SC and HC Judgments Online at MyNation

Judgments of Supreme Court of India and High Courts

Perkins Eastman Architects DPC Vs. HSCC (India) Ltd. [26/11/19]

Section

Perkins Eastman Architects DPC Anr. Vs. HSCC (India) Ltd.

[Arbitration Application No. 32 of 2019]

Uday Umesh Lalit, J.

1. This application under Section 11(6) read with Section
11(12)(a) of Act1 and under the Scheme2 prays
for the following principal relief:

“(a) appoint a sole Arbitrator, in accordance with clause 24 of
the Contract dated 22nd May, 2017 executed between the parties and the sole Arbitrator so
appointed may adjudicate the disputes anddifferences between the parties
arising from the said Contract.”

1 The Arbitration and Conciliation Act, 1996

2 The Appointment of Arbitrators by the Chief Justice of India
Scheme, 1996 Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd.

2. The application has been filed with following assertions: –

(A) As an executing agency of Ministry of Health and Family
Welfare, the respondent was desirous of comprehensive architectural planning
and designing for the works provided under Pradhan Mantri Swasthya Suraksha Yojna (PMSSY). Therefore a request for Proposals
bearing RFP No.HSCC/3-AIIMS/Guntur/2016 was issued on 15.07.2016 for appointment
of Design Consultants for the “comprehensive planning and designing, including preparation
and development of concepts, master plan for the campus, preparation of all
preliminary and working drawings for various buildings/structures, including
preparation of specifications and schedule of quantities for the proposed All
India Institute of Medical Sciences at Guntur, Andhra Pradesh”.

(B) In response to the RFP, the consortium of the Applicants,
namely,

(i) Perkins Eastman Architects DPC, an Architectural firm having
its registered office in New York and (ii) Edifice Consultants Private Limited,
having its office in Mumbai submitted their bid on 28.09.2016. Letter of Intent
was issued on 31.01.2017 awarding the project to the Applicants, the consideration
being Rs.15.63 crores. A letter of award was issued in favour of the Applicants
on 22.02.2017 and a contract was entered into between the Applicants and the
respondent on 22.05.2017, which provided Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd. inter alia for dispute resolution in Clause 24. The
relevant portion of said Clause was as under:

“24.0 DISPUTE RESOLUTION

24.1 Except as otherwise provided in the contract all questions
and disputes relating to the meaning of the specifications, design, drawings and instructions herein before mentioned and as to the quality of services rendered for the works or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, design, drawings, specifications estimates instructions, orders or these conditions or
otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work
or after the cancellation, termination, completion or abandonment thereof thereof shall be dealt with as mentioned hereinafter:

(i) If the Design Consultant considers any work demanded of him to
be outside the requirements of the contract or disputes on any drawings, record
or decision given in writing by HSCC on any matter in connection with arising
out of the contract or carrying out of the work, to be unacceptable, he shall
promptly within 15 days request CGM, HSCC in writing for written instruction or
decision. There upon, the CGM, HSCC shall give his written instructions or decision
within a period of one month from the receipt of the Design Consultants
letter.

(ii)
If the CGM, HSCC fails to give his instructions or decision in writing
within the aforesaid period or if the Design Consultant(s) is dissatisfied with
the instructions or decision of the CGM, HSCC, the Design Consultants(s) may,
within 15 days of the receipt of decision, appeal to the Director (Engg.) HSCC
who shall offer an opportunity to the Design Consultant to be heard, if the latter so desires, and to offer evidence in
support of his appeal. The Director (Engg.), HSCC shall give his decision
within 30 days of receipt of Arbitration Application No.32 of 2019Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd. Design Consultants appeal. If
the Design Consultant is dissatisfied with the decision, the Design Consultant
shall within a period of 30 days from receipt of this decision, give notice to
the CMD, HSCC for appointment of arbitrator failing which the said decision
shall be final, binding and conclusive and not referable to adjudication by the
arbitrator.

(ii) Except where the decision has become final, binding and
conclusive in terms of sub-Para (i) above disputes or difference shall be
referred for adjudication through arbitration by a sole arbitrator appointed by
the CMD HSCC within 30 days form the receipt of request from the Design
Consultant. If the arbitrator so appointed is unable or unwilling to act or
resigns his appointment or vacates his office due to any reason, whatsoever
another sole arbitratorshall be appointed in the manner aforesaid.

Such person shall be entitled to proceed with the reference from
the reference from the stage at which it was left by his predecessor. It is a
term of this contract that the party invoking arbitration shall give a list of disputes
with amounts claimed in respect of each such dispute along with the notice for
appointment of arbitrator and giving reference to the rejection by the CMD,
HSCC of the appeal.

It is also a term of this contract that no person other than a
person appointed by such CMD, HSCC as aforesaid should act as arbitrator. It is
also a term of the contract that if the Design Consultant does not make any
demand for appointment of arbitrator in respect of any claims in writing as
aforesaid within 120 days of receiving the intimation from HSCC that the final
bill is ready for payment, the claim of the Design Consultant shall be deemed to
have been waived and absolutely barred and HSCC shall be discharged and
released of all liabilities under the contract and in respect of these claims.

The arbitration shall be conducted in accordance with the
provisions of the Arbitration and Conciliation Act, 1996 (26 of 1996) or any
statutory modifications or re-enactment thereof and the rules made there under
and for the time being in force shall apply to the arbitration proceeding under
this clause.” Arbitration
Application No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC
(India) Ltd.

