 30 days of receipt of the letter then the Petitioner would be constrained to file

appropriate proceedings in the court of law.

3.13 The Respondent No.1 vide its letter dated 16 th March, 2018 called for the report

in respect of the reservation of the said plot from the Director, Town Planning,

Municipal Commissioner, Nashik and others. The Respondent No.1 has forwarded a

copy of the said letter to the Petitioner for information and record. However, despite

the Petitioner’s request, the Respondent has failed to issue the said notification in the

Ofcial Gazette which they were bound under Section 127(2) of the MRTP Act read

with regulation 14(2) of DCPR.

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::

Nitin 8 / 30 WP-5347-2018-F.doc

3.14 The Petitioner have therefore filed the above Petition seeking reliefs set out in

Paragraph 2 above.

4. The Assistant Director of Town Planning, Nashik has filed her Afdavit-in-

Reply dated 26th June, 2019 on behalf of the Respondent No.1. In the said Afdavit,

the deponent has admitted the fact that as per the Sanctioned Development Plan, the

said plot is shown as part and parcel of final plot No.454 (consisting of S.No.713 and

714) of Sanctioned Town Planning Scheme No.2 Nashik and is reserved as Site

No.321 for “City Bus Terminus”; that the total area of reservation is about 5000

sq.mtrs.; and that the appropriate authority for acquisition and development of the

said reservation was MSRTC. The deponent has also admitted that Regulation

No.14.0(2) of DC PR for Nashik Municipal Corporation provides that if the

reservation in the earlier Sanctioned Development Plan has lapsed in pursuance of

notice under Section 127 (1) of the MRTP Act, then the corresponding reservation

shall stand lapsed in the Revised Development Plan to the extent of area covered in the

said notice and that the Municipal Commissioner shall take decision on such matters.

The deponent has also admitted in her Afdavit that it seems from the letter dated 20 th

February, 2018 (Exhibit “H” of the Writ Petition) relied upon by the Petitioner that a

request was made by the Petitioner to the Principal Secretary, Urban Development

Department, Government of Maharashtra to issue a notification in the ofcial gazette

under Section 127(2) of the said Act notifying that the said reservation of bus

stand/terminus from the previous Development Plan and revised sanctioned

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 9 / 30 WP-5347-2018-F.doc

Development Plan has lapsed. The Government has thereupon vide its letter dated

16th March, 2018 called for a report from the concerned ofce. In her Afdavit filed on

behalf of Respondent No. 1, the deponent has not commented on any of the averments

concerning the Nashik Municipal Corporation and/or MSRTC. The deponent has

submitted that after considering the say of the Nashik Municipal Corporation and / or

MSRTC, the Court may pass suitable orders as may deem fit and proper.

5. Mr. Suresh Devram Nikumbhe has also filed an Afdavit-in-Reply dated 9 th

July, 2019 on behalf of Respondent No.2 – Municipal Corporation of Nashik, stating

that an area of about 5000 sq. mtrs. out of survey Nos.713 and 714, F.P. No.454-TPS II

Nashik was reserved for City Bus Terminus in the sanctioned Development Plan of

1993 as Site No. 321 ; that a purported notice was issued under Section 127 (1) of the

MRTP Act by the Petitioner on 30th September, 2013. However, at that time, since the

appropriate authority for acquisition was MSRTC, the Corporation was not required

to take steps for acquisition ; that the Petitioner has after issuing notice not taken any

steps and the revised draft Development Plan of Nashik dated 21 st May, 2015 was

published in the Maharashtra Government Gazette dated 04-10 June 2015 by which

suggestions/objections were invited from General Public ; that the Petitioner

thereafter by letter dated 12th June, 2015 made a request to remove the S.T.

Reservation from the proposed Development Plan ; that the objections were

considered by the planning committee and it was of the opinion not to change the

reservation ; that the land under reservation is urgently required by the Corporation ;

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::

Nitin 10 / 30 WP-5347-2018-F.doc

that the notice purported to be under Section 127 of the MRTP Act cannot be

construed to be a purchase notice ; that the purported purchase notice sent to the

Divisional Controller, MSRTC, Nashik is not valid, as the same was required to be

sent to the appropriate authority and the appropriate authority in that behalf is the

Managing Director, MSRTC, Mumbai Central ; that the Writ Petition is liable to be

rejected on that ground and also on the ground of delay and laches.

