SC and HC Judgments Online at MyNation

Judgments of Supreme Court of India and High Courts

Delhi Metro Rail Corporation Ltd. vs Delhi Airport Metro Express … on 15 January, 2019

$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI

+ FAO(OS) (COMM) 58/2018 CM Nos. 13434/2018, 17581/2018
31531/2018

Reserved on : 2nd November 2018
Date of decision: 15th January, 2019

DELHI METRO RAIL CORPORATION LTD. ….. Appellant
Through: Mr. P.S. Narasimha, ASG, Mr. Parag P.
Tripathi Mr. Ajit Kumar Sinha, Sr. Advocates
with Mr. Tarun Johri, Mr. Ankit Saini, Mr.
Srinivasan Ramaswamy Ms. Athira G. Nair,
Advocates.
versus

DELHI AIRPORT METRO EXPRESS PRIVATE LIMITED… Respondent

Through: Mr.P. Chidambaram, Sr. Advocate with
Mr.Rishi Agrawala, Ms. Megha Mehta Agrawal
Mr. Nishant Rao, Advocates.

CORAM:

HON’BLE MR. JUSTICE SANJIV KHANNA
HON’BLE MR. JUSTICE CHANDER SHEKHAR

SANJIV KHANNA, J.:

Delhi Metro Rail Corporation Ltd. (‘DMRC’, for short) in this intra-
Court appeal under Section 37 of the Arbitration and Conciliation Act, 1996
(„A C‟ Act, for short) read with Section 13 of the Commercial Courts,
Commercial Division and Commercial Appellate Division of the High
Courts Act, 2015 has impugned judgment and order dated 6 th March, 2018,
whereby the learned single Judge has dismissed objections under Section 34

FAO(OS)(COMM) No. 58/2018 Page 1 of 97
of the A C Act upholding the award dated 11th May, 2017 passed by the
Arbitral Tribunal.

2. DMRC is a state-owned company with equal participation from the
Government of India and the Government of National Capital Territory of
Delhi.

3. The respondent, Delhi Airport Metro Express Private Limited
(‘DAMEPL’, for short), is a company incorporated as a special purpose
vehicle by the consortium of M/s Reliance Infrastructure Limited and M/s
Construcciones Y Auxiliar de Ferrocarriles SA, Spain („consortium‟, for
short).

4. The consortium were successful bidders in the international
competitive bidding process for construction, operation and maintenance of
the Delhi Airport Metro Express Line („AMEL‟, for short) based on Public-
Private Partnership model for providing high speed metro connectivity with
maximum speed of 120 Kms per hour between New Delhi Railway Station
and Indira Gandhi International Airport, T-3 Terminal with further line till
Section-21 at Dwarka with underground section of 15.7 Kms and elevated
viaduct section of 7 Kms.

5. On 25th August, 2008 Concessionaire Agreement (‘CA’, for short) was
signed and executed between DMRC and DAMEPL.

6. DMRC had undertaken clearances and borne costs relating to
acquisition of land and in construction of all civil structures like tunnels,
viaducts, station buildings except depot buildings.

FAO(OS)(COMM) No. 58/2018 Page 2 of 97

7. Design, supply, installation, testing and commissioning of various
railway systems like rolling stock, power supply, overhead equipment,
signaling, track systems, platform, screen doors, ventilation, architectural
finishing etc. were to be provided by DAMEPL, as a private partner in the
project.

8. As per the CA, DAMEPL was allowed two years period for
completion of obligations and scope of work after they were granted access
to the civil segment by DMRC. DAMEPL was to operate and maintain
AMEL for next 28 years i.e. till August, 2038.

9. The scheduled commissioning and operation date of AMEL as
stipulated in the CA was 31st July, 2010 which was extended from time to
time to 30th September, 2010. As per Article 16.5 of the CA, the
Commercial Operation Date („COD‟, for short) was to be within two
months from the date of scheduled project completion date, i.e., by 31 st
November, 2010. On 11th January,2011 safety clearance/sanction for
operation of the line was granted by the Commissioner of Metro Road
Safety (CMRS) under the Delhi Metro Rail (Operation and Maintenance)
Act, 2002, which is now known as Metro Railways (Operation and
Maintenance) Act, 2002 [hereinafter would be referred to as „the Metro
Act‟]. Clearance was given with conditions and reduced speed limit of 105
kilometers per hour. On 23rd February, 2011, COD was achieved when
Airport Line Consultancy as per Article 17.6 of the CA had issued
provisional completion certificate.

10. DMRC had incurred expenditure of Rs.2,700 crores towards costs for
executing their part of obligations.

FAO(OS)(COMM) No. 58/2018 Page 3 of 97

11. Exact figure of the costs incurred on fixed assets by the DAMEPL is
unclear. Paragraph 118 of the Award refers to the report of IRCON who
were appointed by DMRC as consultants to evaluate the works executed by
DAMEPL. As per the IRCON‟s report cost of assets including overheads
and other charges created by DAMEPL was Rs.2273.67 crores. (This figure
has been referred to indicate that DAMEPL had incurred substantial
expenditure/costs. We express no opinion on correctness or otherwise of the
report).

12. DAMEPL was entitled to collect fare from the passengers and from
non-fare revenue sources like lease of retail space, property development in
adjacent areas, advertisements, vending machines etc. As per the terms, the
concessionaire was required to carry out an independent study to assess the
revenue likely to be generated from traffic and non-fare revenue sources and
prepare their own business model. The business plan was not a part of the
CA. As per DMRC business plan prepared by DAMEPL had indicated
losses for first five years and surplus earnings thereafter.

13. Based on the business model, DAMEPL had quoted annual
concessionaire fee of Rs. 51 crores to be paid to DMRC with escalation of
5% (cumulative) per year till termination. Requirement of payment of
annual concessionaire fee as stated by DAMEPL was incorporated in
Article 8.2 of the CA and became a binding term.

14. DAMEPL had paid concessionaire fee of Rs.51 crores for the first
year of operation i.e. for the period from 23rd February, 2011 to 22nd
February, 2012. Thereafter, they did not pay concessionaire fee.

FAO(OS)(COMM) No. 58/2018 Page 4 of 97

15. DAMEPL by letter dated 20th April, 2012, had requested DMRC to
defer payment of concessionaire fee for five years due to financial
constraints. In this letter while accepting that AMEL had been running
without glitches since 23rd February, 2011, DAMEPL had stated that in spite
of earnest efforts for meeting projections they were facing tremendous
limitations beyond their control. Commercial viability of the project was
largely based upon retail/property development component along with
advertisements and other commercial activities, which were to account and
cover 3/4th of the total revenue as against 1/4th for fare collections.
However, retail activities had not picked up as retailers were taking
significant time in fit outs; concept of retailing in metro stations had not
percolated amongst big brands; there were delays in finalizing retail
agreements, etc. Infrastructure projects have long a gestation period. The
project being the first public private partnership in the metro domain,
DAMEPL would require support from the public partner, namely DMRC, to
make it viable. This letter did not mention of any breaches on the part of
the DMRC and defects in the viaducts, etc. By letter dated 5 th May, 2012,
DMRC had turned down the request of DAMEPL for deferment of the
concessionaire fee. This letter dated 20th April,2011 of DAMEPL has not
been mentioned and stated in the award. The award however refers to the
DAMEPL’s letter dated 24th September, 2012, requesting for waiver of
concessionaire fee and restructuring of the CA (see paragraph 111 of the
Award).

16. DAMEPL by their letter dated 22nd March, 2012 had requested
DMRC to arrange for joint inspection of viaducts and bearings before expiry

FAO(OS)(COMM) No. 58/2018 Page 5 of 97
of „Defect Liability Period‟ of the civil contractors. For convenience and
clarity, we must state that viaducts were constructed and fell within the
scope of civil work executed by DMRC.

17. DAMEPL by letter dated 23rd May, 2012 had alleged that there were
serious design and quality issues with regard to installation of viaducts
bearings and there were signs of girders having sunk at some locations
causing deformation and cracks. DMRC had responded by their letter dated
2nd June, 2012, stating that detailed inspections as per Article 19 of the CA
and all preventive maintenance were within the scope of concessionaire i.e.
DAMEPL. DAMEPL was asked to give detailed inspection reports to
DMRC for review and their comments. DMRC had inspected some
locations identified by DAMEPL and had noticed that bearings were not
damaged but the grouting material filled above/below the bearings was
damaged or had loosened for which repair action had been taken on priority.
DAMEPL was asked to impose speed restrictions as deemed necessary in
interest of safety.

18. The Ministry of Urban Development had thereupon convened a
meeting of stakeholders on 2nd July, 2012 and a Joint Inspection Committee
(„JIT‟, for short) was set up. JIT had inspected the site on 4 th and 5th
July,2012 and submitted their report, which was signed by representatives
of DMRC and DAMEPL.

19. DAMEPL by their letter dated 6th July, 2012 to DMRC had expressed
their intent to stop the operations with effect from 8th July, 2012 on the
ground that the line was unsafe to operate. Operations were stopped by
DAMEPL with effect from 8th July, 2012.

FAO(OS)(COMM) No. 58/2018 Page 6 of 97

20. On 7th July, 2012, in the second round of meeting held with the
Ministry of Urban Development, it was envisaged that joint inspection
would be completed by 15th July, 2012. DAMEPL had also agreed to repair
viaduct bearings.

21. On 9th July, 2012, DAMEPL issued notice setting out a non-
exhaustive list of defects, which according to them had created unsafe
conditions to operate AMEL and thereby had prevented DAMEPL from
performing its obligations as per the CA. DMRC was asked to take all
actions and measures necessary to cure the defects within a period of 90
days, failing which the same would be treated as material breach and
„DMRC‟s Event of Default‟ under the CA. We shall subsequently
reproduce portions of the letter.

22. It is accepted and admitted that number of meetings were thereafter
held under the aegis of Ministry of Urban Development in which officers of
Ministry of Railways had also participated. Systra Consulting India Pvt.
Ltd., („Systra‟, for short) the original design consultant for viaduct section
were involved and had participated. Repair work was carried out by DMRC
through agencies engaged by them. DMRC had also engaged other
agencies to check quality of repair work. Progress of the repairs was
monitored by the Secretary, Ministry of Urban Development.

23. On 8th October, 2012, DAMEPL issued a letter/notice terminating the
CA claiming that though period of 90 days had expired from 9 th July, 2012,
i.e. the date of the cure notice, but neither the DMRC had cured the defects
nor had they taken effective steps to cure the defects. Therefore, DMRC’s
„Event of Default‟ had taken place, which entitled DAMEPL to terminate

FAO(OS)(COMM) No. 58/2018 Page 7 of 97
the CA. DMRC was called upon to pay the termination amount under
Article 29.5.1 of the CA.

24. DMRC by their letter dated 10th October, 2012 controverted and
negated the contentions of DAMEPL, including the grounds relied by
DAMEPL for terminating the CA.

25. DMRC further invoked Article 36.1 for conciliation process for
amicable resolution of the disputes.

26. As per DMRC, the meeting called by Ministry of Urban Development
on 12th October, 2012 was attended by representatives of DMRC,
DAMEPL, Ministry of Railways, Systra and other sub-contractors engaged
in repair work. In this meeting, DMRC had stated that 1986 bearings out of
2016 bearings had been rectified and other associate works such as load test,
etc. would be completed by 31st October, 2012. DAMEPL had agreed to
start the project after 31st October, 2012 with trial run of trains loaded with
sand bags being undertaken. Thereafter, clearance from CMRS would be
sought.

27. On 12th October, 2012, DAMEPL had agreed to participate in the
conciliation proceedings in accordance with Article 36.1 of the CA. Weekly
meetings were thereupon held on 20th and 22nd October, 2012 with the
representatives of DMRC, DAMEPL, Systra, TUV-SOGL, an independent
engineer, in which various issues pertaining to trial runs were discussed.

28. DMRC claims that on 22nd October, 2012 they had informed
DAMEPL that all bearings had been repaired. DAMEPL had then

FAO(OS)(COMM) No. 58/2018 Page 8 of 97
requested that they should be given seven days‟ notice when they can make
a public announcement for commencement of the operations of the line.

29. On 26th October, 2012, it was decided that trial runs would be held on
28th October, 2012 with a stipulation on specific piers that would be
observed during the train trial runs.

30. Notwithstanding the aforesaid meetings, on 23rd October, 2012
DMRC invoked the arbitration clause under Article 36.2. However, there
was substantial delay in constitution of the Arbitration Tribunal consisting
of Mr. H.L. Bajaj, Presiding Arbitrator, Mr. S.S. Khurana, Arbitrator and
Mr. A.P. Mishra, Arbitrator, which was constituted on 8th August, 2013.

31. On 19th November, 2012, DMRC and DAMEPL submitted a joint
application to CMRS for re-opening of the line with the speed limit of 80
kilometres per hour. This application for inspection had resulted in CMRS
asking for details which were supplied by DAMEPL and DMRC. CMRS
had thereupon asked for extra load test on 10 most critical girders that were
selected on the basis of location covering maximum cracks, etc. These tests
were conducted by DMRC in December, 2012, in presence of the
representatives of DAMEPL and were certified by Systra. CMRS had
personally inspected the line on 14th and 15th January, 2013.

32. On 18th January, 2013, CMRS issued certification to AMEL
permitting re-starting of the line with certain conditions, including reduced
speed limit of 50 kilometers per hour, which could be enhanced by 10
kilometers per hour till 80 kilometres per hour. We shall subsequently refer

FAO(OS)(COMM) No. 58/2018 Page 9 of 97
to this letter which as per DAMEPL was hedged with conditions and would
not meet the terms and obligations imposed on DAMPEL under the CA.

33. DAMEPL thereafter started operations on the line with effect from
22nd January, 2013 reserving and without prejudice to its rights and
obligations and allegedly on the instructions of the DMRC and not as a
concessionaire. In the letter dated 21st January, 2013 DAMEPL had stated
that they would be working as an agent of DMRC, which was not accepted
by DMRC vide their reply dated 8th February, 2013. We shall subsequently
examine the said aspect in some detail for one of the contentions raised by
the DMRC is that DAMEPL by election and conduct had withdrawn the
termination notice.

34. On 27th June, 2013, DAMEPL addressed a letter to DMRC calling
upon them to take over the project and the assets by close of business hours
of 30th June, 2013. DAMEPL stopped operations on close of working hours
of 30th June, 2013 and AMEL operations were handed over to DMRC, who
have continued to operate AMEL since 1st July, 2013.

35. As noticed above, on 8th August, 2013 the Arbitral Tribunal
consisting of Mr. H.L. Bajaj, Mr. S.S. Khurana and Mr. A.P. Mishra were
constituted. The first sitting was held on 6th September, 2013. The
arbitration proceedings continued for nearly three years. On 11th May,
2017, a unanimous Arbitral Award was pronounced substantially in favour
of DAMEPL.

The Award

FAO(OS)(COMM) No. 58/2018 Page 10 of 97

36. The Arbitral Award dated 11th May, 2017 records that DAMEPL in
the first hearing held on 21st September, 2013 had stated that in view of the
termination notice dated 8th October, 2012, they were not proceeding and
pressing their claim for restructuring of CA. DMRC by their letter dated 3rd
October, 2013 had agreed to withdrawal of DAMEPL‟s claim on the issue
of viability and restructuring of CA/project. This issue was also deliberated
in the second sitting of the Arbitral Tribunal held on 19 th October, 2013 in
which DAMEPL had stated that at that stage they would not claim for
restructuring and if such claim at all subsists or survives, it would be post
any decision on the issue of validity of termination or consequential reliefs.
Thereupon, the Arbitral Tribunal had recorded that the issue to be
determined would relate to termination notice dated 8th October, 2012 issued
by DAMEPL and all consequential and cognate claims arising from and
relating to termination notice. The Arbitral Tribunal during the course of
hearings had passed orders on different applications referring to another
arbitration proceeding pending between the parties. Arbitration Tribunal
held that in the present arbitration they were not interested to go into the
question of fixing responsibility for the defects nor would they entertain
such attempt. However, questions relating to cause of defects, their nature,
severity and curability were relevant for determination of issues (see
paragraph 17 of the Arbitral Award).

37. DMRC had led evidence which included affidavits of Mr. Ranjan
Katarai, Executive Director/Technical, DMRC, Mr. Vinod Nair, Inspection
Engineer of TUV-SOWILL and affidavit in rejoinder of Mr. Mathieu Muls

FAO(OS)(COMM) No. 58/2018 Page 11 of 97
of Systra. DAMEPL had filed affidavits of Ms. Neena Goel, Chartered
Accountant and Mr. Abhay Kumar Mishra, CEO of DAMEPL.

38. In paragraph 19 of the Award, the Arbitral Tribunal has referred to
issues which have been divided into; DMRC‟s issues, counter claim issues,
DAMEPL issues etc. We may note that issues were not specifically framed
by a specific order by the Arbitration Tribunal and circulated to the parties.
Thereupon, in paragraph 20, the Arbitral Tribunal observed that in
substance the following main issues arose for consideration:-

“(i) Were there any defects in the civil structure of the airport
metro line?

(ii) If there were defects, did such defects have a material
adverse effect on the performance of the obligation of DAMEPL
under CA?

(iii) If there were defects in the civil structure, which had a
material adverse effect on the performance of the obligations
under the CA by DAMEPL, have such defects been cured by
DMRC and / or have any effective steps been taken within a
period of 90 days from the date of notice by DAMEPL to cure the
defects by DMRC and thus were DMRC in breach of the CA as
per 29.5.1 (i)?

The determination of the aforesaid issues would then lead us to
the determination of consequential questions particularly those
related to specific performance of the contract or, alternatively,
the award of damages or the outcome of the counter claim filed by
DAMEPL.”