(C) Within six days of the signing of the said contract, in letter
dated 26.5.2017 the respondent alleged failure on part of the Applicants which was
followed by stop work notice dated 03.11.2017. It is the case of the Applicants
that officials of the respondents were deliberately trying to stall the project
and were non-co-operative right from the initial stages.

(D) Later, a termination notice was issued by the respondent on 11.01.2019
alleging non-compliance of contractual obligations on part of the Applicants,
which assertions were denied. However, termination letter was issued on
20.02.2019. On 11.04.2019 a notice was issued by the Advocate for the
applicants invoking the dispute resolution Clause namely Clause 24 as aforesaid
raising a claim of Rs.20.95 crores. According to the Applicants, a decision in respect of the notice
dated 11.04.2019 was required to be taken within one month in terms of Clause 24
of the contract but a communication was sent by the respondent on 10.05.2019
intimating that a reply to the notice would be sent within 30 days.

(E) An appeal was filed by the Applicants before the Director (Engineering)
in terms of said Clause 24 but there was complete failure on part of the
Director (Engineering) to discharge the obligations in terms of said Clause 24.
Therefore, by letter dated 28.06.2019 the Chief Managing Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. Director of the respondent was called upon to appoint a sole
arbitrator in terms of said Clause 24. However, no appointment of an arbitrator
was made within thirty days but a letter was addressed by Chief General Manager
of the respondent on 30.07.2019 purportedly appointing one Major General K.T.
Gajria as the sole arbitrator.

(F) The relevant averments in para 3 of the application are:- “z. The
30 (thirty) day time period for appointment of a sole arbitrator stood expired
on 28th July, 2019 and yet the CMD of the respondent failed to appoint a
sole arbitrator or even respond to the letter dated 28th June,
2019 (received on 29th June, 2019). aa. Shockingly, in continuance of its highhanded approach and in
contravention to its own letter dated 24th June,
2019, the CGM of the Respondent addressed the Purported Appointment Letter
dated 30th July, 2019 to one Major General K.T. Gajria thereby purportedly
appointing him as a sole arbitrator in the matter. On the same date, the CGM of
the Respondent also addressed a letter to the Applicants inter alia informing
about the purported appointment of Mr. Gajria”

3. In the aforesaid premises the Applicants submit:-

(a) The Applicants had duly invoked the arbitration clause;

(b) The Chairman and Managing Director was the competent authority
to appoint a sole arbitrator;

(c) But the Chief General Manager of the respondent wrongfully appointed
the sole arbitrator;

(d) Such appointment was beyond the period prescribed; Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd.

(e) In any case, an independent and impartial arbitrator is
required to be appointed.

4. In response to the application, an affidavit-in-reply has
been filed by the respondent denying all material allegations. It is accepted
that the contract entered into between the parties contains Clause 24 regarding dispute resolution. It is, however, disputed that there was any
inaction on part of the respondent in discharging their obligations in terms of
Clause

24. It is submitted, inter alia, that

(a) The appointment of Major General K.T. Gajria was in consonance
with Clause 24 of the contract;

(b) Such appointment could not in any way be said to be illegal;

(c) There was no occasion to file an application seeking appointment
of any other person under the provisions of Section 11(6) read with Section
11(12)(a) of the Act; and

(d) In any case, the arbitration in the present matter would not
be an International Commercial Arbitration within the meaning of Section 2(1)(f)
of the Act.

5. We heard Mr. Amar Dave, learned Advocate for the Applicants
and Mr. Guru Krishna Kumar, learned Senior Advocate for the respondent. Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. It was submitted by Mr. Dave, learned Advocate that on account
of failure on part of the respondent in discharging its obligations in terms of
Clause 24, the applicants would be entitled to maintain the present Application
and seek appointment of an arbitrator as prayed for.

It was further submitted that the appointment process
contemplated in Clause 24 gave complete discretion to the Chairman and Managing
Director of the respondent to make an appointment of an arbitrator of his
choice, the Chairman and Managing Director of the respondent would naturally be
interested in the outcome or decision in respect of the dispute, the
prerequisite of element of impartiality would, therefore, be conspicuously absent
in such process; and as such it would be desirable that this Court makes an
appropriate appointment of an arbitrator.

Reliance was placed on the decisions of this Court in Walter
Bau AG, Legal Successor of the Original Contractor, Dyckerhoff and Widmann,
A.G. v. Municipal Corporation of Greater Mumbai and another 3 and TRF
Limited v.Energo Engineering Projects Limited 4 in
support of the submissions. Mr. Dave, learned Advocate also relied upon the
decision of this Court in Larsen and Toubro Limited SCOMI Engineering BHD
v. Mumbai Metropolitan Region Development Authority 5 to bring home the point that Arbitration Application No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd.

the arbitration in the present matter would be an International
Commercial Arbitration.Mr. Guru Krishna Kumar, learned Senior Advocate
appearing for the respondent submitted that no case was made out to maintain
the instant application. He submitted that two basic submissions were raised in
para 3 in sub-para (z) and (aa) of the application that the Chairman and
Managing Director failed to appoint the sole arbitrator within 30 days of the requisition
dated 28.06.2019 and that it was the Chief General Manager of the respondent
who purportedly made the appointment of a sole arbitrator on 30.07.2019.

The infirmities thus projected were on two counts, namely, for
over-stepping the limit of 30 days; and secondly the appointment was not made
by the Chairman and Managing Director of the respondent. He pointed out that
the period in terms of requisition dated 28.06.2019 expired on Friday and the
appointment was made on the first available working day. Secondly, the
appointment was actually made by the Chairman and Managing Director but was
conveyed by the Chief General Manager, and as such the alleged infirmities were
completely non-existent. He further submitted that arbitration, if any, in the
instant matter would not be an International Commercial Arbitration.