6. Mr. Swapnil Rajendra Pawar has filed an Afdavit-in-Reply on behalf of

Respondent No.4, wherein no objection whatsoever is raised qua the notice dated 30 th

September, 2013 issued under Section 127(1) of the MRTP Act. The main objection

raised in the Afdavit of MSRTC is that there is inordinate delay on the part of the

Applicant in approaching the Court based on the said notice. It is also stated in the

said Afdavit that the planning committee has taken a decision that there is no need to

change the proposed reservation as the Development Control and Promotional

Regulations provides for the same and that the same is apparent from Exhibit “G” of

the Petition. It is admitted in the Afdavit that vide letter dated 16 th March, 2018, the

Urban Development Department asked the Director of Town Planning, State of

Maharashtra and others to file the detailed report in respect of the objection raised by

the Petitioner, however, the deponent is not aware whether report is filed by the

Director of Town Planning.

7. The Petitioner has filed an Afdavit-in-Rejoinder dated 16 th July, 2019, wherein

they have stated that Section 136 of MRTP Act inter-alia provides that the notice

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 11 / 30 WP-5347-2018-F.doc

required to be served under MRTP Act or its rule, regulations on Corporation shall be

deemed to be validly served if the same is served on the principal ofcer of such

Corporation. It is submitted that the Divisional Controller of Respondent No.4, by

virtue of the ofce which he holds signs and verifies the pleadings on behalf of

Respondent No.4 in legal proceedings which is evident from the list of Writ Petitions

filed/defended by the Divisional Controller on behalf of Respondent No.4 in various

High Courts, particulars of which are set out in paragraph 9 of the Afdavit-in-

Rejoinder. It is also averred in the Afdavit-in-Rejoinder that Order 29 Rule 1 of Code

of Civil Procedure inter-alia provides that in a suit by or against Corporation,

pleadings on behalf of Corporation can be signed and verified by its principal ofcer

and it is clear from the aforesaid that the Divisional Controller is the principal ofcer

of Respondent No.4. It is therefore submitted that the notice is deemed to be duly

served on Respondent no.4 under Section 127 (1) of the MRTP Act. It is also pointed

out in the Afdavit in Rejoinder that the Respondent No.4 – MSRTC has not raised

any dispute regarding the validity of the purchase notice served on them by the

Petitioner and the objection sought to be raised in regard thereto by the Respondent

Nos.2 and 3 is without any substance and is liable to be rejected.

8. Dr. Virendra Tulzapurkar, learned Senior Advocate appearing for the Petitioner

took us through the facts in the Petition which are already set out in Paragraph 3

above. He pointed out that the development plan under which the said plot belonging

to the Petitioner was reserved as site No. 321 for City Bus Terminus was sanctioned on

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 12 / 30 WP-5347-2018-F.doc

28th June, 1993 and was subsequently modified and sanctioned on 19 th February, 1996.

Since the said plot was not acquired within 10 years from the date on which the final

development plan came into force, the Petitioner served statutory notice dated 30 th

September, 2013 under Section 127 (1) of the MRTP Act to the Municipal

Corporation, Nashik-Respondent No.2 and also to MSRTC-Respondent No.4. The

Respondent No.2 admittedly failed to acquire the said plot within the statutory period

of 12 months (which period prior to the amendment of 2009 was 6 months) In the

circumstances, as provided in Section 127 of the MRTP Act, the reservation of the

said plot deemed to have lapsed and the land stood released from reservation and

became available to the owners / Petitioners for the purpose of development.

However, Respondent No. 1 failed to comply with the mandate provided in Sub

Section (2) of Section 127 of the MRTP Act i.e. issuing a notification in the ofcial

gazette notifying the lapsing of reservation of the said plot.

9. Mr.Tulzapurkar submitted that the Petitioner was therefore constrained to

address a letter dated 12th June, 2015 to Respondent No.2 reiterating that the

reservation for the bus terminus on the said plot made in Development Plan, 1993 as

site No.321 has lapsed and requested the Respondent No.2 to take necessary steps to

remove reservation on the said plot from its record as well as from the proposed

Development Plan in future. In response to the Petitioner’s said letter, the

Respondent No.1 addressed a letter dated 21 st August, 2015 and asked the Petitioner to

remain present with necessary documents before the Planning Committee of

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 13 / 30 WP-5347-2018-F.doc

Respondent No.1 on 4th September, 2015 at 3.00 p.m. Accordingly, the Petitioner

remained present before the Planning Committee on 4 th September, 2015 and

submitted necessary documents. However, for almost two years, no such decision was

taken by the Planning Committee of Respondent No.1 and when the matter regarding

Petitioner’s request to de-reserve the said plot in Government records was pending

before the Planning Committee, the Revised Development Plan of Nashik came into

force in 2017. The Respondent No.1 gave its sanction to the said plan vide

TPS-116/CR-140(A)/2016/UD-9 dated 9th January, 2017 and the reservation for the

bus stand on the said plot continued as site No.231. Dr.Tulzapurkar submitted that

since reservation No.321 on the said plot made for city bus terminus under final

Development Plan of 1993 already stood lapsed under Section 127(1) of the MRTP

Act, the reservation site No.231 on the said plot made for bus stand under revised

Development Plan of 2017 stood lapsed. The same also stood lapsed by virtue of

Regulation 14 (2) to the DC PR.