39. Under the heading “JURISDICTION”, the Arbitral Tribunal rejected
the plea of DMRC that it had no jurisdiction to examine, who was
responsible for defects; whether civil segment of AMEL was plagued by

FAO(OS)(COMM) No. 58/2018 Page 12 of 97
“permanent defects”. Referring to the contention of DMRC that DAMEPL
had raised several issues regarding defects, which were not mentioned in the
cure notice/letter dated 9th July, 2012 or at any time between June, 2012 to
January, 2013, when operations had re-commenced, it was observed that
the notice dated 9th July, 2012 was not an exhaustive list of defects as
DAMEPL had stated that unless and until it was ascertained what the
defects were, it was not possible to find out whether the defect were cured
or not and whether effective steps were taken within the cure period to
remedy the breaches (see paragraph 24 of the Award). In paragraph 27,
reference was made to chronology of events in the form of correspondence
written by DAMEPL that had referred to latent or inherent defects.
Arbitration Tribunal had thereafter held:-

“28. From the aforesaid, it transpires that the notice dated 9”
July 2012 is not confined only to defects relating to bearings. It
gives a “non-exhaustive” list of the various defects and makes
reference to various “latent/inherent” defects as well. DMRC has
not only admitted but has also contended and led evidence to show
that defects, apart from those relating to bearing assembly, such as
cracks at the soffit of the girders, were according to DMRC
addressed and repaired. If DMRC was concerned only with the
defects in bearing assembly and understood the complaint of
DAMEPL as relating only to the bearing assembly, there was no
point of DMRC addressing various other defects such as cracks at
the soffit of the girders, gaps between the girders and girder and
the shear key and twist in girders, etc. The contention of
DAMEPL is that some of the said defects which were pointed out
by DAMEPL and actually found to exist, which DMRC claims to
have remedied, are not cured. A necessary pre-requisite of
investigating the question of what the defects were/are and
whether they have been remedied or not is to find out the nature,
quantum and severity of the defects. This Is necessary to
determine whether defects have been cured and / or effective steps

FAO(OS)(COMM) No. 58/2018 Page 13 of 97
have been taken by DMRC to cure the defects. Thus, the
submission of DMRC that addressing the questions as to what the
defects are and what is the nature of the said defects is beyond the
jurisdiction of the Arbitral Tribunal is not correct.

29. To conclude, the main issue to be decided in this arbitration is
whether there were defects in the civil structure of the Airport
Metro Line and whether the defects have been cured and/or
effective steps to cure the same have been taken by DMRC in
terms of Article 29.5.1 of the CA and the consequences of the
finding on the said issue. The Arbitral Tribunal has undertaken
only the said exercise. In the circumstances, It is held that the
issues considered by the Tribunal are within the scope and
jurisdiction of the Tribunal.”

40. Under the heading “DETAILED ANALYSIS OF THE SPECIFIC
DEFECTS/DEFICIENCIES IN THE VIADUCT STRUCTURE AND
THEIR REPAIRS/RECTIFICATION” under different sub-headings after
referring to submissions of the parties, the Arbitration Tribunal had made
analysis and discussion. Thereupon the following summary was recorded by
the Arbitral Tribunal:-

“The views of the Arbitral Tribunal on defects/design
deficiencies/constrains in the civil structures of Delhi Metro Airport
Line are summarized herein below:-

SI Defect/Deficiency in Views of the Arbitral Tribunal
Design/Constraints
No.

1. Cracks at the bottom of Occurrence of such large numbers of
the girders cracks in the base slab of the pre-

stressed concrete girders within just
one year of train operation, tentative
assessment of the cause of cracks,
unreliable measurement of crack
depth which in many cases extend to

FAO(OS)(COMM) No. 58/2018 Page 14 of 97
more than half of the depth of bottom
slab of U girder and non serious
inspection of the repairs by an agency
appointed by DMRC impact
adversely on the integrity of the
structure. This leads to the conclusion
that DMRC is in the breach of the CA
as effective steps were not taken
within the cure period of 90 days to
cure this defect and this has caused
Material Adverse Effect on the
Concessionaire (DAMEPL).

2. Twist in the Girders Effective steps were not taken to cure
twist in all the girders (twist up to 20
mm was left unattended) and girders
of suspect integrity were allowed to
remain in the network. This
constitutes a DMRC Event of Default.
DMRC is in breach and this breach
has Material Adverse Effect on the
Concessionaire (DAMEPL).

3. Gaps between girders No action to cure this defect was
and between girders and taken by the claimant (DMRC) during
shear key the cure period (09- 07-2012 to 08-

10-2012). Gaps higher than 25 mm
were not rectified. As such, this defect
was neither cured nor effective steps
were

“77. In the light of the aforesaid, it is clear that there were defects
in the civil structure of the Airport Metro Line. It is also found that
the above mentioned defects, which would have Material Adverse
Effect on the performance of the obligations under the CA by
DAMEPL, have not been cured within the cure period of 90 days
from the date of the cure notice nor have effective steps been
taken to cure such defects.

FAO(OS)(COMM) No. 58/2018 Page 15 of 97

78. Thus, it is concluded that DMRC is in breach of the CA as it
has failed to cure the breach or take effective steps for curing the
breach within 90days of the notice dated 09.07.2012 from
DAMEPL. Such breach has Material Adverse Effect on the
Concessionaire (DAMEPL).As such, the Ingredients of Article
29.5.1(1) of CA are satisfied and, therefore, the Termination
Notice given by DAMEPL on 08.10.2012 is valid.”

The Arbitral Tribunal has held that there were cracks at the bottom
and gaps between girders and between girders and shear key. Accordingly
DMRC was in breach of CA as effective steps to cure the defects were not
taken within 90 days that had caused „material adverse effect‟ on the
concessionaire i.e. DAMEPL, which entitled them to invoke Article 29.5.1

(i) of CA. Therefore, the termination notice given by DAMEPL on 8th
October, 2012 was valid. DMRC has challenged the said findings on
perversity and other grounds, which we would deal with subsequently.

41. After recording the aforesaid findings on validity of termination
notice dated 8th October, 2012 and that ingredients of Article 29.5.1 (i) of
CA were satisfied, the Arbitral Tribunal had dealt with the following legal
issues:-

“A. Is the Concession Agreement specifically enforceable and
should specific performance of such an agreement be as a rule
directed or are damages an adequate remedy for the breach of the
OA?

B Whether DAMEPL has abandoned or “disowned” or “negated”
or “nullified” the termination notice by continuously participating
in the defect rectification process prior to and after the termination
notice and by its conduct of operating the line subsequent to the
termination notice?

FAO(OS)(COMM) No. 58/2018 Page 16 of 97

C. Is the sudden and abrupt abandonment of a public interest
project and the abrupt termination of the OA by DAMEPL valid?

D. Was DAMEPL entitled to or justified in termination of the OA,
since the cost of repairs of the alleged defects was only
approximately Rs.14 crores as compared to the total costs of the
project of approximately Rs. 5700 crores?

E. Did DAMEPL fail to carry out the required inspection resulting
in the alleged defects not being discovered during the defect
liability period of the civil contractors? Or, as contended by
DAMEPL, was only limited access permitted to DAMEPL by
DMRC without actually handing over the structures as required
under the CA?

F. Was perceived financial unviability and not the defects in the
structure, the real reason of the termination of the CA by
DAMEPL?

G. Has DAMEPL failed to discharge its onus of disproving
DMRC’s case by not leading oral evidence to counter the rebuttal
evidence of DMRC or was DAMEPL entitled to disprove the case
of DMRC and prove its own case by cross examining the
witnesses of DMRC?

H. Did the issuance of certificate by CMRS show that the defects
were duly cured?”

42. Regarding prayer for specific enforceability and performance of CA,
it was held that such prayer cannot be granted since DMRC had committed
breach of contract having ‘material adverse effect’ on the ability of
DAMEPL to perform the contract which disentitled DMRC to seek
performance of CA. Further, specific performance was not permissible
under Section 14 (1) (d) of the Specific Relief Act. Section 10 of the
Specific Relief Act would not be applicable as this was not a case relating to

FAO(OS)(COMM) No. 58/2018 Page 17 of 97
immoveable property. On issue „B‟ it was observed that DAMEPL‟s
participation in the discussions during the period 9 th July, 2012 to 8th
October, 2012 was immaterial as the CA was in operation and had not been
terminated. After the termination notice dated 8 th October, 2012, DAMEPL
had asserted that it was participating without prejudice to their rights and
contentions. Besides DMRC had invoked re-conciliation process under
Article 36.1 of the CA. Immediately thereafter DMRC had invoked
arbitration proceedings by their letter dated 23 rd October, 2012.
Participation of DAMEPL being without prejudice would not negate and
nullify the termination notice as DAMEPL was always insisting that the CA
was terminated. On issue „C‟, the Arbitral Tribunal observed that no doubt
the project was of public interest but DMRC had committed material breach
of CA. Therefore, the argument of DMRC was untenable as DAMEPL
could validly exercise their right to terminate the contract in terms of the
contract which governed the rights of the parties.

43. On issue „D‟, the Arbitral Tribunal had held :-

” D. Issue: Was DAMEPL entitled to or justified In
termination of the CA, since the cost of repairs of the
alleged defects was only approximately Rs.14 crores as
compared to the total costs of the project of approximately
Rs.5700 crores?

91. It is contended by DMRC in para 1.1 of Addl.
Submission dated 14.11.2016, that the cost of repair of the
defects was only Rs. 14 crores while the cost of the project is in
excess of Rs.5700 crores. The small quantum of the amount
incurred to execute the repairs of the defects as compared to the

FAO(OS)(COMM) No. 58/2018 Page 18 of 97
huge amount of the cost of the projects Itself shows that the
defects were not substantial and that there was no breach of the
CA on part of DMRC as contemplated by Article 29.5.1 of the
CA.

92. In reply. DAMEPL contends that what is required to be
seen is the nature of the defects themselves and not the costs of
the repairs. It is the contention of DAMEPL that defects have
not been cured and / or effective steps have not been taken
during the cure period and, thus, the question of the quantum of
the expense is immaterial. The fact that the repairs were not
cured shows that the exercise undertaken by DMRC to repair
the defects was inadequate.

93. Finding and Conclusion:

In view of our conclusions that there were defects which
caused material breach of the CA and all the defects have not
been cured nor have effective steps been taken during the cure
period, It is not relevant that only a small amount in
comparison to the overall cost of the project has been spent in
the process of curing the defects.”

44. On issue ‘E’, the Arbitration Tribunal held that DAMEPL was
responsible only for maintaining such section of the site which had been
handed over and not that section of which mere access was granted. DMRC
had not formally handed over the site to DAMEPL and had only provided
the access. Defects in the DMRC‟s work were apparent within 12 months
of the handing over of the section and DAMEPL had advised the same to
the consultant. DAMEPL was not aware of the completion certificate
issued to the civil contractors effective from 30th September, 2010. “Built

FAO(OS)(COMM) No. 58/2018 Page 19 of 97
drawings” were not provided to DAMEPL till much after the cure notice
dated 9th July, 2012. There was no document to show that there was formal
handing over of the site by DMRC and taking over by DAMEPL.

45. With regard to issues F, G and H, we would like to reproduce the
findings of the Arbitration Tribunal in entirety:-

“F. Issue: Was perceived financial unviability and not the
defects in the structure, the real reason of the termination of
the OA by DAMEPL?

99. DMRC in its Statement of Claim (Para 47) contends that the
action of DAMEPL was nothing else but an attempt on the part of
DAMEPL to absolve itself from the obligation under the CA as a
result of the financial distress in which DAMEPL had found itself
after aggressively bidding for the project. DMRC submitted that
the said cause cannot be legal and valid cause for absolving
successful bidder from the obligations undertaken by it under the
Concession Agreement.

100. To similar effect are DMRC’s contentions in para 41 of its
Written Submissions dated 14.10.2016. In reply, DAMEPL has
reiterated its stand in the Respondent’s Rejoinder note-IV
submitted on 20.08.2016 that if its termination was valid under
Article 29.5.1 of the CA, the question of financial viability or
otherwise of the Project is completely irrelevant.

101. Findings and Conclusion:

While dealing with defects in the civil structures and constraints
due to faulty construction, the Tribunal came to the conclusion
that there continued to be uncured defects/constraints of a far
reaching nature which adversely affect the ability of DAMEPL to
perform its obligations under the CA. The Tribunal has not been
called upon to go Into the question of the financial viability or
otherwise of the project. In view of our findings that the
termination is valid, the issue of financial viability Is not being
dealt by us.

FAO(OS)(COMM) No. 58/2018 Page 20 of 97

G. Issue: Has DAMEPL failed to discharge its onus of
disproving DMRC’S case by not leading oral evidence to
counter the rebuttal evidence of DMRC or was DAMEPL
entitled to disprove the case of DMRC and prove its own case
by cross examining the witnesses of DMRC?

102. DMRC contends that DMRC has led rebuttal evidence of Mr.
Matheu Muls and Mr. Rajan Kataria on several aspects. DAMEPL
ought to have led evidence in re-rebuttal to discredit the evidence
of the said witnesses which DAMEPL has not done and, thus,
DAMEPL has failed to prove its case.

103. DAMEPL, on the other hand, contends that Mr. Muls and
Mr. Kataria have been elaborately cross examined while giving
evidence in rebuttal and by the said cross examination, DAMEPL
has successfully discredited the evidence of Mr. Muls and Mr.
Kataria. DAMEPL contends that DAMEPL has been able to show
from various codal provisions and the documents produced during
the course of rebuttal cross examination that the evidence given by
DMRC In rebuttal is not correct, In legal support of their
contention that DAMEPL need not have led evidence In re-
rebuttal but was entitled to discredit the rebuttal evidence of the
witnesses by their cross examination and with reference to various
documents and codal provisions, DAMEPL has cited various
judgments.

104. Findings and Conclusion:

The Tribunal has considered the evidence both oral and
documentary led by the parties. The Tribunal has also considered
the provisions of various applicable codes. We are aware that the
provisions of the Arbitration and Conciliation Act, 1996 (Section

19) clarify that the Arbitrators are not bound by the provision of
the Indian Evidence Act, 1872. Thus, strict compliance with the
provisions of the Evidence Act by the arbitrators is not warranted.
However, even if the provisions of the Indian Evidence Act 1872
was to be considered, the judgments cited by DAMEPL support
the proposition that it is indeed possible for a party to establish its

FAO(OS)(COMM) No. 58/2018 Page 21 of 97
own case by means of the opponent’s witness. In this respect, we
quote herein below an extract (page 429) from the judgment of the
Karnataka High Court, in the case of Shri. Ramchandra and Ors.
Vs Shri Vittal and Other Reported in ILR 2009 KAR (Page 423 to

432) (Compilation of Judgments submitted by DAMEPL on
20.08.2016).

“The object of cross examination is twofold. Firstly, to weaken
qualify or destroy the case of the opponent. To impeach the
accuracy, credibility and general value of the evidence given in
chief, to sift the facts already stated by the witness, to detect and
expose discrepancies or to elicit suppressed facts which will
support the case of cross examining party. Secondly, to establish
the party’s own case by means of his opponents witnesses. It may
be either by way of admissions or by way of eliciting facts which
would prove the case of the cross examining party. It is like a
double edged sword. Properly used it may destroy the opponents
case and support the cross examining party. Otherwise, it may
destroy the case of the cross examining the party. It is an art which
requires great skill. It can be acquired only by training and
experience”.

b. In the circumstances, it is concluded that the contention of
DMRC that merely on account of DAMEPL not leading evidence
in re-rebuttal, DAMEPL has failed to prove its case is not correct.

H. Issue: Did the issuance of certificate by CMRS show that
the defects were duly cured?

105. DMRC contends that CMRS has cleared the operations of the
line inJanuary2013. The line has been running successfully since
and no problems or defects have been discovered or encountered
during the period of subsequent operations. This shows that the
defects have been completely cured.

106. DAMEPL, on the other hand, has contended that far from the
CMRS certificate showing that the defects have been cured, the
large number of conditionality imposed by CMRS including the

FAO(OS)(COMM) No. 58/2018 Page 22 of 97
reduction in the speed of the line and the mandatory requirements
for periodical inspection shows that CMRS was not entirely
satisfied with the condition of the line. Further, It is the
submission of DAMEPL that events that have taken place after the
date of the termination ofCA are not relevant.

107. Findings and Conclusion-

For the purposes of considering the aforesaid submissions the
relevant extract of the CMRS sanction dated 18.01.2013 (RC – 14.
Page 165 to 169) are reproduced below; –

“(xi) The repairs to all the bearings used in U girders have
been carried out by DMRC in the entire stretch of the line. Such
type of repairs have been done for the first time on the Metro
Network and needs to be monitored.

(xii) Cracks in soffit of some of the „U‟ girders have also been
repaired by DMRC. These cracks are required to be monitored
during operation also to make sure that the situation remains
stable. The monitoring of cracks for any propagation should be
carried out as per Railway Board‟s letter no.2012/Proj/AME/1/6
dated 04.01.2013 addressed to CPM/AP/DMRC.

(xiii) Apart from routine inspection, operation and
maintenance by the Concessionaire, DMRC should also carry out
periodical inspection to ensure that the condition to track structure,
viaducts etc is commensurate with speed in operation.

Further increase of speed in this section beyond 50 (fifty) kmph up
to the propose speed of 80 (eighty) kmph may be authorized by
Dir/W/DMRC, who accompanied the inspection, in steps of 10
Kmph at the time on satisfactory tram operation in the section for
a reasonable period of time and after his personal inspection,
satisfaction, certification and after due consideration of items
mentioned in para 2 (ix) to (xii) above. Before any increase in the
speed, he should satisfy himself about the adequacy and any

FAO(OS)(COMM) No. 58/2018 Page 23 of 97
necessary attention as required with reference to the safety of
public carriage of passengers.

For increasing the speed beyond 80 kmph, the DMRC shall
approach the Commission for sanction with adequate justification
in regard to the improvements brought out.”