6. The present application, therefore, raises two basic issues;
first whether the arbitration in the present case would be an International Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. Commercial
Arbitration or not. In case, it is not, then this Court cannot deal with the
application under Section 11(6) read with Section 11(12)(a) of the Act. The
second issue is whether a case is made out for exercise of power by the Court
to make an appointment of an arbitrator.

7. During the course of hearing, reliance was placed by the
Applicants on the Consortium Agreement entered into between the Applicant No.1
and the Applicant No.2 on 20.09.2016 which described the Applicant No.1 as the
lead member of the Consortium. The relevant recital and the Clause of the
Agreement were as under:

“1. WHEREAS all the Parties agree that Perkins Eastman will be
the focal point for the agreement and interaction with the client.”

“9. Perkins Eastman and M/s. Edifice Consultants are jointly and
severally responsible for the execution of the project” In terms of requirements of the bid documents and RFP a “Declaration
for Lead Member of the Consortium (Form E)” was also submitted. The declaration
was as under:

“WHEREAS M/s. HSCC (India) Ltd. (HSCC) (the Client) has invited
Bids/Bids from the interested parties for providing Comprehensive Planning and Designing
of the Proposed All India Institute of Medical Sciences at Mangalagiri, Guntur
(AP). AND WHEREAS, the members of the Consortium are interested in
bidding for the Project and implementing the Project in accordance with the Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd.

terms and conditions of the Request for Bid (RFP) document,
Terms of Reference, Clients Requirement, Notice Inviting Bid, Instructions to
Bidders,Conditions of Contract and other connected documents in respect of the
Project, and AND WHEREAS, it is necessary under the RFP document for the
members of the Consortium Bidder to designate one of them as the Lead Manager
with all necessary power and authority to do for and on behalf of the
Consortium bidder, all acts, deeds and things as may be necessary in connection
with the Consortium Bidders proposal for the Project.

NOW THIS DECLARATION WITNESSETH THAT; We, Perkins Eastman
Architects DPC, and having its registered office at 115 5th Ave
Floor 3, New York, NY 10003-10004, USA and M/s. Edifice Consultants Private
Limited having its registered office at Srirams Arcade, 3rd Floor,
Opp. Govandi P.O., Off Govandi Station Road, Govandi East, Mumbai, Maharashtra 400088
do hereby designate Perkins Eastman Architects DPC being one of the members of
the Consortium, as the Lead Member of the Consortium, to do on behalf of the
Consortium, all or any of the acts, deeds of things necessary or incidental to
the Consortiums Application/Bid for the Project, including submission of
Application/Bid, participating in conferences, responding to queries, submission
of information/documents and generally to represent the Consortium in all its
dealings with HSCC, any other Government Agency or any person, in connection with
the Project until culmination of the process of bidding and thereafter till the
completion of the Contract.”

8. It is not disputed by the respondent that it was a requisite
condition to declare a lead member of the Consortium and that by aforesaid declaration
the applicant No.1 was shown to be the lead member of the Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. Consortium.
The reliance is however placed by the respondent on Clause 9 of the Consortium
Agreement by virtue of which both the Applicants would be jointly and severely
responsible for the execution of the project.

It is clear that the declaration shows that the Applicant No.1
was accepted to be the lead member of the Consortium. Even if the liability of
both the Applicants was stated in Clause 9 to be joint and several, that by itself
would not change the status of the Applicant No.1 to be the lead member. We
shall, therefore, proceed on the premise that Applicant No.1 is the lead member
of the Consortium.

9. In Larsen and Toubro Limited SCOMI Engineering BHD 5 more or less similar fact situation came up for consideration. The only distinction was
that the lead member in the consortium was an entity registered in India.
Paragraphs 2, 3, 4, 15, 17, 18 and 19 of the decision are as under:

“2. Since disputes arose between the parties to the agreement,
various interim claims had been made by the Consortium of M/s Larsen and
Toubro, an Indian company, together with Scomi Engineering Bhd, a company
incorporated in Malaysia, for which the Consortium has filed this petition under Section 11 of the Act
to this Court, since according to them, one of the parties to the arbitration
agreement, being a body corporate, incorporated in Malaysia, would be a body corporate,
which is incorporated in a country other than India, which would attract Section
2(1)(f)(ii) of the Act. Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd.

3. Shri Gopal Jain, learned Senior Counsel appearing on behalf of the Consortium, has taken us through the agreement, in which he strongly relies upon the fact that the two entities, that is, the Indian company and the Malaysian company, though stated to be a Consortium, are jointly and severally liable, to the employer.The learned Senior Counsel has also relied upon the fact that throughout the working of the contract, separate claims have been made, which have been rejected by the Mumbai Metropolitan Region Development Authority (hereinafter referred to as “MMRDA”). He has also further relied upon the fact that by at least three letters, during the working of the agreement, the claims have in fact been rejected altogether and that, therefore, there is no impediment in invoking the arbitration Clause under Section 20.4 of the general conditions of contract (hereinafter referred to as “GCC”), as the procedure outlined by Claus
es 20.1 to 20.3 had already been exhausted.

4. On the other hand, Mr Shyam Divan, learned Senior Counsel
appearing on behalf of MMRDA, the respondent, has relied upon both the contract
dated 9- 1-2009 as well as the actual consortium agreement dated 4-6-2008
between the Indian company and the Malaysian company, which, when read together, would show that
they are really an unincorporated association and would, therefore, fall within
Section 2(1)(f)(iii) as being an association or a body of individuals,
provided the central management and control is exercised in any country other than India.