10. According to Dr. Tulzapurkar, the Petitioner by its letter dated 20 th February,

2018 requested the Respondent No.1 to notify in the Ofcial Gazette that reservation

of bus terminus on the said plot having site No.321 under final Development Plan,

1993 and reservation for bus stand on the said plot as site No.231 under revised

Development Plan, 2017 stands lapsed with efect from 29 th September, 2014, but the

Respondent No.1 failed to issue a notification to that efect. Dr. Tulzapurkar therefore

submitted that the above Writ Petition ought to be allowed as prayed. In support of his

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 14 / 30 WP-5347-2018-F.doc

submissions, Dr. Tulzapurkar relied on the decisions of the Supreme Court in the case

of SectionPrafulla C. Dave and Ors. v. Municipal Commissioner and Ors. 1, SectionBhavnagar

University v. Palitana Sugar Mill (P) Limited Ors. 2 and Girnar Traders V/s. State

of Maharashtra and Ors.3.

11. The Learned Advocate appearing for the State of Maharashtra/Respondent

No.1 referred to the Afdavit dated 26th June, 2019 filed by the Assistant Director of

Town Planning, Nashik and submitted that the Writ Petition specifically relates to

Municipal Corporation of Nashik / Respondent Nos.2 and MSRTC/ Respondent

No.4. This Court may therefore pass suitable orders considering the say of

Respondent Nos. 2 to 4 and as may deem fit and proper.

12. The Learned Advocate appearing for Respondent No.2-Municipal Corporation

of Nashik submitted that a company by the name of ‘Nashik Mahanagar Parivahan

Mahamandal Ltd.’ is incorporated under the SectionCompanies Act for providing bus

services in the City, pursuant to the resolution made by the general body of the

Corporation on 19th September, 2018. He submitted that therefore, the Corporation

requires the said land for providing bus services in diferent areas within its limits. The

Learned Advocate appearing for the Corporation also submitted that the notice served

on the Divisional Controller, MSRTC, Nashik is not valid since the same was required

to be sent to the appropriate authority and the appropriate authority in that behalf is

1 (2015) 11 Supreme Court Cases 90
2 (2003) 2 Supreme Court Cases 111
3 (2007) 7 Supreme Court Cases 555

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 15 / 30 WP-5347-2018-F.doc

the Managing Director, MSRTC, Mumbai Central. He submitted that the Divisional

Controller is not the appropriate authority and on this ground the Writ Petition be

rejected. The learned Advocate for the Corporation relied on Section 15 of the

MSRTC Act of 1950, which provides that the Managing Director of the MSRTC shall

be the executive head of the Corporation and all other ofcers and employees of the

Corporation shall be subordinate to him. He also relied on the decision of the Division

Bench of this Court in the case of SectionC.V. Shah A.V. Bhat v. State of Maharashtra 4 and

the decision in case of Shrikant s/o Uttamrao Bhutekar and others v. State of

Maharashtra and others 5.

13. The Learned Advocate appearing for Respondent No.4 submitted that though

notice under Section 127(1) of the MRTP Act was served on MSRTC on 30 th

September, 2013, the Writ Petition is filed only in April 2018. He submitted that since

there is inordinate delay in approaching this Court, the Petitioners are guilty of delay

and latches and therefore, not entitled to any reliefs.

14. In rejoinder, Dr. Tulzapurkar relied on Afdavit-in-Rejoinder dated 16 th July,

2019 filed by the Petitioner and pointed out that it is not the case of MSRTC that the

notice served on them is not valid. However, it is the Municipal Corporation of

Nashik who has alleged that the notice under Section 127(1) of MRTP Act is not valid

since the same was served on the Divisional Controller of MSRTC and not the

Managing Director who is not the appropriate authority. Dr. Tulzapurkar has given

4 2006 (3) Bom.C.R. 216
5 (2009) 2 Mah LJ 673 : (2008) 110 (9) Bom LR 3360 : (2009) 1 AIR Bom R 561

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 16 / 30 WP-5347-2018-F.doc

particulars of several Writ Petitions filed by the Divisional Controller of MSRTC as a

principal ofcer of MSRTC and pointed out that the submissions raised by the

Advocate for the Municipal Corporation of Nashik is baseless and untenable. Dr.