108. From the said letter, it is evident that the CMRS sanction
clearly recognizes that rigorous monitoring is required to be done
during the operation of the line. CMRS imposed a speed
restriction of 50 kmph to start with. The prime purpose of the
Airport Metro Line is to serve as a high speed connectivity, which
is not fulfilled due to the severe speed restriction imposed by
CMRS. As such, the CMRS certificate does not support the
contention of DMRC. The subsequent operation of the line in the
hands of DMRC is not relevant for the purpose of determination of
issues before the Tribunal. Thus, the said contention of DMRC is
not accepted.”

46. Thereafter the Arbitration Tribunal had specifically dealt with the
claims, counter claims and had pronounced the final Award. Claim of
DMRC relating to non-payment of the concessionaire fee was accepted
holding that DAMEPL would be liable to pay concessionaire fee of Rs.51
crores for the first year of operation and thereafter with 5% increase for
every year for the period upto 7th January, 2013, which was quantified and
computed at Rs.46.94 crores Accordingly DAMEPL was held liable to pay
concessionaire fee for the period between 23rd February, 2012 to 7th January,
2013. Thus, it was held that the contract was terminated only on 7 th January,
2013. Other claims made by DMRC were rejected.

47. The Award on the counter claims by DAMEPL held that the Article
29.5.2 of the CA was applicable and accordingly DMRC was liable to make
termination payment of Rs.1260.73 crores on account of Rupee term loan

FAO(OS)(COMM) No. 58/2018 Page 24 of 97
and Rs.538.58 crores on account of external commercial borrowings as debt
due. Further Rs.983.02 crores was payable by DMRC to DAMEPL being
130% of adjusted equity. Ergo, an amount of Rs.2782.33 crores was
payable by DMRC to DAMEPL under Article 29.5.2 of the CA.

48. DMRC, it was held was also liable to pay interest on Rs.2782.33
crores payable as termination payment as per Article 29.8 of the CA at
annualized rate of SBI Prime Lending Rate (PLR) plus 2%. The interest, it
was held, would be payable and accrued from 7th August, 2013, i.e., 30 days
after DAMEPL had raised the demand for termination payment vide their
letter dated 8th July, 2013. It was also directed that in terms of Article 29.9,
this amount shall be credited to the Escrow account, details of which had
been furnished by DAMEPL. As per the DMRC, total amount of interest
payable in terms of the Award towards termination payment cumulatively
amounts to Rs.4506.02 crores.

49. The Award has also directed DMRC to pay Rs.147.52 crores with
interest @ 11% per annum from the date of payment of stamp duty on the
Award to DAMEPL towards expenses incurred for operating AMEL from
7th January, 2013 to 30th June, 2013 on account of net operating cost of
Rs.39.76 crores and net debt servicing cost of Rs.107.76 crores.

50. DMRC has been also directed to reimburse Rs.62.07 crores on
account of encashment of bank guarantee of Rs.55 crores and Rs.7.07 crores
on account of differential commission and penal interest charged by the
bank from DAMEPL. DMRC is also directed to reimburse the principal
security deposit of Rs.56.8 lacs along with interest @ 11% per annum,

FAO(OS)(COMM) No. 58/2018 Page 25 of 97
which would accrue from the date of payment of requisite stamp duty on the
Award.

51. Some of the other counter claims made by DAMEPL have been
rejected on the ground of duplication or principle of remoteness of damages.
The claim for refund of the concessionaire fee was also rejected on the
ground that it cannot be granted under the CA.

52. For the sake of clarity, we would like to reproduce paragraph 139 of
the Award, which summarizes the claims raised and answers given by the
Arbitral Tribunal:-

“139. In view of the discussions and findings above, we proceed to
answer the issues raised by the parties as follows:

DMRC’S ISSUES ON CLAIM:

Sr Issues Answers
No.
1. Whether the letter dt 8/10/2012 In the negative. The
issued by respondent is illegal, termination notice dtd.
incorrect and against the 08.10.2012 issued by
provisions of the Concession the Respondent
Agreement and should be treated DAMEPL is valid.
as null and void?
2. Whether the Claimants have In the negative.
performed their obligations under
Concession Agreement towards
curing of the defects as pointed
out by the Respondent vide their
letter dated July 9, 2012?
3. Whether the real motive of Not relevant in view of
Respondent to terminate the answer to issues 1 and 2
concession agreement is Financial above.
viability of their Business Plan?

FAO(OS)(COMM) No. 58/2018 Page 26 of 97
4. Whether the Claimants are In the negative.
entitled to the compensation of
Rs.3173 crore from the
Respondent along with interest @
18% as per the Claim Petition?
5. Whether the Claimant is entitled In the negative.
to an amount of Rs.4.92 crore per
month as claimed in the Claim
Petition along with interest @
18% per annum?
6. Whether the Claimant is entitled In the negative.
to an amount of Rs.1,000 crores
along with interest as loss of
reputation and goodwill caused
due to illegal acts of the
Respondent?
7. Whether the Claimant is entitled We direct parties to
to cost of the Arbitration bear their own cost of
proceedings? arbitration.
8. Whether, as stated by In the affirmative.
Respondents, the Claimants had
failed to cure the breach within
the period specified under
Concession Agreement as per the
provisions of Article 29.5.1?(Para
11 of Reply)
9. Whether, as stated by Claimants DMRC
Respondent, the Claimants failed failed to take effective
to make honest or sincere efforts steps for curing the

or take effective steps for curing defects as required by
the defects as required by the Concession
Concession Agreement? (Para 11 Agreement.
12 of Reply)

10. Whether the participation of In the negative.

Respondent in the repair process,
submission of Application to
CMRS and recommencement of
Operation and Maintenance of the

FAO(OS)(COMM) No. 58/2018 Page 27 of 97
Project by Respondent, proves
that the contentions of
Respondent, as contained in letter
dated October 8, 2012, stood
negated and nullified.

(Para 32 of the claim)

DMRC’S ISSUES ON COUNTER CLAIM:

Sr Issues Answers
No.
1. Whether the Respondent is DAMEPL
entitled to sum of Rs.3470 cr. as (Respondent) is entitled
Termination Payment along with to the sum of
interest and further interest @ Rs.2782.33 crores from
SBI PLR plus 2% per annum as DMRC. Interest and
claimed in the Counter Claim? manner of payment
should be as stipulated
in Articles 29.8 and
29.9 of CA.
2. Whether the Respondent is In the affirmative.
entitled to sum of Rs.166.32 crore DAMEPL is entitled to

including interest on the Principal receive the sum of
amount of Rs.152.59 cr. of claims Rs.147.52 crores from
in Counter Claim? DMRC interest at the
rate of 11 percent per
annum will accrue from
the date requisite stamp
duty is paid by
DAMEPL.

3. Whether the Respondent is In the negative.
entitled to sum of Rs.105.74 cr
with interest @ 18% per annum
as claimed in Counter Claim?

4. Whether the Respondent is In the affirmative.

entitled to an amount of Rs.66.93 DAMEPL is entitled to
crores with interest @ 18% per receive sum of Rs.62.07

FAO(OS)(COMM) No. 58/2018 Page 28 of 97
annum as claimed in Counter crores. Interest at the
Claim? rate of 11 percent per
annum will accrue from
the date requisite stamp
duty is paid by
DAMEPL.

5. Whether the Respondent is In the affirmative.

entitled to an amount of Rs.56.8 DAMEPL is entitled to
lakhs with interest @ 18% per receive sum of Rs.56.8
annum as claimed in Counter lakh. Interest at the rate
Claim? of 11 percent per
annum will accrue from
the date requisite stamp
duty is paid by
DAMEPL.

6. Whether the Respondent is In the negative.

entitled to an amount of
Rs.2382.82 crore with interest @
18% per annum as claimed in
Counter Claim?

7. Whether the Respondent is In the negative.

entitled to an amount of
Rs.452.17 crore with interest @
18% per annum as claimed in
Counter Claim?

8. Whether the Respondent is In the negative.

entitled to an amount of Rs.1250
crore with interest @ 18% per
annum as claimed in Counter
Claims?

9. Whether the Respondent is In the negative.

entitled to an amount of
Rs.725.78 crore along with
interest at the rate of SBI
PLR+2% per annum on Rs.685
crore as claimed in Counter
Claim?

10. Whether the Respondent is Parties to bear their

FAO(OS)(COMM) No. 58/2018 Page 29 of 97
entitled to cost as claimed in the own cost of Arbitration.
Counter Claim?

PROCEEDINGS BEFORE THE SINGLE JUDGE:

53. DMRC had thereupon preferred petition under Section 34 of the AC
Act, which was registered as OMP (COMM) No.307/2017. DAMEPL, on
the other hand, had filed an application/petition under Section 9 of the AC
Act, OMP (COMM) (I) No. 200/2017 ,seeking direction that DMRC should
deposit Rs.3502.62 crores being 75% of the awarded amount and the said
amount should be released to the lenders. By order dated 30 th May, 2017,
learned single Judge had directed DMRC to pay Rs.60 crores directly to the
lead banker, subject to furnishing of an unconditional bank guarantee of
Rs.65 crores. The controversy; whether the Office Memorandum issued by
NITI Aayog would be applicable was to be decided on the next date of
hearing. This order was challenged by the DMRC before the Division
Bench without success and the Special Leave Petition by DMRC was also
dismissed.

54. Learned single Judge by the impugned judgment dated 6 th March,
2018 has upheld the Award and rejected the objections filed by DMRC
under Section 34 of the AC Act. It directs DMRC to deposit the amount
awarded alongwith interest directly with the Escrow account maintained by
the project lenders. The bank guarantee issued by the concessionaire and
furnished by DAMEPL to secure payment made by DMRC was discharged.

FAO(OS)(COMM) No. 58/2018 Page 30 of 97

INTERIM ORDERS IN THIS APPEAL

55. On the present appeal being preferred, vide order dated 10 th April,
2018 the Court disposed of interim application for stay, CM No.
13435/2018, taking letter dated 9th April, 2018 written by the DMRC on
record. By the said letter, the DMRC had undertaken and the order dated 9th
April 2018 has directed that DMRC would be liable to pay service dues of
DAMEPL to its bankers. This order was subject to final outcome of the
appeal and in the event of DMRC succeeding, appropriate orders for
restitution, etc. would be passed. Thereafter, CM No. 17581/2018 was filed
by promoter of DAMEPL, namely, M/s Reliance Infrastructure Limited,
which application was subsequently disposed of vide order dated 26 th
September, 2018 as not pressed since arguments had commenced in the
main appeal itself.

OBJECTIONS/ SUBMISSIONS

56. Objections raised by DMRC can be divided under the following
heads:-

(i) Waiver of termination notice by election and conduct.

(ii) Validity of termination notice dated 8th October, 2012 and the
findings of the Award that the DMRC had not taken effective
steps for removal of defects and thereby caused ‘material
adverse effect’ on DAMEPL and, therefore, Article 29.5.1 of
the CA was attracted.

(iii) Computation or calculation under Article 29.5.1 by treating and
adding Rs.611.95 crores to adjusted equity.

FAO(OS)(COMM) No. 58/2018 Page 31 of 97

(iv) Award of interest under Article 29.8 of the CA at annualized
rate of SBI PLR plus 2% notwithstanding Article 36.2.6.1 of
CA which states that where an Arbitral Award is for payment
of money, no interest shall be payable on whole or any part of
money till award is made.

57. At the outset, we must record that DMRC has not challenged findings
of the Arbitral Tribunal in the Award rejecting their prayer for direction for
specific performance and direction to DAMEPL to operate the AMEL
except and to the extent of challenging the finding recorded in the award
that ingredients of Article 29.5.1 are satisfied. Similarly, DAMEPL has not
challenged the Award insofar as it directs them to make payment of
Rs.46.94 crores with interest @ 11% per annum from the date of payment of
stamp duty by DMRC, being the unpaid concessionaire fee for the period
23rd February, 2012 to 7th January, 2013.

58. For clarity, we would clarify that the challenge made in the present
appeal, therefore, is confined to direction to DMRC to make termination
payment under Article 29.5.1 of Rs.2782.33 crores, including adjusted
equity after including Rs.611.95 crores to arrive at the figure of Rs.756.17
crores payable @ 130% with interest in terms of Article 29.9 of the CA at
the annualized rate of SBI PLR plus 2%; claim for paying net operating cost
of the line plus debt servicing cost for the period 7 th January, 2013 to 30th
June, 2013; payment/refund of Rs.62.07crores with interest @ 11% per
annum from the date of payment of requisite stamp duty on account of
encashment of bank guarantee of Rs.55 crores and Rs.7.07 crores on
account of differential commission and penal interest and lastly refund of

FAO(OS)(COMM) No. 58/2018 Page 32 of 97
security deposit of Rs. 56.8 lacs with interest @ 11% per annum from the
date of payment of requisite stamp duty by DAMEPL.

Whether participation in the reconciliation process, signing of the
application form dated 19th November, 2012 submitted to CMRS for
recommencement of AMEL and operation thereafter for a period of 5
½ months from 21st January, 2013 till 30th June, 2013 had amounted to
waiver of the right to terminate

59. The aforesaid question and issue have been discussed by the Arbitral
Tribunal under legal issue „B‟. Their findings are that DAMEPL‟s
participation during the cure period from 9th July, 2012 to 8th October, 2012
was inconsequential and would not amount to waiver. Subsequent
participation of DAMEPL in the discussions, submission of papers to
CMRS and operation of AMEL from 23rd January 2013 till 30th June 2013,
after issue of termination notice on 8th October, 2012, was without
prejudice. DMRC had invoked the conciliation process under Article 36.1
of the CA. Further, DAMEPL had made substantial investment in the
infrastructure of AMEL and, therefore, they were interested in the process
being undertaken. Throughout DAMEPL had not relinquished, abandoned,
waived or negated the termination notice. Reliance was placed upon the
correspondence as per which the DAMEPL had throughout asserted the
termination.

60. On behalf of DMRC, it was submitted that to sustain an action based
upon contractual right of termination, the termination must be unequivocal
in both letter and conduct. In the present case, the conduct was inconsistent
with termination and, therefore, doctrine of waiver should have been
applied. When a contract is terminated, parties do not by conduct affirm

FAO(OS)(COMM) No. 58/2018 Page 33 of 97
continuation of the contract as had happened in the present case when
DAMEPL had jointly made an application with DMRC to CMRS on 19th
November, 2012 for re-starting operations, which had in fact commenced
with DAMEPL operating the AMEL from 22nd January, 2013 to 30th June,
2013. The DAMEPL had equally participated in the joint meetings which
had continued even after the termination notice with the intent and purpose
to cure/rectify the defects and make the project safe for transportation. In
these meetings, DAMEPL had not actually reiterated the intent to terminate.

61. The Award highlighted that DAMEPL had participated in the
conciliation proceedings without prejudice to the termination notice. It was
highlighted that their interest was to protect their huge investment, which
was valued at Rs.2273.67 crores by IRCON. DAMEPL has also stated, that
they were specifically instructed by Ministry of Urban Development vide
Minutes of Meetings dated 31st October, 2012 to apply to CMRS by 5th
November, 2012. Accordingly, DAMEPL had signed the draft applications
pertaining to systems installed by DAMEPL, which was thereafter filled up.
The form was signed by DMRC with reference to the civil structure before
the same was forwarded to CMRS. Even after CMRS had granted sanction,
on 18th January, 2018, DMRC had instructed DAMEPL to run the line in
accordance with Article 29.7 of the CA. DAMEPL by their letter dated 21st
January, 2013, which was marked without prejudice as the CA stood
terminated, had agreed to commence operation subject to the pending
adjudication before the Arbitral Tribunal. Reference is made to the contents
of the letter dated 31st January, 2013 written by DAMEPL to DMRC.

FAO(OS)(COMM) No. 58/2018 Page 34 of 97

62. Having considered the contention raised on both sides, we are not
inclined to interfere with the findings recorded in paragraph 87 of the
Award, which reads as under:-

“87.1 ……..during the cure period DAMEPL was required to
give all assistance in the process and since it had made substantial
investment in the infrastructure of the metro line, it was obviously
interested in the process being undertaken. No sooner was the
termination notice given on 08.10.2012 (CD-28, Pg. 284),
DAMEPL repeatedly asserted that whatever it was doing was
“without prejudice” to its rights and contentions and, additionally,
the parties immediately invoked the conciliation process under
Article 36.1 of CA followed immediately by invoking the
arbitration by DMRC by its letter dated 23.10.2012
(Miscellaneous Application dated 30.10.2013, Pg. 14-15). The
subsequent actions of DAMEPL were without prejudice to its
rights and contentions as well as without prejudice to the
pendency of the arbitral proceedings. Thus, far from “negating”
or “nullifying” the termination notice, DAMEPL was insisting
upon the same.”

The aforesaid findings are predicated and founded on the conduct of
DAMEPL, including the letters written by them, which had made it clear
that their participation in the conciliation proceedings, etc. were without
prejudice to their rights. There is force in the contention of DAMEPL that
the finding in the Award should not be re-appraised afresh.

63. DAMEPL had also drawn our attention to the DMRC application
dated 6th December, 2014 filed before the Arbitral Tribunal for interim
direction relying upon Articles 36.2.4 and 36.3.3 of the CA for directing
DAMEPL to operate and maintain AMEL and the assets till the arbitration
proceedings attained finality. The application was opposed. The aforesaid
Articles 36.2.4 and 36.3.3 read as under:-

FAO(OS)(COMM) No. 58/2018 Page 35 of 97

“36.2.4 No Suspension of Work
The reference to arbitration shall proceed notwithstanding that
Works shall not then be or be alleged to be complete, provided
always that the obligations of the DMRC, the Engineer and the
Concessionaire shall not be altered by reasons of arbitration being
conducted during the progress of Works. Neither party shall be
entitled to suspend the work to which the dispute relates on
account of arbitration and payments to the Concessionaire shall
continue to be made in terms of the Contract.

XXXXX
36.3.3 This Agreement and rights and obligations of the Parties
shall remain in full force and effect pending the Award in any
arbitration proceeding hereunder.”