15. Section 2(1)(f)(iii) of the Act refers to two different
sets of persons: an “association” as distinct and separate from a “body of
individuals”. For example, under Section 2(31) of the Income Tax Act, 1961,”person”
is defined as including, under subclause

(v), an association of persons, or body of individuals,
whether incorporated or not. It is in this sense, that an association is
referred to in Section 2(1) (f)(iii) which would therefore
include a consortium consisting of two or more bodies corporate, at least one
of whom is a body corporate incorporated in a country other than India. Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd.

17. Law Commission Report No. 246 of August 2014, which made several amendments to the Arbitration and Conciliation Act, 1996, gave the following reason for deleting the words “a company or”: “(iii) In sub-section (1), clause (f), sub-clause (iii), delete the words “a company or” before the words “an association or a body of individuals”. [Note.-The reference to “a company” in subsection

(iii) has been removed since the same is already covered under
sub-section (ii). The intention is to determine the residence of a company based on its place of incorporation and not the place of central management/control. This further re-enforces the “place of
incorporation” principle laid down by the Supreme Court in TDM
Infrastructure (P) Ltd. v. UE Development India (P) Ltd.6, and
adds greater certainty in case of companies having a different place of incorporation
and place of exercise of central management and control.]” It would become
clear that prior to the deletion of the expression “a company or”, there were
three sets of persons referred to in Section 2(1)(f)(iii) as
separate and distinct persons who would fall within the said sub-clause. This
does not change due to the deletion of the phrase “a company or” for the reason
given by the Law Commission. This is another reason as to why “an association” cannot be read with “body of individuals”
which follows it but is a separate and distinct category by itself, as is
understood from the definition of “person” as defined in the Income Tax Act
referred to above.

18. This being the case, coupled with the fact, as correctly argued
by Shri Divan, that the Indian company is the lead partner, and that the
Supervisory Board constituted under the consortium agreement makes it clear
that the lead partner really has the determining voice in that it appoints the Chairman of the said
Board (undoubtedly, with the consent of other members); and the fact that the
Consortiums office is Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd. in Wadala, Mumbai as also that
the lead member shall lead the arbitration proceedings, would all point to the fact
that the central management and control of this Consortium appears to be
exercised in India and not in any foreign nation.

19. This being the case, we dismiss the petition filed under Section
11 of the Act, as there is no “international commercial arbitration” as defined
under Section 2(1)(f) of the Act for the petitioner to come to this
Court. We also do not deem it necessary to go into whether the appropriate stage for invoking arbitration
has yet been reached.”

10. It was thus held that “Association” and “Body of
individuals” referred to in Section 2(1)(f) of the Act would be separate
categories. However, the lead member of the Association in that case being an
Indian entity, the “Central Management and Control” of the Association was held
to be in a country other than India. Relying on said decision we conclude that
the lead member of the Consortium company i.e. Applicant No.1 being an
Architectural Firm having its registered office in New York, requirements of
Section 2(1)(f) of the Act are satisfied and the arbitration in the present case would be an “International Commercial
Arbitration”.

11. That takes us to the second issue, namely, whether a case
has been made out for exercise of power by the Court for an appointment of an arbitrator. Arbitration Application No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd.

12. The communication invoking arbitration in terms of Clause 24 was sent by the Applicants on 28.06.2019 and the period within which the respondent
was to make the necessary appointment expired on 28.07.2019. The next day was a
working day but the appointment was made on Tuesday, the 30th July,
2019. Technically, the appointment was not within the time stipulated but such
delay on part of the respondent could not be said to be an infraction of such
magnitude that exercise of power by the Court under Section 11 of the Act
merely on that ground is called for.

13. However, the point that has been urged, relying upon the
decision of this Court in Walter Bau AG 3 and TRF
Limited 4 , requires consideration. In the present case Clause 24 empowers
the Chairman and Managing Director of the respondent to make the appointment of a sole
arbitrator and said Clause also stipulates that no person other than a person
appointed by such Chairman and Managing Director of the respondent would act as
an arbitrator.

In TRF Limited 4 , a
Bench of three Judges of this Court, was called upon to consider whether the
appointment of an arbitrator made by the Managing Director of the respondent
therein was a valid one and whether at that stage an application moved under Section 11(6)
of the Act could be entertained by the Court. The relevant Clause, namely,
Clause 33 which provided for resolution of disputes in that case was under: Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. “33. Resolution of dispute/arbitration

(a) In case any
disagreement or dispute arises between the buyer and the seller under or in connection with the PO, both shall make every effort to resolve it amicably by direct informal negotiation.

(b) If, even after 30 days from the commencement of such
informal negotiation, seller and the buyer have not been able to resolve the dispute amicably, either party may require that the
dispute be referred for resolution to the formal mechanism of arbitration.

(c) All disputes which cannot be settled by mutual negotiation
shall be referred to and determined by arbitration as per the Arbitration and Conciliation Act, 1996 as amended.

(d) Unless otherwise provided, any dispute or difference between the parties in connection with this agreement shall be referred to sole arbitration
of the Managing Director of buyer or his nominee. Venue of arbitration shall be
Delhi, and the arbitration shall be conducted in English language.

(e) The award of the Tribunal shall be final and binding on
both, buyer and seller.”

