SC and HC Judgments Online at MyNation

Judgments of Supreme Court of India and High Courts

Chief General Manager (IPC) Madhya Pradesh Power Trading Co. Ltd. Vs. Narmada Equipments Pvt. Ltd. [23/03/2021]

Tweet

Chief General Manager (IPC) Madhya Pradesh Power Trading Co. Ltd. Anr. Vs. Narmada Equipments Pvt. Ltd.

[Civil Appeal No. 1051 of 2021 arising out of S.L.P. (C) No. 5750 of 2017]

Dr Dhananjaya Y Chandrachud, J

1 Leave granted.

2 This appeal arises from a judgment and order of a learned Single Judge of the High Court of Madhya Pradesh dated 30 November 2016 where it appointed an Arbitrator in the dispute between the parties, in an application1 filed by the respondent under Section 11(6) of the Arbitration and Conciliation Act 19962.

3 The genesis of the matter is from when the Madhya Pradesh Electricity Board3, entered into a Power Purchase Agreement4 on 20 May 1999 with the respondent. Under the PPA, the respondent was to establish a mini hydro-electric project on a built and operate basis. However, the PPA was terminated on 27 September 2001 by the Board. The respondent initially filed a writ petition challenging the termination of the PPA. The High Court, by its order dated 4 November 2009, declined to entertain the petition in view of an arbitration agreement contained in Clause 12.3 of the PPA. Thereafter, the respondent filed a review petition7which was dismissed by the High Court by an order dated 10 December 2009.

4 As a consequence of the orders dated 4 November 2009 and 10 December 2009, on 28 December 2009, the respondent issued a notice to the Board under Clause 12.1 of the PPA, seeking to resolve the dispute by mutual discussion. Since the respondent did not receive a reply to the notice dated 28 December 2009 from the Board, on 30 May 2011, the respondent issued another notice to the Board invoking arbitration under Clause 12.3 of the PPA. In the notice, the respondent stated that if the Board did not act upon the notice within 30 days of its receipt, it would approach the High Court under Section 11(6) of the 1996 Act.

5 Having received no reply from the Board, an application8 was filed under Section 11(6) of the 1996 Act by the respondent seeking the appointment of an arbitrator. The High Court, by its order dated 21 January 2014, recorded that the respondentand the appellant had agreed to nominate their arbitrators, and observed that the two arbitrators would proceed to appoint a third arbitrator, in accordance with the procedure in Clause 12.3(a) of the PPA. The nominated Arbitrators fixed their first meeting on 7 May 2014, when both parties appeared and the Arbitrators’ fee was fixed. However, the Arbitrators, by a letter dated 7 July 2014, highlighted their inability to proceed with the arbitration proceedings on the ground that their fees had not been paid.

6 Thereafter, the respondent filed AC No 1 of 2015 on 8 December 2014, seeking the appointment of an arbitrator under Section 11(6) of the 1996 Act. This application was opposed by the appellant on the ground that, in view of the provisions of Section 86(1)(f) of the Electricity Act 20039, it was the State Electricity Commission which was vested with the exclusive jurisdiction to adjudicate upon disputes between licensees and generating companies. By the impugned judgment and order dated 30 November 2016, the Single Judge of the High Court allowed the application filed by the respondent under Section 11(6) of the 1996 Act. The Single Judge held that the remedies under Section 86(1)(f) of the 2003 Act and under Section 11(6) of the 1996 Act are independent of each other, and it was open to the High Court to exercise its jurisdiction under Section 11(6). The appellant now comes before this Court in appeal.

7 The submission of the appellant, which has been urged before this Court by Mr Varun Chopra, learned counsel, is that the view which has been taken by the High Court is contrary to the law which has been laid down by a two-Judge Bench of this Court in Gujarat Urja Vikas Nigam Limited v Essar Power Limited10.

8 Controverting the submissions, Mr Sanjay K Agrawal, learned counsel appearing on behalf of the respondent, however, urged that the decision in Gujarat Urja Vikas Nigam Limited (supra) would not apply to the facts of the present case since the PPA was executed on 20 May 1999 and the termination by the Board was on 27 September 2001; both of these events have taken place before the enforcement of the 2003 Act on 10 June 2003. It was further urged that the appellant did not raise its objection stemming from Section 86(1)(f) of the 2003 Act when the High Court appointed Arbitrators by the consent of both parties in its order dated21 January 2014 in AC No 76 of 2011 and also before the Arbitrators so appointed, and hence it cannot be raised at this stage.