64. DAMEPL had also relied upon Article 40.2 of the CA on the question
of waiver, which had stipulated that waiver in the observance and
performance of any provision or obligations and/or under the agreement
shall not be effective unless it is in writing and executed by duly authorized
representative of the parties.

65. DMRC had drawn distinction between waiver by election and waiver
by estoppel or promissory estoppel. The said distinction exists in law as
held in HIH Casualty and General Insurance Limited Vs. Axa
Corporation Solutions, 2001 WL 161 2576. Concept of waiver by election
involves a choice by the waiving party between two inconsistent courses of
action, which becomes applicable when there is a repudiatory breach of a
promissory warranty by one party and the other has a choice to accept the
breach as discharging the contract or waive it and affirm the contract. If the
party waives by election, the contract continues to be in force. Essence of
waiver by estoppel or promissory estoppel is to show willingness of the

FAO(OS)(COMM) No. 58/2018 Page 36 of 97
representor to forego his rights, which should be reasonably seen by the
other side. Reference in this regard can be also made to Motor Oil (Hellas)
Corinth Refineries S.A. v. Shipping Corp. of India, (1990) 108 N.R. 280
(HL), interpreting expression „waiver‟, in its different contours. Waiver, it
was observed, in a sense is abandonment of a right which arises by virtue of
a party making an election, which may arise when a state of affairs comes
into existence in which one party becomes entitled, either in terms of the
contract or by general law to exercise a right and he has to decide whether or
not to do so. Characteristically, this state of affairs arises where the other
party has repudiated the contract or has committed a breach if the contract,
which entitles the innocent party to bring it to an end, but the latter has made
a tender of performance which conform to the terms of the contract. If a
party with the knowledge of the fact, which has given rise to repudiation,
acts in a manner consistent only with treating the contract as still alive, he is
taken in law to have exercised his election to affirm the contract. The
election must be unequivocal.

66. The conduct of DAMEPL in commencing operations from 22nd
January, 2013, notwithstanding the earlier termination vide notice dated 8 th
October, 2012, would indicate their intent and desire to find an amicable
solution and resolve financial unviability as stated in communications dated
20th April, 2012 and 24th September, 2012 expressing DAMEPL‟s desire to
re-negotiating the terms, but it would be difficult to hold that the decision of
the Arbitral Tribunal on the issue of waiver is flawed and can be corrected in
limited jurisdiction and scrutiny under Section 34 of A C Act. Similarly,
the contention that use of words „without prejudice‟ in the communication

FAO(OS)(COMM) No. 58/2018 Page 37 of 97
and letters is inconsequential and does not require interference or rejection
of the findings in the Award. Reliance placed on Segal Securities Ltd. Vs.
Thoseby, 1963 Queen‟s Bench 887 on the question of tenancy law
applicable in England does not justify interference in exercise of power
under Section 34 read with Section 37 of the A C Act.

67. Looked from all angles and situations, we are not inclined to interfere
with the finding recorded in the Award rejecting the contention of DMRC
that DAMEPL had withdrawn or waived the termination notice.

Termination on ‘DMRC Event of Default’

68. As noticed above, DAMEPL had issued cure notice dated 9 th July,
2012 followed by termination notice dated 8th October, 2012.

69. Counsel for both sides had drawn our attention to Article 29 of the
CA under the heading “Termination for the Concessionaire event of
Default”. Relevant clauses of Article 29.1.1, which deals with DMRC’s right
to terminate, read as under:-

“29.1.1 Concessionaire Event of Default

The following events shall constitute an event of default by the
Concessionaire (a “Concessionaire Event of Default”) unless such
Concessionaire Event of Default has occurred as a result of DMRC
Event of Default or a Force Majeure Event;

XXXXX

(xi) The Concessionaire is in Material Breach of this Agreement or
any of the Project Agreements resulting in Concessionaire’s
incapacity to perform under this Concession Agreement to the
satisfaction of DMRC;

FAO(OS)(COMM) No. 58/2018 Page 38 of 97

XXXXX

(xiii) The Concessionaire abandons the operations of the Airport
Metro Express Line for more than 15 (fifteen) consecutive days
without the prior consent of DMRC, provided that the
Concessionaire shall be deemed not to have abandoned such
operation if such abandonment was (i) as a result of Force Majeure
Event and is only for the period such Force Majeure is continuing,
or (ii) is on account of a breach of its obligations by DMRC.

(xiv) The Concessionaire repudiates this Agreement or otherwise
evidences an intention not to be bound by this Agreement;

XXXXX

(xvi) The Concessionaire has delayed any payment that has fallen
due under this Agreement if such delay exceeds 90 (ninety) days.”

70. Article 29.1.2 empowers the DMRC to terminate the agreement by
issue of termination notice to the concessionaire if the concessionaire has
failed to cure such breach or default within the period provided in the CA.
However, before issuing termination notice, DMRC was obliged to issue
notice in writing to inform the concessionaire of its intent to issue
termination notice and grant 15 days time to the concessionaire to make
representation against such intended termination notice. Upon expiry of 15
days, whether or not any representation was received, DMRC had sole
discretion to issue termination notice. Article 29.1.3 is subject to Article
29.2 and stipulates that the DMRC could issue cure notice for any of the
defaults or breaches under the agreement asking the concessionaire to cure
the breach or default specified therein. Issue of cure notice would not
relieve the concessionaire from liability of damages caused by breach or

FAO(OS)(COMM) No. 58/2018 Page 39 of 97
default or extend the period of the CA. DMRC, however, had right to
extend the period during which the concessionaire was required to take
reasonable action to cure the defects. We shall subsequently refer to Article
29.4 as this clause is of some significance, when we deal with the question
of computation/calculation of termination made in the Award with reference
to termination payment payable on „DMRC Event of Default‟

71. Article 29.5 deals with „Termination of DMRC Event of Default‟ and
clauses (1) and sub-clause (i) thereof read as under:-

“29.5 Termination for DMRC Event of Default.

29.5.1 The Concessionaire may after giving 90 (ninety) days
notice in writing to DMRC terminate this Agreement upon the
occurrence and continuation of any of the following events (each a
“DMRC Event of Default”), unless any such DMRC Event of
Default has occurred as a result of Concessionaire Event of
Default or due to a Force Majeure Event.

(i) DMRC is in breach of this Agreement and such breach
has a Material Adverse Effect on the Concessionaire and
DMRC has failed to cure such breach or take effective steps for
curing such breach within 90 (ninety) days of receipt of notice
in this behalf from the Concessionaire;

             (ii)     xxx
(iii) xxx
(iv) xxx
(v) xxx"

Clause (1) states that the concessionaire may after giving 90 days
notice in writing to DMRC terminate the CA upon occurrence and
continuation of the events enumerated in sub-clauses (i) to (iv), which events
have been described as „DMRC Event of Default‟. There is also a
stipulation that „DMRC Event of Default‟ should not have occurred as a

FAO(OS)(COMM) No. 58/2018 Page 40 of 97
result of „Concessionaire‟s Event of Default‟ referred to above or due to
force majeure event. Sub-clause (i) of Article 29.5.1 states that DMRC
would be in breach of the agreement if the breach has 'material adverse
effect' on the concessionaire and DMRC has failed to cure such breach or
taken effective steps for curing such breach within 90 days of the receipt of
the notice in this behalf from the concessionaire. The expression 'material
adverse effect' has been defined in the CA to mean "material adverse effect
of any act or any event on the ability of either party to perform any of its
obligations under and in accordance with the provisions of this agreement".
Obligations of DMRC have been set out in Article 9 of the CA. Article 10
deals with the obligations of the concessionaire, i.e., DAMEPL.

72. The cure notice dated 9th July, 2012 states that DAMEPL had noticed
certain defects in DMRC‟s works, which were affecting performance
obligations of DAMEPL under the CA. A non-exhaustive list of defects
that had created unsafe conditions for performance of DAMEPL‟s
obligations under the CA were thereafter enumerated and read as:-

"i) Failure by the DMRC/Claimant to assume correct Super-
imposed Dead-load in its design;

ii) The Co-efficient of Dynamic augmentation (CDA)
assumed by the Claimant for longitudinal analysis in the Design
Basis Report‟

iii) The strengthening by the Claimant of all piers having
eccentric pier caps by jacketing of reinforced concrete;

iv) Non-adherence of the Design by the Claimant, such:

a) Non-adherence to design principles;

b) Non-compliance to dimensional requirements;

c) Non-compliance of material specifications; and

FAO(OS)(COMM) No. 58/2018 Page 41 of 97

d) Method Statements have not been prepared,
independently checked, approved and followed;

e) Defects in the U-Girder;

f) Defects in Pier Caps

v) The Claimant failed to ensure adequate gap between the
girders and the shear key, which has led to permanent flaw in the
civil structure;

vi) Twist in girder has led to permanent damage to girder;

vii) The cracks in the girder are relatable to inherent defect in
the design of the girder."

73. Notice states that DAMEPL had carried out inspections without
original and other relevant designs and drawings, which had not been
provided by DMRC. Defects in DMRC‟s work were not capable of being
noticed and identified at the time of taking over due to defaults of latent and
inherent nature. Preliminary investigation report had been prepared by an
internal team. Reference was made to the earlier letter dated 17 th May,
2012, report submitted by M/s Shirish Patel and Associates Consultants
Private Limited engaged by DAMEPL and observations of others on the
question of safety of passengers that were paramount. Hence, it was not
possible for DAMEPL to continue with the operation of trains in view of
defects to safeguard life and property of public at large. Defects in DMRC's
work had resulted in 'adverse material effect' as the situation had made the
operation highly unsafe with potential to cause loss of life and property
thereby severely impairing technical capabilities of DAMEPL. DMRC was
accordingly requested to take such actions or measures as were necessary to
completely cure the defects within 90 days, failing which there would be a
material breach and „DMRC Event of Default‟.

FAO(OS)(COMM) No. 58/2018 Page 42 of 97

74. Thereafter, DAMEPL had issued termination notice dated 8 th
October, 2012, which reads as under:-

"Ref: DAME/DMRC/2012/5107
Dated: 8th October. 2012

By Hand/Email
To,
Managing Director
Delhi Metro Rail Corporation,
Metro Bhawan,
Fire Brigade Lane,
Barakhamba Road New Delhi.

Project :Airport Metro Express Line Contract AMEL-P1

Subject : Termination Notice under the Concession
Agreement for High Speed Airport Metro Express Line
between New Delhi - Indira Gandhi International Airport

- Dwarka Sector 21 ("Project") consequent of upon
DMRC's Event of Default

Ref : a) Concession Agreement dated August 25, 2008
("Concession Agreement")

b) Our letter no. DAME/DMRC/2012/4728 dated
July 9, 2012 ("Notice to cure DMRC Events Of
Default")

c) DMRC's letter no. DMRC/20/1I/AP/P1 dated
August 3, 2012 ("DMRC‟s Reply")

d) Our letter no. DAME/DMRC/2012/5101 dated
October 5. 2012

Dear Sir,

FAO(OS)(COMM) No. 58/2018 Page 43 of 97
1.0 The Concessionaire writes in respect of the
captioned subject and the letters under reference
hereinabove

2.0 Notwithstanding anything that is alleged in
DMRC's Reply, the Concessionaire hereby repeats
and reiterates that it has duly complied with all its
obligations under the Concession Agreement and
maintenance manuals including in respect of the
conduct of regular inspections and undertaking of
repairs of the works which were its responsibility.

3.0 The Concessionaire submits that it was due to its
efforts and periodic inspections only that the
Defects could be detected. The Defects being
latent/inherent in DMRC Works were not capable
of identification at any point of time, including at
the lime of providing access of the Site to the
Concessionaire for carrying out the
Concessionaire‟s Works.

4.0 DMRC, despite receiving notifications and all
necessary and reasonable support from the
Concessionaire, has failed to cure the breach of its
obligations under the Concession Agreement
Including for the cure of the Defects, which have
resulted into the DMRC Events of Default.

5.0 A period of 90 (ninety) days has expired since the
issue of Notice to cure DMRC Events of Default,
and none of the DMRC Events of Default have
been cured.

6.0 In view of the above, the Concessionaire hereby
terminates the Concession Agreement under
Article 29.5.1 of the Concession Agreement.

FAO(OS)(COMM) No. 58/2018 Page 44 of 97

7.0 The exercise of its rights by the Concessionaire
concerning termination of the Concession
Agreement under Article 29.5 1 of the Concession
Agreement is without prejudice to its rights and
remedies available to it under the Concession
Agreement, law or in equity.

8.0 As the Concession Agreement is terminated due
to the DMRC Event of Default, the
Concessionaire is hereby immediately released
from all its obligations under the Concession
Agreement or any document forming part thereto.

9.0 In view of the termination of the Concession
Agreement and pursuant to the provisions of
Clause 29.5.2 of the Concession Agreement, the
Concessionaire hereby calls upon DMRC to pay,
by way of Termination Payment, an amount equal
to:

(a) Debt Due, which is Rs. 2.940 Crores (Rupees
Two Thousand Nine Hundred and Forty
Crores Only); and

(b) 130% of the Adjusted Equity, which is Rs.
130,000 (Rupees One Lakh and Thirty
Thousands Only)

within 7 (seven) days hereof.

10.0 In view of DMRC‟s failure to discharge its
functions and obligations in accordance with the
terms of the Concession Agreement and the
DMRC Events of Default, the Concessionaire has
suffered the revenue and other operational losses,
damages and expanses, and accordingly, the
Concessionaire hereby reserves its right to call
upon DMRC to indemnify the Concessionaire for

FAO(OS)(COMM) No. 58/2018 Page 45 of 97
all such revenue and other operational losses,
damages and expenses of whatsoever nature as per
the relevant provisions of the Concession
Agreement including Article 34.1(b) thereof, upon
its quantification.

11.0 The Concessionaire hereby also calls upon
DMRC to appoint its nominee and instruct him to
be present at a mutually convenient time to take-
over the possession of the Project Assets and the
inventory thereof. If DMRC fails to appoint its
nominee or agree upon a mutually convenient lime
within 7 days hereof, then the Project will be
vacated at the sole risk and liability of DMRC.
and the Concessionaire will not be responsible for
any form of risk or liability whatsoever in relation
to the Project Assets or any inventory forming part
thereof.

12.0 In the event DMRC fails, neglects or delays to
do the acts and things stated above, the
Concessionaire reserves right to initiate

appropriate legal actions at DMRC's risk as to
costs and consequences.

13.0 Nothing contained in this Termination Notice
shall be seen as a waiver of any of the
Concessionaire's rights or the obligations of
DMRC, under the Concession Agreement, of any
nature. The Concessionaire hereby reserves all its
rights and remedies against DMRC.

14.0 Unless otherwise defined herein, the
capitalized terms shall mean to have the same
meaning as ascribed to such term under the
Concession Agreement or under the Notice to cure
DMRC Events of Default."

FAO(OS)(COMM) No. 58/2018 Page 46 of 97

Notice was not specific on failures albeit had simply eluded to
latent/inherent defects in DMRC‟s work that had not been cured despite
notification and DAMEPL‟s support. CA was terminated with immediate
effect.

75. As per DMRC in terms of Article 29.5.1 DAMEPL should have given
90 days‟ notice in writing to DMRC setting out its intention to terminate the
CA, post and in addition to the cure notice of 90 days to constitute „DMRC
Event of Default‟. For valid termination under Article 29.5.1 the default by
DMRC in the form of failure to cure or take effective steps to cure was
"upon occurrence and continuation" till the date of termination. The period
postulated in Article 29.5.1 was 90 days plus 90 days and then and then
alone on DMRC's failure to cure or take effective steps, there would be
„DMRC‟s Event of Default‟. Specific emphasis was laid on the words "The
Concessionaire may after giving 90(ninety) days notice......upon
occurrence and continuation of any of the following events......(i) DMRC
has failed to cure such breach or take effective steps for curing such breach
within 90 (ninety) days". DMRC also relies upon letter dated 21st January,
2013, written by DAMEPL in which they had stated that termination would
be effective after 90 days of cure notice plus 90 days of the termination
notice. Notice of termination dated 8th October, 2012 was invalid as it had
terminated the CA with immediate effect.

76. Our attention was specifically drawn to paragraph 78 in heading
"Summary of Arbitral Tribunal‟s view" quoted in paragraph 40 above,
which states that DMRC had failed to cure any breach as it had failed to
take effective steps within 90 days of the notice dated 8th July, 2012 to

FAO(OS)(COMM) No. 58/2018 Page 47 of 97
rectify and cure cracks at the bottom of the girders, twist in the girders, gaps
between the girders and between the girders and the shear key. It was
observed that such breach had „material adverse effect‟ on DAMEPL. As
such ingredients of Article 29.5.1 of CA were satisfied. Therefore, the
Award records in paragraphs 77 and 78 that termination notice given by
DAMEPL on 8th October, 2012 was valid. The aforesaid finding, it was
highlighted, contradicted subsequent findings on termination date recorded
by the Arbitral Tribunal in paragraphs 128, 130 and 131 of the Award.
Contention of DMRC is that two different dates of termination of CA
consequent to DMRC‟s „Event of Default‟ have been mentioned in the
Award.

77. We have already quoted paragraph 78 of the Award, which states that
the DMRC had failed to take effective steps to cure the breach within 90
days of the notice dated 9th July, 2012 and as such ingredients of Article
29.5.1(i) of the CA were satisfied. Termination notice issued on 8th October,
2012, effective immediately was valid. Paragraph 115 records that the
Arbitral Tribunal had already concluded in paragraph 78 that termination
notice dated 8th October, 2012 was valid. Accordingly, the counter claims
of DAMEPL were being considered. Ex facie the CA could not have been
terminated with immediate effect from the date of termination notice.
DAMEPL would not even contend to the contrary.

78. Paragraphs 128, 130 and 131 of the Award read as under: -

"128. The other component of Termination Payment is "Debt
due". "Debt due" comprises of two elements i.e. Rupee term loan
and External commercial borrowing (in foreign currency). For the
loan received and repaid, we have relied upon the information

FAO(OS)(COMM) No. 58/2018 Page 48 of 97
submitted by DAMEPL through their advocates vide letter no.
DJK/HM/1208 dtd. 01.12.2014. In the absence of definition of
"Transfer Date" in the CA, we have taken the date of termination
i.e. 07.01.2013 as the reference date for the calculation of the
"Debt due".