14. In TRF Limited 4 , the
Agreement was entered into before the provisions of the Amending Act (Act No.3
of 2016) came into force. It was submitted by the appellant that by virtue of
the provisions of the Amending Act and insertion of the Fifth and Seventh
Schedules in the Act,the Managing Director of the respondent would be a person
having direct interest in the dispute and as such could not act as an
arbitrator. The extension of the submission was that a person who himself was disqualified
and disentitled could also not nominate any other person to act Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. as an arbitrator. The submission countered by the respondent therein was as under:

“7.1. The submission to the effect that since the Managing Director of the respondent has become ineligible to act as an arbitrator subsequent to the amendment
in the Act, he could also not have nominated any other person as arbitrator is absolutely unsustainable, for the Fifth and the Seventh Schedules fundamentally guide in determining whether circumstances exist which give rise to justifiable doubts as to the independence and impartiality of the arbitrator. To elaborate, if any person whose relationship with the parties or the counsel or the subject-matter of dispute falls under any of the categories specified in the Seventh Schedule, he is ineligible to be appointed as an arbitrator but not otherwise. The issue was discussed and decided by this Court as under:

50. First, we shall deal with Clause (d). There is no quarrel that by virtue of Section 12(5) of the Act, if any person who falls under any
of the categories specified in the Seventh Schedule shall be ineligible to be
appointed as the arbitrator. There is no doubt and cannot be, for the language employed in the Seventh
Schedule, the Managing Director of the Corporation has become ineligible by
operation of law. It is the stand of the learned Senior Counsel for the appellant
that once the Managing Director becomes ineligible, he also becomes ineligible
to nominate.

Refuting the said stand, it is canvassed by the learned Senior
Counsel for the respondent that the ineligibility cannot extend to a nominee if
he is not from the Corporation and more so when there is apposite and requisite
disclosure. We think it appropriate to make it clear that in the case at hand
we are neither concerned with the disclosure nor objectivity nor impartiality
nor any such other circumstance. We are singularly concerned with the issue,
whether the Managing Director, after becoming ineligible by operation of law,
is he still eligible to Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd. nominate an arbitrator. At the
cost of repetition, we may state that when there are two parties, one may nominate
an arbitrator and the other may appoint another. That is altogether a different
situation. If there is a clause requiring the parties to nominate their respective
arbitrator, their authority to nominate cannot be questioned.

What really in that circumstance can be called in question is
the procedural compliance and the eligibility of their arbitrator depending
upon the norms provided under the Act and the Schedules appended thereto. But,
here is a case where the Managing Director is the “named sole arbitrator” and
he has also been conferred with the power to nominate one who can be the
arbitrator in his place. Thus, there is subtle distinction. In this regard, our
attention has been drawn to a two-Judge Bench decision in State of Orissa v.
Commr. of Land Records Settlement7. In
the said case, the question arose, can the Board of Revenue revise the order passed
by its delegate. Dwelling upon the said proposition, the Court held: (SCC p.
173, para 25)

“25. We have to note that the Commissioner when he
exercises power of the Board delegated to him under Section 33 of the
Settlement Act, 1958, the order passed by him is to be treated as an order of
the Board of Revenue and not as that of the Commissioner in his capacity as Commissioner.
This position is clear from two rulings of this Court to which we shall
presently nrefer. The first of the said rulings is the one decided by the
Constitution Bench of this Court in Roop Chand v. State of Punjab8. In
that case, it was held by the majority that where the State Government had,
under Section 41(1) of the East Punjab Holdings (Consolidation and Prevention
of Fragmentation) Act, 1948,delegated its appellate powers vested in it under Section
21(4) to an “officer”, an order passed by such an officer was an order passed
by the State Government itself and “not an order passed by any officer under this Act” within Section 42 and was not
revisable by the State Government.

It was pointed out that for the purpose of exercise 7 (1998) Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. of
powers of revision by the State under Section 42 of that Act, the order sought
to be revised must be an order passed by an officer in his own right and
not as a delegate of the State. The State Government was, therefore, not
entitled under Section 42 to call for the records of the case which was
disposed of by an officer acting as its delegate.”

(emphasis in original).

51. Be it noted in the said case, reference was made to Behari
Kunj Sahkari Awas Samiti v. State of U.P.9, which
followed the decision in Roop Chand v. State of Punjab8. It is
seemly to note here that the said principle has been followed in Indore
Vikas Pradhikaran10.

52. Mr Sundaram has strongly relied on Pratapchand Nopaji11. In the said case, the three-Judge Bench applied the maxim “qui facit per alium
facit per se”. We may profitably reproduce the passage: (SCC p. 214, para
9) “9.The principle which would apply, if the objects are struck by
Section 23 of the Contract Act, is embodied in the maxim: “qui facit per alium
facit per se” (what one does through another is done by oneself). To put it
in another form, that which cannot be done directly may not be done indirectly
by engaging another outside the prohibited area to do the illegal act within
the prohibited area. It is immaterial whether, for the doing of such an illegal
act, the agent employed is given the wider powers or authority of the “pucca
adatia”, or, as the High Court had held, he is clothed with the powers of an
ordinary commission agent only.”

53. The aforesaid authorities have been commended to us to establish the proposition that if the 10 Indore Vikas Pradhikaran v.
Pure Industrial Coke Chemicals Ltd., (2007) 8 SCC 705 11 Pratapchand
Nopaji v. Kotrike Venkata Setty Sons, (1975) 2 SCC 208 Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. nomination
of an arbitrator by an ineligible arbitrator is allowed, it would tantamount to carrying on the proceeding of arbitration by himself. According to the learned counsel for the appellant, ineligibility strikes at the
root of his power to arbitrate or get it arbitrated upon by a nominee.