9 In the present case, the notice for the initiation of arbitration under Clause 12.3 of the PPA was issued by the respondent on 30 May 2011. The commencement of the arbitral proceedings by the invocation of the arbitration agreement would, therefore, relate to 30 May 2011, when the notice invoking Clause 12.3 was issued. Hence, the fact that the PPA and the notice of termination predate the 2003 Act would not constitute material circumstances. Section 2111 of the 1996 Act specifies that unless otherwise agreed by the parties, the arbitral proceedings in respect of a particular dispute would commence on the date on which a request for that dispute to be referred to arbitration is received by the respondent. Hence, there can be no manner of doubt that 30 May 2011 would be the material date, since it is on this date that the notice invoking Clause 12.3 was issued by the respondent to the appellant.

10 The first issue which is raised in this appeal is governed by Gujarat Urja Vikas Nigam Limited (supra). In that case, the power purchase agreement between the parties was entered into on 30 May 1996, and the notice for referring the dispute to arbitration was sent by one of the parties on 14 November 2005. The other party opposed the notice by stating that the State Electricity Commission had exclusive jurisdiction in accordance with Section 86(1)(f) of the 2003 Act. The Gujarat High Court thereafter appointed an Arbitrator in an application under Section 11(6) of the 1996 Act, which was impugned before this Court. Speaking for the two-Judge bench, Justice Markandey Katju settled the position of law in paragraphs 26, 27 and 28 of the judgment, which are extracted below for convenience of reference:

“26. It may be noted that Section 86(1)(f) of the Act of 2003 is a special provision for adjudication of disputes between the licensee and the generating companies. Such disputes can be adjudicated upon either by the State Commission or the person or persons to whom it is referred for arbitration. In our opinion the word “and” in Section 86(1)(f) between the words “generating companies” and “to refer any dispute for arbitration” means “or”. It is well settled that sometimes “and” can mean “or” and sometimes “or” can mean “and” (vide G.P. Singh’s Principles of Statutory Interpretation, 9th Edn., 2004, p. 404).

27. In our opinion in Section 86(1)(f) of the Electricity Act, 2003 the word “and” between the words “generating companies” and the words “refer any dispute” means “or”, otherwise it will lead to an anomalous situation because obviously the State Commission cannot both decide a dispute itself and also refer it to some arbitrator. Hence the word “and” in Section 86(1)(f) means “or”.

28. Section 86(1)(f) is a special provision and hence will override the general provision in Section 11 of the Arbitration and Conciliation Act, 1996 for arbitration of disputes between the licensee and generating companies. It is well settled that the special law overrides the general law. Hence, in our opinion, Section 11 of the Arbitration and Conciliation Act, 1996 has no application to the question who can adjudicate/arbitrate disputes between licensees and generating companies, and only Section 86(1)(f) shall apply in such a situation.”

This position has subsequently also been approved by two three-Judge benches of this Court in Hindustan Zinc Limited v Ajmer Vidyut Vitran Nigam Limited12 and NHAI v Sayedabad Tea Company Limited13.

11 From the above judgment, it is evident that this Court has held that Section 86(1)(f) of the 2003 Act is a special provision which overrides the general provisions contained in Section 11 of the 1996 Act. Section 86(1)(f) vests a statutory jurisdiction with the State Electricity Commission to adjudicate upon disputes between licensees and generating companies and to refer any dispute for arbitration. The “and” between “generating companies” and “to refer any dispute for arbitration” is to be read as an “or”, since the State Electricity Commission cannot obviously resolve the dispute itself and also refer it to arbitration. Section 86(1)(f) is extracted below:

“86.Functions of State Commission.- (1) The State Commission shall discharge the following functions, namely:-

*** *** ***

(f) adjudicate upon the disputes between the licensees and generating companies and to refer any dispute for arbitration;”

12 Section 174 of the 2003 Act provides overriding effect to the 2003 Act notwithstanding anything inconsistent contained in any other law for the time being in force or in any instrument having effect by virtue of any law other than the 2003Act itself. Section 174 provides thus:

“174. Act to have overriding effect. – Save as otherwise provided in Section 173, the provisions of this Act shall have effect notwithstanding anything inconsistent therewith contained in any other law for the time being in force or in any instrument having effect by virtue of any law other than this Act.”

13 We refer now to the second argument raised on behalf of the respondent, that the appellant cannot raise an objection relying on Section 86(1)(f) of the 2003 Act in the second application filed by it under Section 11(6) of the 1996 Act, when it had not raised the same objection in the first application under Section 11(6) of the 1996 Act or before the Arbitrators so appointed. It is pertinent to note that this argument was rejected by the Single Judge of the High Court in the impugned judgment and order dated 30 November 2016 in the following terms”

“9. I will be failing in my duty if the basic objection raised by Shri Manoj Dubey about maintainability of this application is not dealt with. Merely because in earlier round of litigation, the objection of maintainability was not taken, it will not preclude the other side to raise such objection if it goes to the root of the matter. This is trite law that jurisdiction cannot be assumed by consent of the parties. If a statute does not provide jurisdiction to entertain an application/petition, the petition cannot be entertained for any reason whatsoever. Thus, I am not inclined to hold that since for the reason that in the earlier round of litigation i.e. A.C. No.76/2011 parties reached to a consensus for appointment of Arbitrators, this application is also maintainable. I deem it proper to examine whether because of operation of Section 174 of the Act of 2003, the present application under the Act of 1996 is not maintainable.”