XXXXX
"130. Prayer (b) of the Counter Claim
DAMEPL has contended that after termination of the CA
from 07.01.2013, they were asked to run the line which they
continued up to 30.06.2013.....

Therefore , DAMEPL is entitled to Rs. 147.52 Crores
against this counter claim...."

''131. Prayer (c) of the Counter Claim
DAMEPL has contended that it has been servicing the debt
after handing over of the line on 01.07.2013 to DMRC. In CC-5,
it has claimed that an amount of Rs.104.41 crores have been paid
by DAMEPL during the period 01.07.2013 till 30 th November,
2013. DAMEPL has further claimed interest from the date of
filing claim till the date of actual payment at the rate of 18% p.a.
DAMEPL has led the evidence of Ms. Neena Goel who has
examined the records and verified the figures. This evidence has
not been challenged by DMRC nor any counter evidence led.

Tribunal has examined the above claim and is of the view
that the interest allowed in the claims at Annexure CC-1 and CC-3
substantially covers the interest paid by DAMEPL for debt
servicing.

As such, this prayer is a duplication and, hence, not
granted."

FAO(OS)(COMM) No. 58/2018 Page 49 of 97

The aforesaid paragraphs have taken the date of termination of CA as
7th January, 2013. Arbitral Tribunal had also held that DAMEPL was liable
to pay concessionaire fee till 7th January, 2013.

79. Date of termination is crucial as clause (i) to Article 29.5.1 mandates
that the DMRC should have cured the defects or taken effective steps to
cure the defects within the period specified upon occurrence and
continuation of the breach. DMRC‟s failure to cure or take effective steps to
cure the breach upon occurrence and continuation till termination date
constitutes „DMRC Event of Default‟. Confusion and lapse vide aforesaid
contradiction on the termination date as 8th October, 2012 and also as 7th
January, 2013 is obvious and glaring in the face of the Award. Paragraphs
128, 130 and 131 do hold that the effective date of termination was 7 th
January 2013. This could materially change outcome of the findings
recorded by the Arbitral Tribunal.

80. Faced with the aforesaid position, DAMEPL have submitted that
DMRC had not pleaded or argued that the cure period was 90 days plus 90
days and this argument is an afterthought and was raised before the learned
single Judge for the first time. DMRC was required to cure the defects or
take effective steps to cure the defects within 90 days from the date of
DAMPEL‟s letter dated 9th July, 2012 and were not entitled to another
period of 90 days after termination notice dated 8 th October, 2012. This was
not what is postulated under Article 29.5.1 (i) of the CA.

81. In the written submissions, it is also stated that the Arbitral Award
has considered the entire period including the period upto 7 th January, 2013
to examine and conclude whether the defects had been cured or effective

FAO(OS)(COMM) No. 58/2018 Page 50 of 97
steps had been taken to cure the defects. (See paragraph 44 at page 65 of the
written submissions.)

82. In other words, DAMEPL in the written submissions in alternative
has taken the effective date for the purpose of clause (i) to Article 29.5.1 as
7th January, 2013. However, this is not what the Arbitral Tribunal has held
in the first part of the award, including paragraphs 78 and 115 quoted above.
DAMEPL has not explained and justified the reason for the two dates.

83. DMRC has submitted that the contention is not an afterthought and
was raised before Arbitral Tribunal. Reference was made to the written
submissions filed by the DMRC before the Arbitral Tribunal dated 24 th
November, 2016, wherein it was submitted:-

"35. The issuing of termination notice on 8th October, 2012
itself was against the provision of above mentioned provision of
Concession agreement because even if it is assumed that DMRC
Event of Default had occurred under CA or was in continuation in
the opinion of Respondent, still they were not entitled to terminate
the Concession Agreement on 8th October, 2012. They were only
entitled to issue 90 days notice for termination."

84. Similar written submissions on the said aspect made before the single
Judge, read :-

"xxvii. That issuing of termination notice on 8th October, 2012
itself was against the provision of above mentioned provision of
CA because even if it is assumed that DMRC Event of default had
occurred under CA or was in continuation in the opinion of
Respondent, still they were not entitled to terminate the CA on 8 th
October, 2012."

85. We cannot decide this controversy except by referring to the Award,
which does not interpret Article 29.5.1(i) of the CA with specific reference

FAO(OS)(COMM) No. 58/2018 Page 51 of 97
to a period of 90 or 180 days. Nevertheless, the Award does record
confusing and contradictory stances on termination and has predicated its
reasoning in different parts of the Award on two different dates, without
elucidating which date (8th October,2012 or 7th January, 2013) has been
taken as the basis for deciding failure to cure or take effective steps to cure
the defects. We are therefore left baffled and confused as to the date of
termination and the cut off date taken by the Arbitral Tribunal for deciding
„DMRC Event of Default‟.

86. We have already quoted the relevant portion of the Award vide
heading „H‟ dealing with the contention of the DMRC on CMRS approval
dated 18th January, 2013 to re-commence AMEL operations, which DMRC
submits is perverse, illogical and also contrary to law/statute. We would
examine this contention below. At this stage we observe that the Arbitral
Tribunal has not held that the certification/sanction dated 18 th January, 2013
was not relevant as the date for determining „DMRC Event of Default‟ was
8th October, 2012 and not 7th January, 2013. This would indicate as has been
stated by DAMEPL in „alternative‟ that Arbitral Tribunal had taken 7th
January,2013 as the relevant date for Article 29.5.1 of the CA.

87. The Award in paragraph 107 quotes CMRS sanction dated 18 th
January, 2013, which records that repairs of all bearings used in U girders
and cracks in some soffit of some of U girders have been carried out and the
situation was stable. However, the repairs were required to be monitored, to
ensure that the position remained stable. DMRC was directed to carry out
routine inspection, operation and maintenance. Permission to operate
AMEL at 50 kilometres per hour was granted with right to increase the

FAO(OS)(COMM) No. 58/2018 Page 52 of 97
speed till 80 kilometres per hour in steps of 10 kilometres per hour at a time
on personal inspection, satisfaction, certification of conditions specified by
the Director (W) DMRC. For increase in speed beyond 80 kilometres per
hour, DMRC was to approach the CMRS for sanction with adequate
justification.

88. The Arbitral Tribunal after recording the said position rejected the
contention of DMRC observing that AMEL was to serve as a high-speed
connectivity and severe speed restrictions were imposed by CMRS. It did
not examine the issue, and question and answer how and in what way the
speed restrictions imposed would amount to 'material adverse effect' on
DAMEPL as defined in the CA. Findings in paragraphs 77 and 78 refer to
defects in girders etc. and failure to cure the defects. Speed restrictions were
not treated as „material adverse effect‟. Findings in paragraph 108 on the
other hand state that notwithstanding the clearance and statutory certification
given by CMRS, the prime purpose of the project was high speed
connectivity which was not possible to comply with the speed restrictions.
This was not the ground or reason given in either the cure notice or the
termination notice. How and why speed restriction would have prevented
DAMEPL from performing their obligation in the CA to constitute „material
adverse effect‟ is neither stated nor elucidated and explained by reasoning.
The question whether speed restriction as imposed would justify the
termination of the CA should have been debated and answered after due
deliberation on facts put forth by both sides. Factual assertions and counters
were argued before us, but we refrain from making any comments as the
Award is silent and has not examined the facts and given reasons.

FAO(OS)(COMM) No. 58/2018 Page 53 of 97

89. Relevant provisions of the Metro Act read:-

"7. Appointment of commissioner of Metro Rail safety

-The Central Government may appoint one or more
Commissioners of Metro Railway Safety.

8. Duties of Commissioner- The Commissioner shall -

(a) inspect the metro railway with a view to, determine
whether it is fit to be opened for the public carriage of
passengers and report thereon to the Central Government
as required by or under this Act;

(b) make such periodical or other inspections of metro
railway, its rolling stock used thereon and its other
installations as the Central Government may direct;

(c) make an inquiry under the provisions of this Act
into the cause of any accident on the metro railway; and

(d) discharge such other duties as are conferred on
him by or under this Act."

9. Powers of Commissioner -Subject to the control of the
Central Government, the commissioner, Whenever it is
necessary so to do for any of the purposes of this Act,
may-

(a) enter upon and inspect the metro railway or any
rolling stock used thereon, and its other installations;

(b) by order in writing addressed to the metro
railway administration, require the attendance before him
of metro railway official and to require answers or returns
such inquiries as he thinks fit to make from such metro
railway official or from the me railway administration;
and

FAO(OS)(COMM) No. 58/2018 Page 54 of 97

(c) require the production of any book, document or
material object belonging to or in the possession or
control of any metro railway administration which
appears to him to be necessary to inspect.

XXXXX

14. Sanction of Central Government to the opening
of metro Railway-The metro railway in the
metropolitan city of Delhi shall not be opened for the
public carriage of passengers except with the previous
sanction of the Central Government.

15. Formalities to be complied with before giving
sanction to the opening of Metro Railway-(1) The
Central Government hall(sic), before giving its sanction
to the opening of the metro railway under section 14,
obtain a report from the Commissioner that-

a. he has made a careful inspection of the metro railway
and the rolling stock that may be used thereon;
b. the moving and fixed dimensions as laid down by the
Central Government have not been infringed;
c. the track structure, strength of bridges, standards of
signaling system, traction system, general structural
character of civil works and the size of, and maximum
gross load upon, the axles of any rolling stock, comply
with the requirements laid down by the Central
Government; and
d. in his opinion, metro railway can be opened for the
public carriage of passengers without any danger to the
public using it.

(2) If the Commissioner is of the opinion that the metro
railway cannot be opened without any danger to the
public using it, he shall, in his report, state the grounds
therefor, as also the requirements which, in his opinion,

FAO(OS)(COMM) No. 58/2018 Page 55 of 97
are to be complied with before sanction is given by the
Central Government.

(3) The Central Government after considering the report of
the Commissioner, may sanction the opening of the metro
railway under section 14 as such or subject to such
conditions as may be considered necessary by it for the
safety of the public.

XXXXX

21. Delegation of Powers - The Central Government
may, by notification, direct that any of its powers or
Delegation of functions under this Chapter, except power
to make rule under section 22, shall, in relation such
matters and subject to such conditions, if any, as may be
specified in the notification, be exercised or discharged
also by the Commissioner."

90. CMRS is appointed under Section 7 of the Metro Act and its duties as
enumerated in Section 8 include duty to inspect metro railway with a view to
determine whether it is fit to open for public carriage, conduct periodical or
other inspection of metro lines when directed by the Central Government
and discharge such other duties as are conferred. To enable CMRS to
perform its duties, it is vested with powers under Section 9. CMRS has to
prepare annual report of its activities and such annual reports are laid before
the Parliament as per Sections 12 and 13 of the Metro Act. Metro
line/railway in terms of Section 14 cannot be opened for public carriage of
passengers except with the pervious sanction of the Central Government.
Section 15 mandates that the Central Government before giving its sanction
shall obtain report from CMRS on aspects referred to in clauses (a) to (d).

FAO(OS)(COMM) No. 58/2018 Page 56 of 97

Section 21 states that the Central Government by a notification may delegate
any of its powers except power to make Rules.

91. The Opening of Delhi Metro Railway for Public Carriage of
Passenger Rules, 2002 as enacted, on power and authority of CMRS
including those delegated to him by the Central Government, state:-

―Rule 4: "Supply of documents to the
Commissioner. -- (1) The Chief Executive Officer
shall, while making reference to the Commissioner for
inspection and report on the safety of the metro
railway under sub-rule (2) or rule 3, furnish all
relevant documents to the Commissioner from the
following list of documents, namely;--

            (a)       Tabulated details;
(b) Index plan and sections;
(c) drawings of works;
(d) Certificate;
(e) List of infringements of moving and fixed
dimensions;
(f) Working orders to be enforced at the

operations control centre and at each station.

(g) Administrative note giving salient features of
the project.

(2) The documents referred to in sub-rule (1) shall indicate
the distances from the same fixed point in kilometers
and decimals up to two digits and the fixed point shall
be clearly defined in a note on the plant and section
sheets of the work documents.

(3) The datum adopted shall be mean sea level as fixed by
the Survey of India and heights shall be mentioned
with reference to the datum in metres and decimals up
to two digits.

FAO(OS)(COMM) No. 58/2018 Page 57 of 97

(4) The documents referred to in sub-rule (1) shall be
signed by atleast an officer equivalent to senior
administrative grade rank except the certificate which
shall be signed by the Chief Executive Officer himself.

(5) The Chief Executive Officer shall furnish such
documents to the Commissioner, as far as possible, at
least one month in advance of the stipulated date of
inspection."

Rule 5: "Contents of documents .--(1) Tabulated
details which shall consist of important characteristics
of the metro railway or a portion thereof to be opened
for public carriage of passengers, and in particular shall
include --

         a)    Curve abstract as specified in Form I ;
b) Gradient abstract as specified in Form ll ;
c) Bridge abstract as specified in Form III ;
d) Viaduct abstract as specified in Form IV ;
e) Important bridges abstract as specified in Form V ;
f) Ballast and permanent way abstract as specified in
Form VI;
g) Stations and station sites as specified in Form VII;
h) Brief particulars of rolling stock as specified in Form
VIII ;
I) Brief particulars of traction installations as specified
in Form IX ;
J) power supply installation abstract as specified in
Form X ;
K) Restricted Over Head Equipment clearances
abstract as specified in Form XI ;

(l) Electrical crossings over metro railway tracks as
specified in Form XII ;

FAO(OS)(COMM) No. 58/2018 Page 58 of 97

(m) Traction maintenance depot abstract as specified in
Form XIII;

(n) Ventilation, smoke management and fire safety
measures in tunnels and stations as specified in Form
XI V; and

(o) Signalling and train control installations as per sample
in Form XV.

(2) Index plan and section sheets, completion
drawings, etc., shall include ,--

(a) Index plan and section sheets as mentioned in
the Schedule;

(b) Completion drawings of bridges / viaducts
showing details of structure, loading standards
adopted, etc.

(c) Completion drawing of tunnels, if any;

(d) Diagrammatic plan of station yards showing
layout of tracks and particulars of turn outs,
gradients, of any signals and interlocking installed;

             and
(e) Implementation diagrams of overhead

equipment masts/ overhead current collection system
as applicable.

             (3)    The comments on the following matters,
namely:--

(a) Moving and fixed dimensions;
(b) Strength of bridges / viaducts;
(c) Brake and communication;
(d) System of working;
(e) Electric traction equipment; and

FAO(OS)(COMM) No. 58/2018 Page 59 of 97
(f) Type of rolling stock, proposed along with list of

restrictions, shall be contained in the certificate in
Form XVI.

(4) List of infringements of moving and fixed dimensions
shall be prepared as specified in Form XVII and shall
contain full explanations for the infringements and
restrictions or precautions to be adopted because of
them and the reference to the authority of the Central
Government under which the infringement is permitted
for allowed.

(5)Working orders to be enforced at each station on the
metro railway to be opened shall be prepared in
accordance with the provisions of the Delhi Metro
Railway General Rules, 2002 and shall specify any
special conditions that are required to be met with and
such orders shall include working rules."

XXXXX

Rule 22:"Sanction to open metro railway. -

(1) The Central Government may, after considering
the report submitted under Rule 21 by the
Commissioner, sanction the opening of the Delhi metro
railway or a portion thereof as the case may be, under
Section 14 of the Ordinance as such or subject to such
conditions as may be considered by it for the safety of
the public.

(2) The Chief Executive Officer shall publish the date
of opening of Delhi metro railway or a portion thereof
for public carriage of passengers in the local
newspapers both in English and Hindi languages.

FAO(OS)(COMM) No. 58/2018 Page 60 of 97

Rule 23: "Opening of a metro railway by the
Commissioner. -

(1) The Commissioner may also sanction opening of Delhi
metro railway for public carriage of passengers, subject
to such conditions as he may impose in the interest of
the passengers. While giving sanction to the opening of
metro railway, he will, however, forward his inspection
report to the Central Government:

(2) On receipt of the inspection report of the
Commissioner, the Central Government may confirm,
modify or cancel the sanction given under sub-rule (1)
subject to such conditions, alterations or relaxation as
may be considered necessary."

92. CMRS performs statutory functions and duties under Sections 9 and
10 of the Metro Act. Under Rule 23 CMRS may also sanction opening of
Delhi metro railway for public carriage of passengers. CMRS as the
technical expert is vested with authority and power to decide on the safety of
the metro tracks/lines, opening and operations of metro tracks/lines and
empowered to suspend traffic, close metro line/station and re-open metro
line/station previously open to public carriage, etc.

93. Safety of metro line is a matter of public importance and therefore
statutory sanction/permission under the Metro Act is required. Certification
or permission is granted by way of administrative act under the statute and in
exercise of statutory power. The certification cannot be challenged or
questioned in the arbitration proceedings. Arbitrators cannot go into validity
of the said sanction. Certificate is factually and legally binding as far as
Arbitral Tribunal is concerned. DAMEPL, in fact, does not contend and has

FAO(OS)(COMM) No. 58/2018 Page 61 of 97
not argued to the contrary. The legal position in this regard is well-settled
(see U.P. State Electricity Board versus Banaras Electricity Light and
Power Company Limited, (2001) 7 SCC 637, Haryana Telecom Limited
versus Sterlite Industries (India) Limited, (1999) 5 SCC 688 and Booz
Allen versus SBI Home Finance, (2011) 5 SCC 532).