Tulzapurkar also submitted that in any event since the Divisional Controller, MSRTC,

Nashik on behalf of Respondent No.4 was responsible for and concerned with the

acquisition of the Petitioner’s land which was reserved as site No.321 under

Development Plan, 1993, the Divisional Controller, Nashik, on behalf of Respondent

No.4 was responsible for and concerned with the acquisition of the Petitioner’s land

which was reserved as site No.321 under Development Plan, 1993. Dr.Tulzapurkar

submitted that in view of the chronology of events set out in the Petition and pointed

out by him in his oral submissions, there is no delay whatsoever on the part of the

Petitioner in approaching this Court.

15. We have perused the above Writ Petition as well as the Afdavits filed by

the parties. We have considered the facts of the present case, the submissions made

by the learned Advocates for the parties and the case law relied upon by them.

16. Chapter VII of the MRTP Act deals with “Land Acquisition”. Section

125 of the MRTP Act deals with “Compulsory acquisition of land needed for purpose

of regional plan, development plan or town planning etc.” Section 126 of the MRTP

Act deals with “Acquisition of land required for public purposes specified in plans.”

Section 127 of the MRTP Act pertains to “Lapsing of reservations”. Section 127 of

the MRTP Act is relevant for deciding the issues raised in the present Writ Petition

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 17 / 30 WP-5347-2018-F.doc

and is therefore reproduced hereunder :

“127. Lapsing of reservations
[(1) If any land reserved, allotted or designated for any purpose
specifed in any plan under this Act is not acquired by agreement
within ten years from the date on which a fnal Regional plan,
or fnal Development Plan comes into force [or if a declaration
under sub-section (2) or (4) of section 126 is not published in the
Ofcial Gazette within such period, the owner or any person
interested in the land may serve notice, alongwith the
documents showing his title or interest in the said land, on the
Planning Authority, the Development Authority or, as the case
may be, the Appropriate Authority to that efectt and if within
twelve months] from the date of the service of such notice, the
land is not acquired or no steps as aforesaid are commenced for
its acquisition, the reservation, allotment or designation shall be
deemed to have lapsed, and thereupon, the land shall be deemed
to be released from such reservation, allotment or designation
and shall become available to the owner for the purpose of
development as otherwise, permissible in the case of adjacent
land under the relevant plan.

[(2) On lapsing of reservation, allocation or designation of any
land under sub-section (1), the Government shall notify the
same, by an order published in the Ofcial Gazette.]”

Section 127 of the MRTP Act therefore, sets out the circumstances in which the land

reserved in the Regional or Development Plan would lapse. It prescribes a period of

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 18 / 30 WP-5347-2018-F.doc

ten years within which acquisition of the land reserved, allotted or designated, has to

be completed by agreement from the date on which a final regional plan or a final

development plan comes into force, or the proceedings for acquisition of such land

under the MRTP Act or under the SectionLand Acquisition Act are commenced. If the said

procedure prescribed is not completed within a period of ten years i.e. no steps are

taken as prescribed, the owner is entitled to issue a notice on the planning authority,

development authority or appropriate authority informing them that they have not

taken any steps within ten years and if no steps are taken within a period of twelve

months from the date of receipt of the such notice by the concerned authorities, the

reservation allotment or designation shall deemed to have lapsed and consequently

the land shall be deemed to be released from the reservation, allotment or designation

and shall become available to the owner for the purpose of development. Upon lapsing

of reservation, allocation or designation of any land, under Sub Section (1) of Section

127 of the MRTP Act, the Government shall as provided in sub-Section (2) of Section

127, notify the said lapsing by an order published in the ofcial gazette.

17. Section 38 of the MRTP Act deals with the revision of a final

development plan, already in operation. Such revision is contemplated on the expiry

of 20 years from the date of coming into operation of a development plan.

18. In the case of Girnar Traders (supra), it is explained that the underlying

principle envisaged in Section 127 of the MRTP Act is either to utilize the land for the

purpose it is reserved in the plan in a given time or let the owner utilize the land for

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 19 / 30 WP-5347-2018-F.doc

the purpose it is permissible under the town planning scheme. However, it is trite law

that Section 127 of the MRTP Act or any other provision of the said Act, does not

provide for automatic lapsing of acquisition, reservation and allotment or designation

of land included in development plan on expiry of 10 years. In case of Prafulla C.