14 A similar issue was raised before a three-Judge bench of this Court in Hindustan Zinc Limited (supra), where an arbitrator was appointed by the State Electricity Commission under Section 86(1)(f) of the 2003 Act with the consent of the parties. Subsequently, the arbitral award was challenged under Section 34 of the 1996 Act before a Commercial Court, and the Commercial Court’s decision was challenged in an appeal under Section 37 of the 1996 Act where it was held that the State Electricity Commission had no jurisdiction to appoint the arbitrator since Section 86(1)(f) refers to disputes only between licensees and generating companies, and not licensees and consumers.

When the matter reached this Court, the contention was that the objection to jurisdiction could not have been raised in a proceeding under Section 37 of the 1996 Act once the parties had consented to arbitration earlier. Speaking for the Court, Justice Rohinton F Nariman held that if there is inherent lack of jurisdiction, the plea can be taken at any stage and also in collateral proceedings. He highlighted the well-established principle that a decree passed by a court without subject matter jurisdiction is a nullity, and that its invalidity could be set up whenever and wherever it is sought to be enforced or relied upon. Such a defect of jurisdiction cannot be cured even by the consent of the parties. The above dictum would apply to the present case.

15 In the above view of the matter, the order of the High Court appointing an arbitrator under Section 11(6) of the 1996 Act is unsustainable. We accordingly allow the appeal and set aside the impugned judgment and order of the High Court dated 30 November 2016 in AC No 1 of 2015. However, this will not come in the way of the respondent in taking recourse to such remedies as are available in law. However, we have expressed no opinion either on the merits or the objections of the appellant which, when urged, would be considered by the appropriate forum. There shall be no order as to costs.

16 Pending application, if any, stands disposed of.

…………………………………….J. [Dr Dhananjaya Y Chandrachud]

…………………………………….J. [M R Shah]

…………………………………….J. [Sanjiv Khanna]

New Delhi;

March 23, 2021

-S-

1 “AC No 1 of 2015”

2 “1996 Act”

3 “Board”

4 “PPA”

5 “WP No 2642 of 2002”

6 “12.3 Arbitration:

(a) If dispute cannot be salted within Thirty (30)days mutual discussions as (sic) by section 12.1 and (sic) to Conciliation is not elected by the Parties pursuant to Section 12.2 of if a Parties so requests in accordance with Section 12.2 the Dispute shall in dally be settled by an Umpire to be appointed by two arbitrators one to be appointed by the Board and other by the Company Provisions of the Indian Arbitration and Conciliation Act 1996 9or any enactment that replaces the said Act) shall apply in such arbitrator. The arbitration proceedings shall be held at head Quarter of the Board i.e. at Jabalpur.

(b) The award rendered shall apportion the costs of the arbitration.

(c) The award rendered in any arbitration commended here under shall be final conclusive and binding upon the Parties and award may be entered in any Court having jurisdiction as darned under article 15.1.”

7 “Review Petition No 716 of 2009”

8 “AC No 76 of 2011”

9 “2003 Act”

10 (2008) 4 SCC 755, hereinafter referred to as “Gujarat Urja Vikas Nigam Limited”

11 “21. Commencement of arbitral proceedings.-Unless otherwise agreed by the parties, the arbitral proceedings in respect of a particular dispute commence on the date on which a request for that dispute to be referred to arbitration is received by the respondent.”

12 (2019) 17 SCC 82; hereinafter, referred to as “Hindustan Zinc Limited”

13 (2020) 15 SCC 161

 Back

Leave a Reply

Your email address will not be published. Required fields are marked *


Not found ...? HOW TO WIN 498a, DV, DIVORCE; Search in Above link
MyNation Times Magzine


All Law documents and Judgment copies
Laws and Bare Acts of India
Landmark SC/HC Judgements
Rules and Regulations of India.

Recent Comments

STUDY REPORTS

Copyright © 2024 SC and HC Judgments Online at MyNation
×

Free Legal Help, Just WhatsApp Away

MyNation HELP line

We are Not Lawyers, but No Lawyer will give you Advice like We do

Please read Group Rules – CLICK HERE, If You agree then Please Register CLICK HERE and after registration  JOIN WELCOME GROUP HERE

We handle Women Centric biased laws like False Sectioin 498A IPC, Domestic Violence(DV ACT), Divorce, Maintenance, Alimony, Child Custody, HMA 24, 125 CrPc, 307, 312, 313, 323, 354, 376, 377, 406, 420, 497, 506, 509; TEP, RTI and many more…

MyNation FoundationMyNation FoundationMyNation Foundation