94. Thus, the Arbitral Tribunal was required to treat and give legal effect
to the sanction and permission accorded for public carriage of passengers
vide CMRS certificate of fitness dated 18th January, 2013.
Sanction/permission was given after examining the civil structure be it
cracks, twists and gaps in the girders, which were not found to be
compromising fitness and safety for public use. Conspicuously, the Arbitral
Tribunal did not consider the legal effect and consequence of the
permission/sanction accorded by the CMRS in the first portion of the Award
recorded in the summary of arbitral views in paragraphs 77, 78 and
paragraph 115 of the Award. Grant and effect of sanction/permission
accorded by CMRS dated 18th January, 2013 was ignored and bypassed.

95. The aforesaid error in the impugned Award has occurred because the
legal issue "H" has been determined and decided separately, whereas it
should have been decided and considered in the first portion of the Award
with reference to the validity of termination. Even the legal issue „H‟-Did
the issue of certificate by CMRS show that the defects were duly cured-; the
answer to which was obvious yes, was not answered.

96. Argument of DAMEPL that compliance of the obligations in the CA
and grant of sanction by CMRS for re-commencement of operations are two
separate issues is ex facie incorrect and unacceptable. Submission has to be

FAO(OS)(COMM) No. 58/2018 Page 62 of 97
rejected for the simple reason that issue of sanction by CMRS directly
relates to whether or not the defects in the viaducts had been repaired or
effective steps for repair had been undertaken by DMRC. Permission
certifies to safety and fitness of repairs that were undertaken for
commencement of commercial passenger operations of the AMEL. The
Arbitral Tribunal has also obviously erred in not accepting and taking into
consideration the factum that the line was operationalized and put to use
continuously after DAMEPL had recommenced operations from 22nd
January, 2013 till 30th June, 2013. Thereafter, DMRC had continued to
operate the line till the Award was pronounced on 11th May, 2017. The fact
that speeds were increased from time to time and numbers of trips and
passengers had increased were spurned and discarded. During this period of
over four years there were no problems, issues and even one accident. This
is too obvious and apparent to have been ignored and treated as
inconsequential.

97. In view of the aforesaid discussion, the following position emerges:-

       (i)     DAMEPL was incurring losses.
(ii) DAMEPL had written to DMRC for deferment of payment of

concessionaire fee and re-structuring of the CA.

(iii) DMRC had rejected the prayers.

(iv) DAMEPL had operated AMEL from 23rd March, 2011 till 8th
July, 2012. During this period, there were no accidents and
damage to life and property.

(v) DAMEPL stopped operations in view of cracks and defects in
the girders, bearings, etc. with effect from 8th July, 2012.

FAO(OS)(COMM) No. 58/2018 Page 63 of 97

(vi) DAMEPL had issued cure notice dated 9th July, 2012 calling
upon DMRC to rectify the „defects‟ within a period of 90 days.

(vii) On 8th October, 2012, DAMEPL had terminated the CA with
immediate effect.

(viii) On 2nd July, 2012, Ministry of Urban Development had
convened meeting of the stakeholders, including DMRC and
DAMEPL on the question of defects in the civil structure,
bearings, etc. Several meetings were held.

(ix) Repairs and rectification work were undertaken with
involvement of consultants. Trial runs were also done and a
joint application for re-opening the line was made to CMRS.
DAMEPL had participated in the said meetings without
prejudice to their rights.

(x) On 18th January, 2013, CMRS had granted
permission/certification for re-starting AMEL.

(xi) DAMEPL thereupon has started operations on the line from
22nd January, 2013. Operation continued till 30th June, 2013.

(xii) DMRC has been thereafter operating and maintaining AMEL
since 1st July, 2013. No accident and damage to life and
property has been reported and alleged in the period from 22nd
January, 2013 till the Award dated 11th May, 2017.

(xiii) The sanction/permission granted by CMRS was in terms of the
Metro Act and the Rules. It is a statutory sanction not
amenable to challenge in arbitration.

(xiv) Notwithstanding the aforesaid sanction/approval, the Arbitral
Tribunal has held that DMRC had not taken steps to cure the

FAO(OS)(COMM) No. 58/2018 Page 64 of 97
structural defects and, therefore, „DMRC Event of Default‟
under Article 29.1.1 of the CA had occurred. Defects in
girders, etc. had caused „material adverse effect‟ on
DAMEPL‟s performance of obligations in the CA.

(xv) While deciding the said issue, the Arbitral Tribunal did not take
into consideration the permission granted by CMRS. The
certification given by CMRS was ignored and bypassed.
Similarly, unhindered actual commercial operations of AMEL
of over four years have not been adverted to and examined.
(xvi) Arbitral Tribunal has given two conflicting effective dates of
termination. In the first portion of the Award, they have
upheld the termination notice dated 8th October, 2012, which
had immediately terminated the CA. In the second portion of
the Award, they have taken the date of termination of CA as 7 th
January, 2013. Thus, the Arbitral Award on the date of
termination is ambivalent if not contradictory.

(xvii) CMRS certificate was separately dealt with in Ground „H‟.

Arbitral Award holds that sanction/certification by CMRS
dated 18th January, 2013 was inconsequential as there was
restriction with upper speed limit of 50 KMPH to start with,
whereas AMEL was to serve as high speed connectivity line.
Further, rigorous monitoring was required. Arbitral Tribunal
did not answer legal issue „H‟- Did the issuance of certificate
by CMRS show that the defects were duly cured?

(xviii)Similarly, in Ground „H‟ it has been held that subsequent
operation of the line by DAMEPL and DMRC from 23rd

FAO(OS)(COMM) No. 58/2018 Page 65 of 97
February, 2012 till the date of Award in November,2017 was
inconsequential.

(xix) Award does not hold that the speed restriction imposed with
certification dated 18th January,2012 had „adverse material
effect‟ on DAMEPL‟s obligations in the CA.

98. In the light of the aforesaid discussion, we would hold that the
impugned Award suffers from perversity, irrationality and patent illegality in
the face of the Award in the form of confusion and ambivalence as to the
termination notice and the date of termination. Most importantly, the
Arbitral Tribunal had ignored and did not consider vital evidence of
certification for commercial operations accorded by CMRS while deciding
the question of civil structure faults and in holding that no effective steps to
cure the defects were taken. Reasoning virtually over-rules, negates and
rejects statutory certification accorded by CMRS. Arbitral Tribunal without
„reason‟ has held that the permission accorded and subsequent satisfactory
commercial operations were not relevant and inconsequential. Pertinently
certification/permission was granted by CMRS after due verification of the
civil structure including the defects in girders. Certification by CMRS was
binding and its validity was not capable of „submission to arbitration‟.
Cumulative effect of the aforesaid discussions is that the Award shocks
conscience of the Court. Consequently, the Award on the said finding
would falter and fail on the tests and parameters elucidated in Associate
Builders versus Delhi Development Authority, (2015) 3 SCC 49, a
judgment is cited and relied by both the sides. The decision holds that
Section 5 of the AC Act bars Courts from intervening with the arbitration

FAO(OS)(COMM) No. 58/2018 Page 66 of 97
award governed by Part-I, except on the grounds mentioned in Sections
34(2) and (3) of the AC Act, which (including sub-section 2A) read as
under:-

               "34. Application      for   setting   aside   arbitral
award.--

XXXXX

(2) An arbitral award may be set aside by the Court
only if--

(a) the party making the application furnishes proof
that--

(i) a party was under some incapacity, or

(ii) the arbitration agreement is not valid under the
law to which the parties have subjected it or, failing
any indication thereon, under the law for the time
being in force; or

(iii) the party making the application was not given
proper notice of the appointment of an arbitrator or of
the arbitral proceedings or was otherwise unable to
present his case; or

(iv) the arbitral award deals with a dispute not
contemplated by or not falling within the terms of the
submission to arbitration, or it contains decisions on
matters beyond the scope of the submission to
arbitration:

Provided that, if the decisions on matters
submitted to arbitration can be separated from those
not so submitted, only that part of the arbitral award

FAO(OS)(COMM) No. 58/2018 Page 67 of 97
which contains decisions on matters not submitted to
arbitration may be set aside; or

(v) the composition of the arbitral tribunal or the
arbitral procedure was not in accordance with the
agreement of the parties, unless such agreement was
in conflict with a provision of this Part from which
the parties cannot derogate, or, failing such
agreement, was not in accordance with this Part; or

(b) the Court finds that--

(i) the subject-matter of the dispute is not capable of
settlement by arbitration under the law for the time
being in force, or

(ii) the arbitral award is in conflict with the public
policy of India.

Explanation 1--For the avoidance of any doubt, it is
clarified that an award is in conflict with the public
policy of India, only if,--

               (i)     the making of the award was induced or
affected by fraud or corruption or was in
violation of section 75 or section 81; or

(ii) it is in contravention with the fundamental
policy of Indian law; or

(iii) it is in conflict with the most basic notions of
morality or justice.

Explanation 2--For the avoidance of doubt, the test
as to whether there is a contravention with the
fundamental policy of Indian law shall not entail a
review on the merits of the dispute.

FAO(OS)(COMM) No. 58/2018 Page 68 of 97

(2A) An arbitral award arising out of arbitrations
other than international commercial arbitrations, may
also be set aside by the Court, if the Court finds that
the award is vitiated by patent illegality appearing on
the face of the award:

Provided that an award shall not be set aside
merely on the ground of an erroneous application of
the law or by re-appreciation of evidence.

(3) An application for setting aside may not be made
after three months have elapsed from the date on
which the party making that application had received
the arbitral award, or, if a request had been made
under section 33, from the date on which that request
had been disposed of by the arbitral tribunal:

Provided that if the Court is satisfied that the
applicant was prevented by sufficient cause from
making the application within the said period of three
months it may entertain the application within a
further period of thirty days, but not thereafter."

99. Explaining the expression "public policy in India" in Associate
Builders (supra), the Supreme Court referred to their earlier judgments in
Renusagar Power Company Limited versus General Electric Company,
1994 Supp (1) SCC 644, ONGC Limited versus Saw Pipes Limited, (2003)
5 SCC 705, Hindustan Zink Limited versus Friends Coal Carbonisation,
(2006) 4 SCC 445, McDermott International Inc. versus Burn Standard
Company Limited, (2006) 11 SCC 181, Centrotrade Minerals Metals
Inc. versus Hindustan Copper Limited, (2006) 11 SCC 245, DDA versus
R.S. Sharma and Company, (2008) 13 SCC 80, J.G. Engineering (P)
Limited versus Union of India, (2011) 5 SCC 758, Union of India versus

FAO(OS)(COMM) No. 58/2018 Page 69 of 97
Col. L.S.N. Murthy, (2012) 1 SCC 718 and thereafter had under the specific
heading "Fundamental Policy of Indian Law" with sub-headings "Interest of
India, „Justice‟ or „Morality‟ and "Patent Illegality" laid down specific
parameters and principles, which are applicable while examining petitions
under Section 34 of the AC Act. The juristic principle of a „judicial
approach‟ demands that the decisions should be fair, reasonable and
objective. Accordingly, on the observe side, anything which is arbitrary or
whimsical would not be determination, which would be fair, reasonable or
objective. This implies fair and equal treatment to parties and adherence to
the principles of audi alteram partem. Another juristic principle is that the
decision/award should not be perverse or irrational, i.e. findings based on no
evidence, or the arbitral tribunal takes into account something irrelevant to
the decision or ignores the vital evidence in arriving at the decision. This
principle would also apply when the finding outrageously defies logic.
Arbitration award is perverse and irrational if no reasonable person would
have arrived at the same decision. However, the courts must exercise
caution and not treat themselves as court of appeal and consequently correct
errors of fact for the Arbitrator is the ultimate master of quantity and quality
of evidence. Sub-section (2A) states and requires that patent illegality
should be appearing on the face of the award. Re-appreciation of evidence
is not permitted and should not be undertaken. An award based on little or
no evidence which does not measure in quality to a trained legal mind would
not be held to be invalid on this score. Under the heading „Justice‟ it was
observed that an award can be said to be against justice, when it shocks the
conscience of the Court. Thereafter, the Supreme Court dealt with the
concept and ground of „morality‟ as distinct and separate from „justice‟.

FAO(OS)(COMM) No. 58/2018 Page 70 of 97

Under the heading „Patent Illegality‟ reference was made to Section 28(1)(a)
and (3), which requires the Arbitral Tribunal to decide arbitration in
accordance with the substantive law for the time being in force and in
accordance with the terms of the contract and to take into account usages of
the trade applicable to the transaction. The last principle, it was observed,
must be understood with the caveat that the Arbitrator can construe the terms
of the contract in a reasonable manner. Construction of the terms of the
contract is primarily for the Arbitrator to decide. The Courts would only
interfere when the Arbitrator construed the contract in a way that it can be
said that no fair minded or reasonable person would do.

100. In the aforesaid background, we are not examining the issue whether
the earlier cure notice dated 9th July, 2012 was bad and contrary to law as it
was indeterminate and not specific. However, we would record that the
DMRC had submitted that the cure notice under law must be exhaustive and
specific and not vague and unspecific. Reliance was placed upon judgments
in Heisler versus Anglo Dal Limited, [1954] 1 W.L.R. 1273 and Glencore
Grain Rotterdam BV versus Lebanese Organisation for International
Commerce, [1997] C.L.C. 1274.

Computation of the amount due under Article 29.5.2

101. DMRC has challenged inclusion of Rs.611. 95 crores in equity to
compute adjusted equity and award of Rs. 983.02 crores as 130% of adjusted
equity as termination payment due on DMRC‟s „Event of Default‟ under
Article 29.5 of the CA.

102. Article 29.5.2 reads as under:-

FAO(OS)(COMM) No. 58/2018 Page 71 of 97

"Upon termination by the Concessionaire on account of DMRC
Event of Default, DMRC shall pay to the Concessionaire, by way
of Termination Payment, an amount equal to

a) Debt due;

b) 130% of the Adjusted Equity; and

c) Depreciated Value of the Project Assets, if any, acquired and
installed on the Project after the 10th anniversary of the COD."

The aforesaid clause states that the termination on account of „DMRC Event
of Default‟, DMRC shall be liable to pay DAMEPL by way of termination
payment an amount equal to the debt due and 130% of the adjusted equity.
Clause (c) relating to depreciated value of the assets, if any, acquired and
installed after 10th anniversary of COD, in this case does not apply. Article
29.5.2 draws a distinction between debt due and equity. In case of debt due
no enhancement is given and the actual amount of debt due is paid. In case
of equity, „adjusted equity‟ enhanced to 130% is payable. Expressions debt
due, equity and adjusted equity have been defined in the CA and quoted and
interpreted below.

103. We must also reproduce Article 29.4 which applies on
„Concessionaire‟s Event of Default‟ in which case DMRC is liable to pay an
amount equal to 80% of the debt due. No amount is payable on account of
equity/adjusted equity to DAMEPL in case of „Concessionaire‟s Event of
Default‟. Article 29.4 reads as under: -

"29.4 Upon Termination by DMRC on account of a
Concessionaire‟s event of Default during the Operations
Period, DMRC shall pay to the Concessionaire by way of
Termination Payment an amount equal to 80% (eighty
percent) of the Debt Due. For the avoidance of doubt,
the Concessionaire hereby acknowledges that no

FAO(OS)(COMM) No. 58/2018 Page 72 of 97
Termination Payment shall be due or payable on account
of a Concessionaire‟s Default occurring prior to COD."

104. DAMEPL it is accepted and admitted had applied for and was
sanctioned project loans to the extent of Rs.1508.50 crores and US$
106000000 by banks and financial institutions. The tripartite escrow
agreement dated 24th March, 2009 was executed amongst DAMEPL, the
lenders and DMRC. There is no dispute and DMRC does not challenge and
question that Rs.1260.73 crores was due and payable under the Rupee term
loan sanctioned as on 7th January, 2013. Computation made with reference
to external commercial borrowings as on 7th January, 2013 of Rs.538.58
crores is also not disputed.

105. The dispute pertains to equity. In the balance sheets, books and
records of the Registrar, paid up and issued share capital of DAMEPL is
Rs.1 lakh. DAMEPL‟s claim letter dated 8th July, 2013 states that their
equity share capital was Rs.1 lakh. On the paid-up and issued share capital
also there is no dispute.

106. The dispute pertains to Rs.685 crores that was brought in as share
application money and was so recorded in the balance sheet and books of
DAMEPL for the year ending 31st March, 2010. However, in the balance
sheet and books for the year ending 31st March,2011 Rs.685 crores was not
shown as share application money. It was specifically shown as „Subordinate
Debt‟. This conversion was pursuant to resolution of the Board of Directors
of DAMEPL. Notice of termination dated 8th October,2012 had quantified
130% adjusted equity payable as Rs.1,30,000/-. In letter dated 1st December,
2012 the subordinate debt shown as payable by DAMEPL to M/s Reliance

FAO(OS)(COMM) No. 58/2018 Page 73 of 97
Infrastructure Ltd. was Rs. 687.90 crores, which includes Rs.685 crores.
DAMEPL in their claim letter dated 8th July,2013 had stated that subordinate
debt of Rs.670.77 crores from M/s Reliance Infrastructure Ltd. had been
used for the project assets.

107. Notwithstanding aforesaid categoric admissions and statements in the
books, balance sheet and records submitted with the Registrar of Companies,
DAMEPL in the claim statement filed before the Arbitral Tribunal had
treated Rs.685 crores as share application money and, therefore, a part of
equity. Accordingly, DAMEPL was entitled to payment of 130% of adjusted
equity by including Rs.685 crores.

108. Inspite of overwhelming evidence and material against DAMEPL,
Arbitral Tribunal has partly accepted the plea of DAMEPL by treating
Rs.611.95 crores as equity share capital for the reasoning which reads as
under:-

"124. In fact, following different figures of Equity/ Subordinated
debt as promoters contribution / Equity share capital appear in
various statements submitted by DAMEPL.