54. In such a context, the fulcrum of the controversy would be, can an ineligible arbitrator, like the Managing Director, nominate an arbitrator,
who may be otherwise eligible and a respectable person. As stated earlier, we
are neither concerned with the objectivity nor the individual respectability.
We are only concerned with the authority or the power of the Managing Director.
By our analysis, we are obligated to arrive at the conclusion that once the
arbitrator has become ineligible by operation of law, he cannot nominate
another as an arbitrator. The arbitrator becomes ineligible as per prescription
contained in Section 12(5) of the Act. It is inconceivable in law that person
who is statutorily ineligible can nominate a person. Needless to say, once the
infrastructure collapses, the superstructure is bound to collapse. One cannot
have a building without the plinth. Or to put it differently, once the identity
of the Managing Director as the sole arbitrator is lost, the power to nominate someone
else as an arbitrator is obliterated. Therefore, the view expressed by the High
Court is not sustainable and we say so.”

15. It was thus held that as the Managing Director became
ineligible by operation of law to act as an arbitrator, he could not nominate
another person to act as an arbitrator and that once the identity of the
Managing Director as the sole arbitrator was lost, the power to nominate
someone else as an arbitrator was also obliterated. The relevant Clause in said
case had nominated the Managing Director himself to be the sole arbitrator and also
empowered said Managing Director to nominate another person to act Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. as an
arbitrator. The Managing Director thus had two capacities under said Clause,
the first as an arbitrator and the second as an appointing authority. In the
present case we are concerned with only one capacity of the Chairman and
Managing Director and that is as an appointing authority.

We thus have two categories of cases. The first, similar
to the one dealt with in TRF Limited 4 where
the Managing Director himself is named as an arbitrator with an additional
power to appoint any other person as an arbitrator. In the second category,
the Managing Director is not to act as an arbitrator himself but is empowered
or authorised to appoint any other person of his choice or discretion as an
arbitrator. If, in the first category of cases, the Managing Director was found
incompetent, it was because of the interest that he would be said to be having
in the outcome or result of the dispute.

The element of invalidity would thus be directly relatable to and arise from the interest that he would be having in such outcome or decision. If
that be the test, similar invalidity would always arise and spring even in the
second category of cases. If the interest that he has in the outcome of the
dispute, is taken to be the basis for the possibility of bias, it will always
be present irrespective of whether the matter stands under the first or
second category of cases. We are conscious that if such deduction is
drawn from the decision of this Court in TRF Limited 4 , all cases
having clauses similar to that with which we are presently concerned, Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd.a party to the agreement would be disentitled to make any appointment of an Arbitrator on its own and it would always be available to argue that a party or an official or an authority having interest in the dispute would be disentitled to make appointment of an Arbitrator.

16. But, in our view that has to be the logical deduction from TRF Limited 4 . Paragraph 50 of the decision shows that this Court was concerned
with the issue, “whether the Managing Director, after becoming ineligible by
operation of law, is he still eligible to nominate an Arbitrator” The
ineligibility referred to therein, was as a result of operation of law, in that
a person having an interest in the dispute or in the outcome or decision thereof,
must not only be ineligible to act as an arbitrator but must also not be
eligible to appoint anyone else as an arbitrator and that such person cannot
and should not have any role in charting out any course to the dispute
resolution by having the power to appoint an arbitrator.

The next sentences in the paragraph, further show that cases
where both the parties could nominate respective arbitrators of their choice
were found to be completely a different situation. The reason is clear that
whatever advantage a party may derive by nominating an arbitrator of its choice
would get counter balanced by equal power with the other party. But, in a case
where only one party has a right to appoint a sole arbitrator, its choice will
always have an element of exclusivity in determining or charting the Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. course
for dispute resolution. Naturally, the person who has an interest in the
outcome or decision of the dispute must not have the power to appoint a sole
arbitrator. That has to be taken as the essence of the amendments brought in by
the Arbitration and Conciliation (Amendment) Act, 2015 (Act 3 of 2016) and
recognised by the decision of this Court in TRF Limited 4 .

17. We must also at this stage refer to the following
observations made by this Court in para 48 of its decision in Indian Oil
Corpn. Ltd. v. Raja Transport (P) Ltd. 12 , which
were in the context that was obtaining before Act 3 of 2016 had come into
force:

“48. In the light of the above discussion, the scope of Section 11 of the Act containing the scheme of appointment of arbitrators may be summarised thus:

(i) Where the agreement provides for arbitration with three
arbitrators (each party to appoint one arbitrator and the two appointed
arbitrators to appoint a third arbitrator), in the event of a party failing to
appoint an arbitrator within 30 days from the receipt of a request from the other
party (or the two nominated arbitrators failing to agree on the third
arbitrator within 30 days from the date of the appointment), the Chief Justice
or his designate will exercise power under sub-section (4) of Section 11 of the
Act.

(ii) Where the agreement provides for arbitration by a sole
arbitrator and the parties have not agreed upon any appointment procedure, the
Chief Justice or his designate will exercise power under sub-section (5) of Section
11, if the parties fail to agree on the Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd. arbitration within thirty days
from the receipt of a request by a party from the other party.

(iii) Where the arbitration agreement specifies the appointment
procedure, then irrespective of whether the arbitration is by a sole arbitrator
or by a threemember Tribunal, the Chief Justice or his designate will exercise
power under sub-section (6) of Section

11, if a party fails to act as required under the agreed procedure
(or the parties or the two appointed arbitrators fail to reach an agreement
expected of them under the agreed procedure or any person/institution fails to
perform any function entrusted to him/it under that procedure).