Dave and Ors. (supra), the Supreme Court relying on its earlier decision in the case of

Bhavnagar University (supra) has held that Section 127 of the Act or any other

provisions of the Act, does not provide for automatic lapsing of the acquisition,

reservation or designation of the land included in any development plan on the expiry

of ten years. In fact, upon expiry of the said period of ten years, the land owner or the

person interested is mandated by the Statute to take certain positive steps i.e. to

issue / serve a notice and there must occur a corresponding failure on the part of the

authority to take requisite steps as demanded therein in order to bring into efect the

consequences contemplated by Section 127. It is further held that if the land owner or

the person interested remains silent and in the meantime a revised plan under Section

38 of the Act comes into efect, obviously, the period of 10 years under Section 127 of

MRTP Act has to get a fresh lease of life of another ten years. This position is clearly

explained in paragraphs 21 and 22 of the said decision and the same are reproduced

hereunder :

“21. ……. Section 127 of the MRTP Act or any other provision
of the said Act does not provide for automatic lapsing of the
acquisition, reservation or designation of the land included in

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 20 / 30 WP-5347-2018-F.doc

any development plan on the expiry of ten years. On the
contrary, upon expiry of the said period of ten years, the
landowner or the person interested is mandated by the Statute to
take certain positive steps i.e. to issue / serve a notice and there
must occur a corresponding failure on the part of the authority to
take requisite steps as demanded therein in order to bring into
efect the consequences contemplated by Section 127. What
would happen in a situation where the landowner or the person
interested remains silent and in the meantime a revised plan
under Section 38 comes into efect is not very difcult to fathom.
Obviously, the period of ten years under Section 127 has to get a
fresh lease of life of another ten years. To deny such a result
would amount to putting a halt on the operation of Section 38
and rendering the entire of the provisions with regard to
preparation and publication of the revised plan otiose and
nugatory. To hold that inactivity on the part of the authority i.e.
failure to acquire the land for ten years would automatically
have the efect of the reservation, etc. lapsing would be contrary
to the clearly evident legislative intent. In this regard, it cannot
be overlooked that under Section 38 a revised plan is to be
prepared on the expiry of a period of 20 years from the date of
coming into force of the approved plan under Section 31 whereas
Section 127 contemplates a period of 10 years with efect from the
same date for the consequences provided for therein to take efect.
The Statute, therefore, contemplates the continuance of a
reservation made for a public purpose in a fnal development
plan beyond a period of ten years. Such continuance would get

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 21 / 30 WP-5347-2018-F.doc

interdicted only upon happening of the events contemplated by
Section 127 i.e. giving / service of notice by the landowner to the
authority to acquire the land and the failure of the authority to
so act. It is, therefore, clear that the lapsing of the reservation,
allotment or designation under Section 127 can happen only on
the happening of the contingencies mentioned in the said section.
If the landowner or the person interested himself remains
inactive, the provisions of the Act dealing with preparation of
revised plan under Section 38 will have full play. Action on the
part of the landowner or the person interested as required under
Section 127 must be anterior in point of time to the preparation
of the revised plan. Delayed action on the part of the landowner,
that is, after the revised plan has been fnalised and published
will not invalidate the reservation, allotment or designation that
may have been made or continued in the revised plan. This
according to us, would be the correct position in law which has, in
fact, been clarifed in SectionMuncipal Corpn. Of Greater Bombay v.
Hakimwadi Tenants’s Assn. 6 in the following terms : (SCC p.
62, para 10)
“10…… If there is no such notice by the owner or any person,
there is no question of the reservation, allotment or designation
of the land under a development plan of having lapsed. It a
fortiori follows that in the absence of a valid notice under Section
127, there is no question of the land becoming available to the
owner for the purpose of development or otherwise.”

22. In fact the views expressed in Bhavnagar University in para
34 to the same efect : (SCC p. 123)
6 1988 Supp SCC 55

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 22 / 30 WP-5347-2018-F.doc

“34….. The relevant provisions of the Act are absolutely clear,
unambiguous and implicit. A plain meaning of the said
provisions, in our considered view, would lead to only conclusion,
namely, that in the event a notice is issued by the owner of the
land or other person interested therein asking the authority to
acquire the land upon expiry of the period specifed therein viz.
ten years from the date of issuance of fnal development plan and
in the event pursuant to or in furtherance thereof no action for
acquisition thereof is taken, the designation shall lapse.”