• Equity share capital Rs 1 lakh (appearing in Balance sheet)
and also in DAMEPL's claim letter dated 08.07.2013 (CD -
17, page 316)
 Equity by Promoters towards project of Rs. 685 crores in
Annexure CC-1 of the Counter Claim
 Net Subordinated Debt from R-lnfra of Rs. 687.90 crores
worked out on page 26 of the details submitted by DAMEPL
vide letter no. DJK/HM/1208 dtd. 01.12.2014
 Subordinated debt of Rs. 670.77 crores from R-lnfra used for
the project assets (DAMEPL's claim letter dtd. 08.07.2013)

FAO(OS)(COMM) No. 58/2018 Page 74 of 97
 Subordinated debt (promoter's contribution) of Rs. 611.95
crores by transfer of Share application dtd. 16.03.2011 (page
55 of the details submitted by DAMEPL vide letter no.
DJK/HM/1208 dtd. 01.12.2014.)

125. We have examined the above figures in the light of the
provisions in the CA. First question is whether "subordinated debt
from the promoters" is covered under the definition of
subordinated debt given in the CA.

From the definition of subordinated debt given in the CA
(reproduced on page 161), it is clear that only such subordinated
debts which are advanced or provided by the lenders or the
Concessionaire for meeting Concessionaire's Capital Costs and
interest thereon as stipulated are to be treated as Subordinated
Debt for the purpose of the CA. The amount contributed by a
member of the Consortium or a shareholder of the Concessionaire
to meet the Capital Costs of the Concessionaire in any form
including any subordinated debt are not to be treated as
Subordinated Debt under the definition of CA.

Second question is, can a project of this magnitude be executed
with an equity of Rs. 1 lakh? No lender will fund a project of this
size if Promoters intends to provide only Rs. 1 lakh as Equity. In
the present case, it will tantamount to an irrationally high Debt
Equity ratio. It is a common practice by lenders to fund the
projects at around 60 : 40 to 80 : 20 as Debt: Equity ratio. The
lenders do allow promoters (in the instant case R Infra) to bring in
their part of contribution, representing equity, either in the form of
equity share capital or preference share capital / subordinated debt
or a mix thereof. Generally, a condition is imposed by the lenders
on the promoters that till the time, the borrower has paid its part of
proportionate equity contribution, it will not be entitled to receive
loan.

126. At this stage, the definition of the word "equity" in the CA
may be recapitulated. The said definition specifically covers not
only the equity capital of DAMEPL, but includes "the funds

FAO(OS)(COMM) No. 58/2018 Page 75 of 97
advanced by any member of the consortium or by any of its
shareholders to the Concessionaire for meeting the equity
component of the Concessionaire's Capital Costs". Thus, there is a
specific definition of the word "equity" in the CA. The said
definition of equity gets subsumed in the definition of "adjusted
equity" in the CA which, in turn, means Equity which, apart from
equity share capital of DAMEPL, also includes the funds
advanced by any member of the consortium or by its shareholders
to DAMEPL. DMRC has nowhere pleaded or shown that
substantial money has not been advanced by the promoters. In
view thereof, the argument that it is only equity share capital as
understood within the meaning of Companies Act that is liable to
be refunded to DAMEPL under Article 29.5.2 (b), in our view, is
not correct. Now, a question arises as to how much of the
subordinated debt received from Reliance Infra (Promoter) is to be
treated as "Equity" for the calculation of "Adjusted Equity". In the
absence of a clear cut documentary proof submitted by DAMEPL,
this Tribunal has to go by the documents available with it. On
page 55 of the document submitted on 01.12.2014 on behalf of
DAMEPL, an amount of Rs. 611.95 crores appears as "Transfer
from share application - BOD Resolution 16th March, 2011". This
figure of Rs 611.95 crores also appears at page 35 in the
calculations given by DAMEPL vide their letter dated 1.12.2014
quoted above. To support the figure of Rs 73.27 crores (Equity
contribution after COD towards project assets), there is no
authentic document provided by the Respondent. Therefore, we
have decided to consider this amount as equity contribution from
the Promoters as this is closest to the COD (23.02.2011).
Adjusted equity will be worked out as per the formula given in CA
taking this amount (Rs. 611.95 crores) as "Equity".

127. After having decided the equity amount, we proceed to work
out the "Adjusted equity" in the manner stipulated in the CA.

• Equity funded till COD Rs.611.95 crores
• WPI on Appointed date (August 2008) 128.90
Appointed date taken as date of signing of Concession
Agreement (25.08.2008) as date of financial close / date of

FAO(OS)(COMM) No. 58/2018 Page 76 of 97
commencement of Concession Period is not available in the
documents submitted by the parties.

               • WPI on COD (23.02.2011)            148.10
• Variation in WPI 19.20
• Mean Variation 9.60
• % of mean variation 7.45%

• Base adjusted equity till COD Rs.611.95x1.0745
Rs.657.54 crores

After COD (February, 2011)

• WPI on COD 148.10
• WPI on the reference date i.e. the date
of Termination (07.01.2013) 170.3
• Variation in WPI 22.20
• % variation 15%
• Adjusted equity 657.54x1.15
Rs.756.17 crores
• 130% Adjusted Equity Rs.983.02 crores

128. The other component of Termination Payment is "Debt due".
"Debt due" comprises of two elements i.e. Rupee term loan and
External commercial borrowing (in foreign currency). For the loan
received and repaid, we have relied upon the information
submitted by DAMEPL through their advocates vide letter no.
DJK/HM/1208 dtd. 01.12.2014. In the absence of definition of
"Transfer Date" in the CA, we have taken the date of termination
i.e. 07.01.2013 as the reference date for the calculation of the
"Debt due."

128.1 Details of Rupee Term Loan are given in page 28 to 30. On
analyzing the said details, the following position emerges:

• Loan received till the date of termination
(07.01.2013) Rs. 1273,05,68,176/-
• Loan repaid till 07.01.2013 Rs. 12,32,78,012/-
• Net loan as on 07.01.2013 Rs. 1260,72,90,164/-

FAO(OS)(COMM) No. 58/2018 Page 77 of 97
Say Rs. 1260.73 crores

128.2 Details of External commercial borrowing is given in page
31 of the document mentioned in para 126 above.

• Loan received till termination date
(07.01.2013) Rs. 541,16,47,984/-

• Repayment till termination date Rs. 2,58,14,928/-
• Net loan on 07.01.2013 Rs. 538,58,33,056/-

Say Rs. 538.58 crores"

109. We find that the reasoning is completely flawed and perverse and
would falter when we apply the principles as held in Associate Builders
(supra). The reasoning suffers from the patent illegality, defies logic and is
irrational which no reasonable person would formulate. This is obvious and
patent from the face of the Award itself. Claim statement is not evidence and
material and cannot be read as evidence to state DAMEPL had given
different figures of equity and subordinate debt. Rs. 611.95 crores was
treated as equity on general assumption that debt equity ratio should be
around 60:40 to 80:20 ignoring overwhelming evidence that the share
application money by choice and election was converted as subordinate debt.
This conversion was pursuant to resolution of the Board of Director of
DAMEPL passed on 16th March.2011. The resolution though accepted and
admitted was not filed and brought on record by DAMEPL. Claim made was
therefore contrary to the books, records and even the Board resolution.
Ms.Neena Goel, partner of T.R. Chadha Co., Chartered Accountants, who
was produced by DAMEPL to prove the claim in question, in her cross-
examination had stated as under:-

"Q53. In that case, madam, please justify in law the
difference between the figure of equity by promoters as

FAO(OS)(COMM) No. 58/2018 Page 78 of 97
reflected in annexure CC-1 to the counter claim and the audited
balance sheet for the year ending 31-03-2013 of DAMEPL?
Ans. The figure of equity, I state once again, in the audited
balance sheet for the year ended 31-03-2013 is as per
Companies Act, 1956, i.e value for which shares have been
issued. Regarding the definition of equity and debt as per
the Concession Agreement there seems to be a case of
interpretation of the definition as given in the Concession
Agreement. The wording seems to suggest that subordinated
debt may be included in "equity". Therefore I have stated
earlier also that this is a matter which needs to be decided
by the Learned Counsel and the Arbitral Panel.

Q54 Madam, whether as per the Company law, the definition
of equity includes subordinate debts?

Ans No."

110. DMRC being aggrieved have highlighted the consequences of
Rs.611.5 crores being treated as a part of equity in their written submissions
stating;-

"a. On Rs. 611.5 Crores which has been treated as equity and has
been enhanced by WPI, and thus adjusted equity is Rs. 983 Cr. and
the total interest of SBI PLI + 2% from August 2013 till date is
approximately Rs. 834 Crore, which comes to Rs.1817 Crores.

b. On treating this amount of Rs. 611.5 Crores as subordinate debt
and therefore debt due, the interest amount would be zero as the
carrying cost on this subordinate debt which is loan from promoters
of DAMEPL is NIL as shown in the balance sheet of DAMEPL for
FY 2012-13 at page No. 10 and 15 of the compilation dated
25.09.2018 tendered by DAMEPL to the Hon‟ble Court, wherein no
interest amount/rate has been shown as payable on the amount of
subordinate debt. The difference between amount mentioned in Para

(b) (a) is Rs. 1205.50 Crore."

FAO(OS)(COMM) No. 58/2018 Page 79 of 97

DMRC‟s calculation on interest on termination payment in the above
computation in (b) as noticed below would not be entirely correct, albeit
difference by including Rs.611.95 crores in equity which was enhanced by
15% and then given mark up of 30% to computed adjusted equity of Rs.
983.02 crores would be substantial. Interest payable on termination payment
on differences between Rs.983.03 crores and 611.95 crores would be
correspondingly higher.

111. It hardly requires any reasoning to understand why share application
money Rs.685 crores were converted into subordinate debt. Under Article
29.4 of CA in case of DAMEPL‟s event of default termination payment
would not have included equity or share application money, but 80% of the
debt due including subordinate debt. Conversion of share application money
into subordinate debt was by choice, intentionally and deliberately taken by
DAMEPL, as it ran risk on converting share application money into equity
or retaining its character. DAMEPL had therefore opted to convert it into
subordinate debt to protect and insulate DAMEPL from the risk in terms of
Article 29.4 of the C.A. The Arbitral Tribunal was conscious of the said
position as in paragraph 125 of the award they had framed two questions
/issues. The award contradicts admission made by DAMEPL in the balance
sheet on equity share capital of Rs.1.0 lakh which was also the figures
mentioned in the DAMEPL‟s claim letter dated 8th July, 2013 and earlier
letter dated 8th October, 2012.

FAO(OS)(COMM) No. 58/2018 Page 80 of 97

112. The expressions "equity", "adjusted equity", "debt due",
"subordinated debt" and "concessionaire‟s capital costs" have been defined
in the CA and read as under:-

"Equity" means the sum expressed in Indian Rupees representing
the equity share capital of the Concessionaire and shall include the
funds advanced by any Member of the Consortium or by any of its
shareholders to the Concessionaire for meeting the equity
component of the Concessionaire's Capital Costs.

"Adjusted Equity" means the Equity funded in Indian Rupees and
adjusted on the first day of the current month (the "Reference
Date"), in the manner set forth below, to reflect the change in its
value on account of depreciation and variations in WPI, and for
any Reference Date occurring:

a) on or before COD, the Adjusted Equity shall be a sum equal
to the Equity funded in Indian Rupees and expended on the
Project, revised to the extent of one half of the variation in WPI
occurring between the first day of the month of Appointed Date
and the Reference Date;

b) from COD and until the 4th (fourth) anniversary thereof, an
amount equal to the Adjusted Equity as on COD shall be
deemed to be the base (the "Base Adjusted Equity") and the
Adjusted Equity hereunder shall be a sum equal to the Base
Adjusted Equity, revised at the commencement of each month
following COD to the extent of venation in WPI occurring
between the COD and the Reference Date.

c) after the 4th (fourth) anniversary of COD, the Adjusted
Equity hereunder shall be a sum equal to the Base Adjusted
Equity, reduced by 0.42% (zero point four two per cent) (This
number shall be substituted in each case by the product of 100
divided by the number of months comprising the Concession
Period. For example, the figure for a 20 year Concession
Period shall be 100/240 0.416 rounded off to decimal points

FAO(OS)(COMM) No. 58/2018 Page 81 of 97
i.e. 0.42) thereof at the commencement of each month
following the 4th (fourth) anniversary of the Project Completion
Date and the amount so arrived at shall be revised to the extent
of variation in WPI occurring between COD and the Reference
Date; and the aforesaid shall apply, mutatis mutandis, to the
Equity funded in Indian Rupees. For the avoidance of doubt,
the Adjusted Equity shall, in the event of Termination, be
computed as on the Reference Date immediately preceding the
Termination Date; provided that no reduction in the Base
Adjusted Equity shall be made for a period equal to the
duration, if any, for which the Concession Period is extended,
but the revision on account of WPI shall continue to be made.

"Debt Due" means the aggregate of the following sums expressed
in Indian Rupees outstanding on the Transfer Date:

a) the principal amount of the debt provided by the Senior
Lenders under the Financing Agreements for financing the
Total Project Cost (the "principal") but excluding any part of
the principal that had fallen due for repayment two years prior
to the Termination Date;

b) all accrued interest, financing fees and charges payable under
the Financing Agreements on, or in respect of, the debt referred
to in Sub-clause (a) above until the Transfer Date but excluding

(i) any interest, fees or charges that had fallen due one year
prior to the Transfer Date, (ii) any penal interest or charges
payable under the Financing Agreements to any Senior Lender,
and (iii) any pre-payment charges in relation to accelerated
repayment of debt except where such charges have arisen due to
Authority Default; and

c) any Subordinated Debt which is included in the Financial
Package and disbursed by lenders for financing the Total
Project Cost;

FAO(OS)(COMM) No. 58/2018 Page 82 of 97

"Subordinated Debt' means the aggregate of the following sums
expressed in Indian Rupees or in the currency of debt, as the case
may be, outstanding as on the date of termination:

a) the principal amount of debt provided by lenders or the
Concessionaire for meeting the Concessionaire's Capital Cost
and subordinated to the financial assistance provided by the
Senior Lenders; and

b) all accrued interest on the debt referred to in Sub-clause (a)
above but restricted to the lesser of actual interest rate and a
rate equal to 5% (five per cent) above the Bank Rate in case of
loans expressed in Indian Rupees and lesser of the actual
interest rate and six-month LIBOR (London Inter Bank Offer
Rate) plus 2% (two per cent) in case of loans expressed in
foreign currency, but does not include any interest that had
fallen due one year prior to the Termination Date.

provided that if all or any part of the Subordinated Debt is
convertible into Equity at the option of the lenders and/or the
Concessionaire, it shall for the purposes of this Agreement be
deemed to be Subordinated Debt even after such conversion and
the principal thereof shall be dealt with as if such conversion had
not been undertaken.

"Concessionaire's Capital Costs" means following:
• Prior to COD, the cost of the Concessionaire's Works as set
forth in the Financing Documents plus any further additional
capital cost for any Change of Scope Instructed since the
finalization of the Financing Documents; and

•After COD, the actual capital cost of the Concessionaire's
Works upon Project Completion as certified by the Statutory
Auditors."

113. The expression "equity" means sum expressed in Indian rupee
representing equity share capital of the concessionaire. It also includes

FAO(OS)(COMM) No. 58/2018 Page 83 of 97
funds advanced by any member of the consortium or by any of its
shareholders for meeting equity component of concessionaire‟s capital costs.
Therefore, all amounts or funds advanced by member of the consortium or
shareholders do not qualify and are not treated as deemed equity. Amounts
advanced to meet equity component concessionaire‟s capital costs qualify
and are treated as equity. Adjusted equity literally adjusts equity by
accounting for depreciation and variation in the wholesale price index from
the reference date. Adjusted equity, therefore, does not postulate
„subordinate debt‟ being treated as equity.

114. The expression „debt due‟ refers to aggregate of sums expressed in
Indian rupees outstanding on the transfer date, which means the principal
amount of debt provided by senior lenders under financing agreements for
financing the total project cost, but excludes part of principal that had fallen
due for repayment two years prior to the termination date, which in this case
would not be relevant. „Debt dues‟ also includes all accrued interest till the
transfer date, but excludes interest which had fallen due one year prior to the
transfer date, penal interest or charges payable under financing agreement to
secure loan or any repayment charges. Lastly, it includes subordinate debt,
which is included in the financial package and disbursed by the lenders for
financing the total project cost. The expression „subordinated debt‟ means
aggregate of sums expressed in Indian rupees or in the currency of debt, as
the case may be, outstanding on the date of termination. This means the
principal amount of debt owed by the lenders or concessionaires, i.e., the
promoters, for meeting the concessionaire‟s capital cost and subordinated to
financial assistance provided by the senior lenders. It also includes interest

FAO(OS)(COMM) No. 58/2018 Page 84 of 97
on the debt above, but restricted to lesser or actual interest and rate equal to
5% above bank rate in case of loans expressed in Indian rupees and lesser of
the actual interest rate and six month LIBOR plus 2% in case of loan in
foreign currency. It does not include interest that had fallen due one year
prior to the termination date. The last part of the definition of „subordinated
debts‟ states that if all or any part of the subordinated debt is convertible into
equity at the option of the promoters of the concessionaire, it shall be
deemed to be subordinated debt even after the conversion. The principal
thereafter will be dealt with as if conversion had not been undertaken. The
expression „concessionaire‟s capital cost‟ means cost of the concessionaire‟s
works set forth in the financing documents plus any additional capital cost.
After COD, the actual capital cost of concessionaire‟s work upon project
completion as certified by the statutory auditors.

115. As noticed above, IRCON in their report had valued the cost of assets
to clear overheads and other charges installed and created by DAMEPL at
Rs.2273.67 crores. These details have been set out in paragraph 118 of the
Award. Arbitral Tribunal had held that the question of actual capital cost of
concessionaire‟s work was inconsequential.