(iv) While failure of the other party to act within 30 days
will furnish a cause of action to the party seeking arbitration to approach the
Chief Justice or his designate in cases falling under sub-sections (4) and (5),
such a time-bound requirement is not found in sub-section (6) of Section 11. The failure to act as per the
agreed procedure within the time-limit prescribed by the arbitration agreement,
or in the absence of any prescribed time-limit, within a reasonable time, will enable
the aggrieved party to file a petition under Section 11(6) of the Act.

(v) Where the appointment procedure has been agreed between
the parties, but the cause of action for invoking the jurisdiction of the Chief
Justice or his designate under clauses (a), (b) or (c) of
sub-section (6) has not arisen, then the question of the Chief Justice or his designate exercising power under subsection (6)
does not arise. The condition precedent for approaching the Chief Justice or
his designate for taking necessary measures under sub-section (6) is that

(i) a party failing to act as required under the agreed
appointment procedure; or

(ii) the parties (or the two appointed arbitrators) failing
to reach an agreement expected of them under the agreed appointment procedure;
or Arbitration Application No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd.

(iii) a person/institution who has been entrusted with
any function under the agreed appointment procedure, failing to perform such
function.

(vi) The Chief Justice or his designate while exercising
power under sub-section (6) of Section 11 shall endeavour to give effect to
the appointment procedure prescribed in the arbitration clause.

(vii) If circumstances exist, giving rise to justifiable doubts
as to the independence and impartiality of the person nominated, or if other
circumstances warrant appointment of an independent arbitrator by ignoring the
procedure prescribed, the Chief Justice or his designate may, for reasons to be recorded ignore the designated
arbitrator and appoint someone else.”

18. Sub para (vii) of aforesaid paragraph 48 lays down that if
there are justifiable doubts as to the independence and impartiality of the
person nominated, and if other circumstances warrant appointment of an independent
arbitrator by ignoring the procedure prescribed, such appointment can be made
by the Court. It may also be noted that on the issue of necessity and
desirability of impartial and independent arbitrators the matter was considered
by the Law Commission in its report No.246. Paragraphs 53 to 60 under the
heading “Neutrality of Arbitrators” are

quoted in the Judgment of this Court in Voestapline
Schienen Gmbh v. Delhi Metro Rail Corpn. Ltd. 13 , while
paras 59 and 60 of the report stand extracted in the decision of this Court in Bharat
Broadband Network Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd. Limited v. United
Telecoms Limited 14 For the present
purposes, we may rely on paragraph 57, which is to the following effect:

“57. The balance between procedural fairness and binding nature
of these contracts, appears to have been tilted in favour of the latter by the
Supreme Court, and the Commission believes the present position of law is far
from satisfactory. Since the principles of impartiality and independence cannot be discarded
at any stage of the proceedings, specifically at the stage of constitution of
the Arbitral Tribunal, it would be incongruous to say that party autonomy can be
exercised in complete disregard of these principles – even if the same has been
agreed prior to the disputes having arisen between the parties.

There are certain minimum levels of independence and impartiality that should be required of the arbitral process regardless of the parties
apparent agreement. A sensible law cannot, for instance, permit appointment of
an arbitrator who is himself a party to the dispute, or who is employed by (or
similarly dependent on) one party, even if this is what the parties agreed.
The Commission hastens to add that Mr P.K. Malhotra, the ex officio member of
the Law Commission suggested having an exception for the State, and allow State
parties to appoint employee arbitrators.

The Commission is of the opinion that, on this issue, there
cannot be any distinction between State and non-State parties. The concept of
party autonomy cannot be stretched to a point where it negates the very basis
of having impartial and independent adjudicators for resolution of disputes. In
fact, when the party appointing an adjudicator is the State, the duty to
appoint an impartial and independent adjudicator is that much more onerous –
and the right to natural justice cannot be said to have been waived only on the
basis of a “prior” agreement between the parties at the time of the contract
and before arising of the disputes.” Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd.

19. In Voestalpine 3, this
Court dealt with independence and impartiality of the arbitrator as under:

“20. Independence and impartiality of the arbitrator are the
hallmarks of any arbitration proceedings. Rule against bias is one of the
fundamental principles of natural justice which applied to all judicial and
quasijudicial proceedings. It is for this reason that notwithstanding the fact that relationship between the parties
to the arbitration and the arbitrators themselves are contractual in nature and
the source of an arbitrators appointment is deduced from the agreement entered
into between the parties, notwithstanding the same non-independence and
nonimpartiality of such arbitrator (though contractually agreed upon) would
render him ineligible to conduct the arbitration.

The genesis behind this rational is that even when an arbitrator
is appointed in terms of contract and by the parties to the contract, he is independent
of the parties. Functions and duties require him to rise above the partisan
interest of the parties and not to act in, or so as to further, the particular
interest of either parties. After all, the arbitrator has adjudicatory role to
perform and,therefore, he must be independent of parties as well as impartial.
The United Kingdom Supreme Court has beautifully highlighted this aspect in Hashwani
v. Jivraj15 in the following words: (WLR p. 1889, para 45)

“45. the dominant purpose of appointing an arbitrator
or arbitrators is the impartial resolution of the dispute between the parties
in accordance with the terms of the agreement and, although the
contract between the parties and the arbitrators would be a contract for the
provision of personal services, they were not personal services under the
direction of the parties.” Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd.

21. Similarly, Cour de Cassation, France, in a judgment delivered in 1972 in Consorts Ury, underlined that: “an independent mind is
indispensable in the exercise of judicial power, whatever the source of that
power may be, and it is one of the essential qualities of an arbitrator.”