19. In the backdrop of the aforestated law laid down by the Supreme Court,

let us consider its applicability to the facts of the present case. Admittedly, the

Petitioner is the owner and in possession of the said plot. The said plot admeasuring

5000 sq. mtrs. was reserved for city bus terminus in the sanctioned development plan

of Nashik, 1993 as site No.321 The said plot was reserved for the benefit of

Respondent No.4 – MSRTC (the Acquiring Authority). The said Development Plan

was sanctioned by the Respondent No.1 vide No.TPS 1191/35(A) CR-88/UD-9 dated

28th June, 1993. The Final Development Plan, 1993 was subsequently modified and

sanction thereto was given by the Respondent No.1 vide TPS 1193/2124/CR-126/95/

UD-9 dated 19th February, 1996. The Respondent No.2 – Municipal Corporation of

Nashik neither acquired the said plot nor took any steps for acquisition of the said plot

within 10 years from the date on which the Final Development Plan became operative.

In view thereof, the Petitioner served a notice dated 30 th September, 2013 as

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 23 / 30 WP-5347-2018-F.doc

contemplated under Section 127(1) of the MRTP Act on Respondent No.3 –

Municipal Commissioner of Nashik and the Divisional Controller of Respondent No.4

– MSRTC.

20. The Petitioners have clearly stated in the said Notice that the

Reservation No.321 for City Bus Terminus made in the Nashik Development Plan,

sanctioned by the Urban Development Department vide No.TPS-1191/35(A) CR-88/

UD-9 dated 28th June, 1993 and subsequently modified and sanctioned by Respondent

No. 1 vide No.TPS-1193/2124/CR-126/95/UD-9 dated 19th February, 1996 has lapsed

since no acquisition proceedings have been initiated within the stipulated period of 10

years as per the provisions of the MRTP Act; that the society urgently needs the said

reserved land for the development and expansion of its charitable and educational

activities; that with the serving of the notice, the Petitioners are initiating the process

of getting the said land dereserved and making it available to the Petitioner for the

purpose of urgent development and expansion needs; and that the necessary

documents are attached to the said notice. Since the Respondents failed to acquire the

said land or to commence any steps for its acquisition within a period of 12 months or

from the date of service/receipt of the said notice dated 30 th September, 2013, the said

reservation in respect of the said plot lapsed and the land stood released from such

reservation and became available to the owner for the purpose of development as

provided in Section 127 of the MRTP Act. Respondent No. 1 was thereupon bound to

notify the lapsing of the said reservation by an order published in the ofcial gazette.

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::

Nitin 24 / 30 WP-5347-2018-F.doc

21. No notification was published in the ofcial gazette under Section 127(2)

of the MRTP Act, notifying that the reservation for bus terminus made on the said

plot in the Final Development Plan, 1993 as site No.321 had lapsed under Section

127(1) of the MRTP Act.

22. Since the Respondent No.1 failed to follow the mandate prescribed in

Sub Clause 2 of Section 127 of the MRTP Act, the Petitioner addressed a letter dated

12th June, 2015 to the Respondent No.2 – Municipal Corporation of Nashik, whereby

after referring to the notice dated 30th September, 2013 addressed by the Petitioner to

the Respondent No.2 under Section 127(1) of the MRTP Act, the Respondent No.2

requested the Petitioner to take necessary steps to remove the reservation on the said

plot from its record as well as the proposed Development Plan in future.

23. The learned Advocate in his oral submission made on behalf of Nashik

Municipal Corporation/Respondent No. 2 has stated that the revised draft

Development Plan of Nashik dated 21st May, 2015 was published in the Maharashtra

Government Gazette dated 04-10 June 2015 by which suggestions/objections were

invited from General Public and the Petitioner thereafter by letter dated 12 th June,

2015 made a request to remove the S.T. Reservation from the proposed Development

Plan and that the objections were considered by the planning committee and it was of

the opinion not to change the reservation since the land under reservation is urgently

required by the Corporation. This submission lends no assistance to the Respondent

No.2 since the said notice under Section 127(1) was issued by the Petitioner to the

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 25 / 30 WP-5347-2018-F.doc

Respondents on 30th September, 2013 i.e. much prior to the publication of the draft

revised development plan of Nashik dated 21st May, 2015 and further since the

Respondents failed to act on the said notice for a period of one year/twelve months

thereafter, the reservation lapsed on and from 29 th September, 2014 and the land stood

released from reservation and became available to the Petitioner for development in

the manner set out in Section 127 of the MRTP Act. In fact, Respondent No. 1 has in

its Afdavit dated 26th June, 2019 reproduced Regulation No. 14.0 (2) of the

sanctioned Development Control and Promotion Regulations for Nashik Municipal

Corporation, which form part of the Revised Development Plan, 2017. The same reads

thus :

“14.0(2) – Reservations lapsed under 127 of the Act. – If the
reservation in the earlier Sanctioned Development Plan is lapsed
in pursuance of notice under Section 127 of the Maharashtra
Regional and Town Planning Act, 1966, then the corresponding
reservation shall stand lapsed in this Revised Development Plan
to the extent of area covered in the said notice. The Municipal
Commissioner shall take decision on such matters.”