116. The Award ignoring the clear position on both factual and legal has
substantially allowed the claim of DAMEPL to hold that amount of
Rs.611.95 crores should be considered as equity contribution by promoters
as it was close to commercial operation dated 23 rd January, 2011. Balance
73.05 crores was considered to be office and maintenance expenses. The
date of 23rd February, 2011 with reference to commencement of commercial
operation is not to be found in any of the clauses and at best would have

FAO(OS)(COMM) No. 58/2018 Page 85 of 97
been rebuttable presumption that the money could be converted into equity
but the fact that this amount was never converted into equity and in fact was
treated and converted into subordinate debt. Thus, violation of Sections
28(1) (a) and (3) of the AC Act as elucidated in Associate Builders (supra)
is clearly attracted. The oscillating conduct and stand of DAMEPL with
reference to the balance sheet, board resolution and even claim letter dated
8th July, 2013 and termination notice dated 8th October, 2012 have all been
brushed aside for specious and illusive reason that a capital-intensive project
would have required substantial equity component and therefore, amount of
Rs.611.95 crores should be treated as equity for calculation of adjusted
equity. This was notwithstanding the Arbitral Tribunal‟s observations and
finding that there were no documents to support the said stand of DAMEPL.

117. During the course of arguments before us and even in the written
submission DAMEPL being aware of their weakness in alternative and
without prejudice had pleaded that amount of Rs.611.95 crores can be
equated to subordinate debt. It cannot be considered as a gift by the
members of the consortium of the promoters to the DAMEPL. We cannot
amend and modify the Award. We can set aside the finding in the Award.
In view of the above, we disapprove and set aside the finding that Rs.611.95
crores out of Rs.685 crores should be treated as equity for computing
adjusted equity, as entirely fallacious, absurd and perverse. These findings
of the Arbitral Tribunal are set aside on the ground of irrationality and no
reasonable person in the given circumstances would have arrived and
reached. Sections 28(1)(a) and (3) of the AC Act are also attracted as the

FAO(OS)(COMM) No. 58/2018 Page 86 of 97
contractual terms have been completely ignored or misconstrued in a way
that no fair minded and reasonable person would do.

INTEREST

118. The award under challenge on several claims has awarded interest to
DMRC and DAMEPL @ 11% per annum which would accrue from the date
of payment of requisite stamp duty. This was in view of the Article 36.2.6.1,
which reads as under:-

"36.2.6.1 Where the arbitral award is for payment of money,
no interest shall be payable on the whole or any part of the
money for any period till the date on which the award is
made"

119. However, the award has awarded interest @ SBI PLR plus 2% for
delay in payment of termination payment, in view of article 29.8 of the C.A.,
which reads as under:-

"29.8 Termination Payments: The Termination Payment
pursuant to this Agreement shall become due and payable to
the Concessionaire by DMRC within thirty days of a
demand being made by the Concessionaire with the
necessary particulars duly certified by the Statutory
Auditors. If DMRC fails to disburse the full Termination
Payment within 30 (thirty) days, the amount remaining
unpaid shall be disbursed along with interest an annualised
rate of SBI PLR plus two per cent for the period of delay
on such amount."

120. The award thus draws a difference between the 'termination payment'
which are covered and on which interest would be payable under Article

FAO(OS)(COMM) No. 58/2018 Page 87 of 97
29.8 post thirty days after demand for payment of termination payment is
made by DAMEPL, and interest payable on other amounts awarded. This
finding in the award is reasonable and we do not think that it can be
challenged under section 34 of the AC Act. Termination payments have
been classified separately and interest is payable by DMRC to the
concessionaire after thirty days of demand by the concessionaire with
necessary particulars certified by the statutory auditors. Rate of interest
payable in case of default and failure by DMRC to make payment has been
specified. The findings of the Arbitral Tribunal with reference to Article
29.8 would also be in consonance with law of contract and other clauses of
the C.A. relating to subordinate debt which stipulates computation the
interest on a different basis i.e. lessor of actual interest rate or Bank Rate
plus 5% in case of loans expressed in Indian rupees. Article 1.4.1 (i) of the
CA states that in case of ambiguities or discrepancies between two or more
articles, the provisions of specific article relevant to the issue under
consideration shall prevail. Between Article 29.8 and Article 36.2.6.1 in
respect of termination payment, Article 29.8, which is specific to termination
payment, will prevail.

121. The contention of DMRC that there would be unjust enrichment, as
the award itself accepts and records that the secured loan account by
DAMEPL carried interest of Rs.12.75% per annum and foreign currency
loan account carried interest in the range of 4.83% to 5.6% per annum, has
been rightly rejected by the Arbitral Tribunal as it would amount to change,
alteration or modification of Article 29.8 of the C.A. Article 29.8 of the
C.A. does not include penal interest and other charges which could be

FAO(OS)(COMM) No. 58/2018 Page 88 of 97
payable by the concessionaire to the lenders. Article 29.8 consciously and
deliberately does not refer to the actual interest being paid by the
concessionaire but rate of interest as stated therein i.e. SBI PLR rate plus 2%
per annum is payable. Actual interest rate applicable to the concessionaire
could be less or even more than the rates specified in Article 29.8.
Difference in language of Article 29.8 and interest component to be included
in „subordinate debt‟ as noticed above is perceptible. In latter case, till
termination payment becomes due, actual interest payable restricted to an
upper limit is payable. Article 29.8 is differently worded and applies on
DMRC‟s failure to make payment within 30 days after termination payment
becomes due. For the same reason it would not matter whether interest free
loan or debt was granted.

122. In the written submission filed by the DMRC, they have submitted
that no interest should be payable on Rs.611.5 crores by treating the said
amount as subordinate debt, even under Article 29.8. In terms of above
reasoning this argument cannot be accepted and must be rejected. Period
covered under „subordinate debt‟ clause and Article 29.8 relating to
termination payment has to be dealt with differently. Rate of interest
payable is different. Even otherwise, nothing prevents DAMEPL from
paying interest to its promoters on the money advanced on receipt of
payment etc. by modifying the terms mutually agreed. The transaction
between the two is not at arm‟s length. Promoter in the present case has
stated that they have borrowed money on interest to finance the costs
incurred by DAMEPL.

FAO(OS)(COMM) No. 58/2018 Page 89 of 97

123. We have quoted above the definition of the term "subordinate debt"
which in Clause B refers to 6 months LIBOR rate plus 2% in case of loan
based upon foreign currency. Questions would necessarily arise as to
application of provisions of Article 29.8 of the C.A. to subordinate debt
expressed in foreign currency. This aspect has not been considered in the
award. Neither has this aspect been raised by the DMRC in the objections or
during the course of arguments before us. We do not therefore, make any
comment on the said aspect.

CONCLUSION AND RESTITUTION

124. We have already referred to the interim order passed by the learned
Single Judge and thereafter in the present appeal by which DMRC has
undertaken and is bearing the interest burden on the debt taken by
DAMEPL. DMRC is not paying any debt or interest taken by the promoters.

125. Facts emerging from the aforesaid discussion are as under:-

(i) Findings of the Arbitral Tribunal on „Termination for DMRC‟s
Event of Default‟ under Article 29.5 of the CA are set aside
and quashed.

(ii) Finding of the Arbitral Tribunal that Rs.611.95 crores was
equity for the purpose of Article 29.5.2 is also set-aside and
quashed.

(iii) In view of the above, Award of Rs.2782.33 crores to DAMEPL
under Article 25.2 as termination payment under Article 29.5.2
on „DMRC Event of Default‟ including the finding of Rs.611.5

FAO(OS)(COMM) No. 58/2018 Page 90 of 97
crores should be treated as equity in adjusted equity, is set aside
and quashed.

(iv) Direction/award for payment of interest under Article 29.8
would become infructuous.

126. We had during the course of arguments called upon the parties to
respond to the issue of restitution and whether an award can be partly,
substantially or fully modified or set aside by this Court in this appeal. This
issue becomes important and relevant in view of the limited powers of the
Court under Section 34 of the AC Act. Supreme Court in Mc Dermott
International Inc. versus Burn Standard Company Limited and Ors.,
(2006) 11 SCC 181, states that AC Act makes provision for supervisory
role of the Court for review of the award only to ensure fairness and
interference in cases of fraud, bias, violation of principles of natural justice
etc. but the Court cannot correct errors of arbitration. It can only quash the
award leaving the parties to free to begin the arbitration again if they so
desire. Court‟s interference is, therefore, to be minimum and confined to
issues:

(i) Whether the award is contrary to the terms of the contract, and
therefore, no arbitrable dispute arose between the parties.

(ii) Whether the award was in any way violative of the public
policy.

(iii) Whether the award is contrary to substantive law in India,
which would include Sections 55 and 73 of the Contract Act.

(iv) Whether the reasons are vitiated by perversity in evidence in
contract.

FAO(OS)(COMM) No. 58/2018 Page 91 of 97

(v) Whether adjudication of a claim has been made in respect
whereof there was no dispute or difference or whether the
award is vitiated by internal contradictions.

127. Supreme Court in this case had also examined the issue of partial
award and observed that this expression is not used in the AC Act. Sub-
section 6 to Section 31 contemplates an interim award which is not one in
respect of which final award can be made but can be a final award on the
matters covered by it made at the interim stage. Reference can be made to
the earlier decision in the case Hindustan Zinc Ltd. versus Friends Coal
Corbonisation, (2006) 4 SCC 445 wherein the Supreme Court has held that
it was impermissible for the Appellate Bench of the High Court to do re-
calculation after it had failed to interfere with the portion of the award on the
ground that it was opposite to the specific terms of the contract. Reference
was also made by DMRC to judgment of the Madras High Court and
Bombay High Court in Central Warehousing Corporation versus A.S.A.
Transport, (2008) 3 MLJ 382 and R.S. Jiwani versus Ircon International
Ltd,. (2010) 1 Bom. CR.529. In the former case it was held after relying
upon the Mc Dermott International Inc. (Supra) that once an award has
been set aside consequential reliefs cannot be granted and the parties have
been left to begin with the arbitration if they so desire. Decision of the Full
Bench of Bombay High Court, however, takes a somewhat different view
and states that Court has the power to set aside the award partly or wholly
depending upon the facts of each case and principle of severability can be
applied where the matters can be clearly separated from the matters not
referred to arbitration. There are a number of decisions of this Court both
Single as well as Division Bench in Bharti Cellular Limited versus

FAO(OS)(COMM) No. 58/2018 Page 92 of 97
Department of Telecommunications, (2012) 192 DLT 729, State Trading
Corporation of Indian Ltd. versus M/s.Toepfer International Asia Pte Ltd.,
(2014) 3 Arb.Law Reporter 109; DDA versus Bhardwaj Brothers, AIR
2014 Delhi 147 and Puri Construction Pvt. Ltd. versus Larsen and Toubro
Ltd. and Another, 2015 SCC online Delhi 9126 holding the Court cannot
modify, amend and rectify the award.

128. The respondents have primarily relied upon the Full Bench decision of
the Bombay High Court in R.S. Jiwani (Supra) and our attention was also
drawn to the decision of the Supreme Court in Kinnari Mullick and Anr.
versus Ghanshyam Das Damani, (2018) 11 SCC 328. In the said decision
the Supreme Court had interpreted Section 34 (4) of the AC Act on the
power of the Court to remand the matter to the arbitral tribunal. It was held
that the said power can only be exercised when there is a written request
made by the party to the arbitration proceedings; where an arbitration award
has not already been set aside; and challenge to the arbitration award has
been set up under Section 34 about the deficiencies in the arbitral award
which may be curable by allowing arbitral tribunal to take such measures
which can eliminate the grounds for setting aside the arbitral award. This
judgment in paragraph 15 has referred to the decision in Mc Dermott
International Inc. (Supra) and has made observations on the assumption,
without expressing any opinion on the correctness and application of the
principle that an appeal is in continuum of the application under Section 34
of the Act.

129. In R.S. Jiwani (supra), the Full Bench of Bombay High Court while
applying the doctrines of severability and partial validity had clarified that

FAO(OS)(COMM) No. 58/2018 Page 93 of 97
the said principles can be applied only when portions of claims/counter
claims are capable of being severed and separated from the rest and not
when the decisions on issues are inter-connected and bifurcation would alter
the scope of the Award. Reference was made to Shin Satellite Public Co.
Ltd. versus Jain Studios Ltd., (2006) 2 SCC 628, where the Supreme Court
was dealing with the issue whether an arbitration clause could be invoked
inasmuch as a particular clause of the agreement was against public policy
and unenforceable. Reference was made to paragraph 430 of Halsbury Law
of England, 4th Edition, Volume 9, page 297 drawing four general principles
applicable to severance in case of contracts. The second principle states that
severance can be allowed where it is possible to strike out the offending
parts, without re-writing or re-arranging the contract. Thirdly, the court
would not alter entirely the scope and intention of the agreement and,
fourthly, shorn of offending parts, the contract must retain characteristics of
a valid contract, otherwise the other parts of the contract would also become
unenforceable. Chitty on Contracts (29th Edn. Vol. 1) pages 1048-49 also
draws distinction between cases where provisions are wholly void and where
good part is severable and not dependent upon the bad part, which can be
then severed, in which case good can be retained and bad can be rejected.
Care must be taken that the Court do not re-write or create a new contract or
an Award in which case it is impermissible to dissect and segregate.
Reference was made to Section 23 of the Contract Act. These principles, it
has been held, can be applied to an award after referring to the decision of
the Supreme Court in J.C. Budhraja versus Chairman, Orissa Mining
Corporation Ltd., (2008) 2 SCC 444 wherein it was held that the entire

FAO(OS)(COMM) No. 58/2018 Page 94 of 97
award need not be set aside and part of the award which is valid and
separable can be upheld.

130. We would, therefore, in the present case following the aforesaid
dictum and principle completely set aside the Award except to the extent we
have upheld the conclusion of the Arbitral Tribunal on the question of
waiver. As noticed, prayer for specific performance has not been pressed by
DMRC. We have also made observations upholding the Award on the
interpretation placed on Article 29.8, which deals with interest payable on
termination payment, but the direction to pay interest under Article 29.8 has
become infructuous. The direction of the Arbitral Tribunal awarding
Rs.46.94 crores as concessionaire fee though not challenged by DAMEPL is
inter-connected with the other portions of the Award, which we have set
aside. It would not be fair and correct to segregate this part and uphold the
direction to pay Rs.46.94 as concessionaire fee notwithstanding that we have
set aside the main portion of the Award. The award that DMRC must pay
DAMEPL net amount of Rs.147.76 crores towards net operating costs from
operations between 7th January, 2013 to 30th June, 2013 and net debt
servicing costs, Rs. 62.07 crores with interest on account of bank guarantee
and bank commission and Rs. 56.8 lakhs with interest for refund of security
deposit is liable to be set aside in view of the findings recorded on
termination on „DMRC Event of Default‟. The matter would have to be
adjudicated afresh if either DMRC or DAMEPL is to invoke and initiate
arbitration proceedings. Our directions for a fresh adjudication would apply
to validity or invalidity of non-exhaustive notice dated 9th July, 2012 on
which we have made no specific pronouncement as the issue is

FAO(OS)(COMM) No. 58/2018 Page 95 of 97
interconnected and linked with the findings in the Award set aside and
quashed by the present judgment. This observation and finding would
equally apply to claims of DMRC and counter claims of DAMEPL rejected
and dismissed for various reasons/grounds. The award on these aspects will
not be treated as binding and final, and these can be made subject matter of
fresh adjudication.

131. On the question of restitution and whether any orders or directions are
required, we leave it open to the DMRC and DAMEPL to file appropriate
application under Section 9 or other provision of the AC Act. It will also
be open to the DMRC to file an application relying on Section 144 read with
Section 151 of the Code of Civil Procedure, 1908, before the Division Bench
in this appeal. Notwithstanding disposal of the present appeal we have
given the said option and liberty as number of issues and contentions would
arise if and when we apply the principles of restitution. We had called upon
DMRC to consider the said aspect, including effect of non-
servicing/payment of debt due and payable by DAMEPL, „termination
payment‟, if payable, under Article 29.4 read-with the interest liability under
Article 29.8, etc. However, counsel for the DMRC were unable to obtain
instructions possibly because they could not have and would not have known
the outcome of the appeal and the final order which would be passed. These
would require due and deeper consideration on several aspects including
commercial consideration. Accordingly, we would leave it open to both
DMRC and DAMEPL to file application under the A C Act/Code of Civil
Procedure. If deemed appropriate and proper, DMRC can file an application
for restitution in view of the interim orders passed. We refrain and do not go

FAO(OS)(COMM) No. 58/2018 Page 96 of 97
into the said aspect at this stage, for it would have been inappropriate for us
to have heard arguments on mere assumptions.

132. The appeal is accordingly partly allowed setting aside the award in the
terms indicated above with liberty to the parties to invoke arbitration clause
for fresh adjudication on their claims and counter claims. Liberty is also
granted to the DMRC to move an application for restitution and both parties
to move applications under the A C Act. In the facts of the case, there
would be no order as to costs.

(SANJIV KHANNA)
JUDGE

(CHANDER SHEKHAR)
JUDGE
JANUARY 15th, 2019
NA/VKR/SSN

FAO(OS)(COMM) No. 58/2018 Page 97 of 97

Leave a Reply

Your email address will not be published. Required fields are marked *


Not found ...? HOW TO WIN 498a, DV, DIVORCE; Search in Above link
MyNation Times Magzine


All Law documents and Judgment copies
Laws and Bare Acts of India
Landmark SC/HC Judgements
Rules and Regulations of India.

Recent Comments

STUDY REPORTS

Copyright © 2024 SC and HC Judgments Online at MyNation
×

Free Legal Help, Just WhatsApp Away

MyNation HELP line

We are Not Lawyers, but No Lawyer will give you Advice like We do

Please read Group Rules – CLICK HERE, If You agree then Please Register CLICK HERE and after registration  JOIN WELCOME GROUP HERE

We handle Women Centric biased laws like False Sectioin 498A IPC, Domestic Violence(DV ACT), Divorce, Maintenance, Alimony, Child Custody, HMA 24, 125 CrPc, 307, 312, 313, 323, 354, 376, 377, 406, 420, 497, 506, 509; TEP, RTI and many more…

MyNation FoundationMyNation FoundationMyNation Foundation