Therefore, in our view after the reservation of the bus terminus made on the said plot

in the Final Development Plan, 1993 as site No. 321, having lapsed on and from 29 th

September, 2014, the Respondents cannot again reserve the said plot in the draft

revised Development Plan of Nashik dated 21st May, 2015. The Respondents who

have failed to comply with the mandate provided in Sub Clause (2) of Section 127 of

the MRTP Act, cannot be allowed to take advantage of its own wrong and blame the

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 26 / 30 WP-5347-2018-F.doc

Petitioner for the delay when in fact the delay lies squarely at the doors of the

Respondents.

24. We are therefore left to answer the main contention of the Respondent

No. 3 Corporation that the purchase notice dated 30 th September, 2013 is not a valid

notice since the same is addressed to the Divisional Controller of Respondent No.4 –

MSRTC, Nashik. As noted earlier, MSRTC which is the acquiring authority has at no

stage in the past or even in their Afdavit or in their submissions before us contended

that the notice served on its Divisional Controller under Section 127 of the MRTP Act

is not valid or that the notice ought not to have been served on Divisional Controller of

Respondent No.4 – MSRTC but ought to have been served on the Managing Director

of MSRTC. The only submission made by the MSRTC before this Court is that the

Petition be dismissed since the Petitioner has approached the Court much after the

service of notice dated 30th September, 2013 on MSRTC. The Planning Authority /

Nashik Municipal Corporation has no grievance qua the notice served on them under

Section 127 of the MRTP Act, but have raised objection on the ground that the notice

ought not to have been served on the Divisional Controller of the Acquiring

Authority / MSRTC, who interestingly have not raised any objection qua the notice

served on them. In fact, even in the decision in the case of C.V.Shah A.V. Bhat

(supra) relied upon by the Municipal Corporation Nashik, the Division Bench of this

Court in paragraph 24 of its Judgment has clearly held as under :

“24. In the reply afdavits fled by the Pune Municipal

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 27 / 30 WP-5347-2018-F.doc

Corporation, no objection has been raised about the legality and
validity of the purchase notice. As a matter of fact, the Pune
Municipal Corporation considered the aforesaid notices as legal
and valid notices under Section 127 of the MRTP Act and
rejected them on the ground that the said notices do not require to
be acted upon as the process for acquisition had already begun
much before the said notices were served”.

25. In any event, as pointed out by Dr.Tulzapurkar the Petitioner has in its

Afdavit in Rejoinder provided particulars of several Writ Petitions filed by the

Divisional Controller of MSRTC, in his capacity as a principal ofcer of MSRTC.

Section 136 of the MRTP Act pertains to service of notice. Sub – clause (a) of Clause

(1) of Section 136 is reproduced hereunder :

“136. Service of notice, etc.
(1) All documents including notices and orders required by this
Act or any rule or regulation made thereunder to be served upon
any person shall save as otherwise provided in this Act or rule or
regulation, be deemed to be duly served –

(a) Where the document is to be served on a Government
department, railway, local authority, statutory authority,
company, corporation, society or other body, if the document is
addressed to the head of the Government department, General
Manager of the Railway, Secretary or Principal Ofcer of the
local authority, company, corporation, society or any other body
at its authority, principal, branch, local or registered ofce, as the

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 28 / 30 WP-5347-2018-F.doc

case may be, and is either –

(i) sent by registered post to such ofce t or

(ii) delivered at such ofce.”

The MSRTC has not disputed the contents of the said Afdavit in Rejoinder. Even

during the oral arguments, it is not submitted by MSRTC that its Divisional

Controller is not its Principal Ofcer. The decision of this Court in the case of

Shrikant S/o. Uttamrao Bhutekar and Others (supra) lends no assistance to the

submission of Respondent No. 3 Corporation qua the service of the notice under

Section 127 of the MRTP Act not being valid, since in that case the Nagar Parishad

had in its Afdavit specifically averred that the notice had not been received by them,

and the said avernment was not controverted by the Petitioners by filing any

Rejoinder.

26. We are therefore of the considered view that the notice issued by the

Petitioner to MSRTC under Section 127 of the MRTP Act, is valid and the

submissions made by the Corporation in that regard are rejected.

27. Before we part with the order, we would like to record that though not

contended / submitted by any of the Respondents, we inquired from Dr.Tulzapurkar

whether it is mandatory for the owner of the land or any person interested therein, to

call upon the government to acquire the land reserved in the notice issued under

Section 127 (1) of the MRTP Act. This question was asked since in paragraph 34 of

the decision of the Supreme Court in Bhavnagar University (supra), we noted the

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 29 / 30 WP-5347-2018-F.doc

statement that in the event notice is issued by the owner or other person interested

therein, asking the authority to acquire the land upon expiry of the period specified

therein viz. ten years from the date of issuance of final development plan and in the

event pursuant to or in furtherance thereof no action for acquisition thereof is taken,

the designation shall lapse. Paragraph 34 of the said decision is reproduced

hereunder :

“34. The relevant provisions of the Act are absolutely clear,
unambiguous and implicit. A plain meaning of the said
provisions, in our considered view, would lead to only one
conclusion, namely, that in the event a notice is issued by the
owner of the land or other person interested therein asking the
authority to acquire the land upon expiry of the period specifed
therein viz. ten years from the date of issuance of fnal
development plan and in the event pursuant to or in furtherance
thereof no action for acquisition thereof is taken, the designation
shall lapse.”

28. Dr. Tulzapurkar relied on the decision of the Supreme Court in the case

of Girnar Traders (supra) pointing out that in paragraph 31 of the majority decision, it

is recorded that “…….The six-month period shall commence from the date the owner or

any person interested in the land serves a notice on the planning authority, development

authority or appropriate authority expressing his intent claiming dereservation of the

land……”. Dr.Tulzapurkar has submitted that therefore the said statements of the

Supreme Court are general / passing statements and is not the law laid down /

proclaimed by the Supreme Court. Dr.Tulzapurkar has further submitted that in fact

::: Uploaded on – 10/10/2019 11/10/2019 02:30:11 :::
Nitin 30 / 30 WP-5347-2018-F.doc

in the said decision, the Supreme Court has clearly recorded that there is no

prescribed format qua the contents of the notice set out in Section 127 of the Act.

Dr.Tulzapurkar has relied on the decision of the Division Bench of this Court in case

of M/s.Jaika Vanijya Limited Anr. v. The State of Maharashtra Ors. 7, wherein it

is expressly recorded that the owner is not required by Section 127 of the MRTP Act

to call upon the authority to take steps to acquire the land within stipulated period and

in fact the authority on which the notice is served, is aware of the obligations cast upon

it by the said Section.

29. For all the above reasons, we hold as follows :

i. The notice issued by the Petitioner under Section 127 of the MRTP Act, dated
30th September, 2013 is a valid notice.

ii. Upon expiry of the period of twelve months from the date of issuance of notice
dated 30th September, 2013, the reservation in respect of the plot of land belonging to
the Petitioner, has lapsed.

iii. Action on the part of the Respondents to show the said plot of the Petitioner as
reserved in its Revised Development Plan, Nashik, which has come in force vide TPS-
116/CR-140(A) /2016/UD-9 dated 9th January, 2017 / final development plan, is void
and illegal and also stands lapsed.

30. The Writ Petition is therefore disposed of in terms of prayer Clause (a).

( S.J. KATHAWALLA, J. )                                      ( AKIL KURESHI, J. )

7 2014 (1) ALL MR 136

::: Uploaded on - 10/10/2019 11/10/2019 02:30:11 :::

Leave a Reply

Your email address will not be published. Required fields are marked *


Not found ...? HOW TO WIN 498a, DV, DIVORCE; Search in Above link
MyNation Times Magzine


All Law documents and Judgment copies
Laws and Bare Acts of India
Landmark SC/HC Judgements
Rules and Regulations of India.

Recent Comments

STUDY REPORTS

Copyright © 2024 SC and HC Judgments Online at MyNation
×

Free Legal Help, Just WhatsApp Away

MyNation HELP line

We are Not Lawyers, but No Lawyer will give you Advice like We do

Please read Group Rules – CLICK HERE, If You agree then Please Register CLICK HERE and after registration  JOIN WELCOME GROUP HERE

We handle Women Centric biased laws like False Sectioin 498A IPC, Domestic Violence(DV ACT), Divorce, Maintenance, Alimony, Child Custody, HMA 24, 125 CrPc, 307, 312, 313, 323, 354, 376, 377, 406, 420, 497, 506, 509; TEP, RTI and many more…

MyNation FoundationMyNation FoundationMyNation Foundation