22. Independence and impartiality are two different concepts. An arbitrator may be independent and yet, lack impartiality, or vice versa.
Impartiality, as is well accepted, is a more subjective concept as compared to independence.
Independence, which is more an objective concept, may, thus, be more straightforwardly
ascertained by the parties at the outset of the arbitration proceedings in
light of the circumstances disclosed by the arbitrator, while partiality will
more likely surface during the arbitration proceedings.

30. Time has come to send positive signals to the international business community, in order to create healthy arbitration environment and
conducive arbitration culture in this country. Further, as highlighted by the
Law Commission also in its report, duty becomes more onerous in government contracts, where one of
the parties to the dispute is the Government or public sector undertaking
itself and the authority to appoint the arbitrator rests with it.

In the instant case also, though choice is given by DMRC to the
opposite party but it is limited to choose an arbitrator from the panel
prepared by DMRC. It, therefore, becomes imperative to have a much broadbased
panel, so that there is no misapprehension that principle of impartiality and
independence would be discarded at any stage of the proceedings, specially at
the stage of constitution of the Arbitral Tribunal. We, therefore, direct that
DMRC shall prepare a broadbased panel on the aforesaid lines, within a period
of two months from today.” Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd.

20. In the light of the aforestated principles, the report of
the Law Commission and the decision in Voestapline Schienen Gmbh 13, the imperatives
of creating healthy arbitration environment demand that the instant application
deserves acceptance.

21. The further question that arises is whether the power can be exercised by this Court under Section 11 of the Act when the appointment of an
arbitrator has already been made by the respondent and whether the appellant
should be left to raise challenge at an appropriate stage in terms of remedies
available in law. Similar controversy was gone into by a Designated Judge of
this Court in Walter Bau AG 3 and the discussion on the point was as under:

“9. While it is correct that in Antrix16 and Pricol
Ltd.17, it was opined by this Court that after appointment of an
arbitrator is made, the remedy of the aggrieved party is not under Section
11(6) but such remedy lies elsewhere and under different provisions of the
Arbitration Act (Sections 12 and 13), the context in which the aforesaid view
was expressed cannot be lost sight of. In Antrix16,
appointment of the arbitrator, as per the ICC Rules, was as per the alternative
procedure agreed upon, whereas in Pricol Ltd.17., the party which had filed the application under Section 11(6)
of the Arbitration Act had already submitted to the jurisdiction of the
arbitrator. In the present case, the situation is otherwise.

10. Unless the appointment of the arbitrator is ex facie valid and such appointment satisfies the Court Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd. exercising jurisdiction under
Section 11(6) of the Arbitration Act, acceptance of such appointment as a fait
accompli to debar the jurisdiction under Section 11(6) cannot be countenanced
in law. In the present case, the agreed upon procedure between the parties contemplated
the appointment of the arbitrator by the second party within 30 days of receipt
of a notice from the first party.

While the decision in Datar Switchgears Ltd.18 may
have introduced some lexibility in the time frame agreed upon by the parties by
extending it till a point of time anterior to the filing of the application
under Section 11(6) of the Arbitration Act, it cannot be lost sight of that in
the present case the appointment of Shri Justice A.D. Mane is clearly contrary
to the provisions of the Rules governing the appointment of arbitrators by
ICADR, which the parties had agreed to abide by in the matter of such
appointment. The option given to the respondent Corporation to go beyond the
panel submitted by ICADR and to appoint any person of its choice was clearly
not in the contemplation of the parties.

If that be so, obviously, the appointment of Shri Justice A.D.
Mane is non est in law. Such an appointment, therefore, will not inhibit the
exercise of jurisdiction by this Court under Section 11(6) of the Arbitration
Act. It cannot, therefore, be held that the present proceeding is not
maintainable in law. The appointment of Shri Justice A.D. Mane made beyond 30
days of the receipt of notice by the petitioner, though may appear to be in
conformity with the law laid down in Datar Switchgears Ltd18., is
clearly contrary to the agreed procedure which required the appointment made by
the respondent Corporation to be from the panel submitted by ICADR. The said appointment,
therefore, is clearly invalid in law.”

22. It may be noted here that the aforesaid view of the
Designated Judge in Walter Bau AG 3 was
pressed into service on behalf of the appellant in TRF Limited 4 and the
opinion expressed by the Designated Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd. Judge was found to be in consonance with the binding authorities
of this Court. It was observed:

“32. Mr Sundaram, learned Senior Counsel for the appellant has also drawn inspiration from the judgment passed by the Designated Judge of this Court
in Walter Bau AG3, where the learned Judge, after referring to Antrix Corpn.
Ltd16. ,distinguished the same and also distinguished the authority in Pricol Ltd. v.
Johnson Controls Enterprise Ltd.17 and came
to hold that: (Walter Bau AG case3, SCC p. 806, para 10)

“10. Unless the appointment of the arbitrator is ex facie
valid and such appointment satisfies the Court exercising jurisdiction under
Section 11(6) of the Arbitration Act, acceptance of such appointment as a fait
accompli to debar the jurisdiction under Section 11(6) cannot be countenanced
in law.”

33.We may immediately state that the opinion expressed in the
aforesaid case is in consonance with the binding authorities we have referred
to hereinbefore.”

23.In TRF Limited 4 , the
Managing Director of the respondent had nominated a former Judge of this Court
as sole arbitrator in terms of aforesaid Clause 33(d), after which the
appellant had preferred an application under Section 11(5) read with Section
11(6) of the Act. The plea was rejected by the High Court and the appeal
therefrom on the issue whether the Managing Director could nominate an
arbitrator was decided in favour of the appellant as stated hereinabove. As
regards the issue about fresh appointment, this Court remanded the matter to
the High Court for Arbitration Application No.32 of 2019 Perkins Eastman Architects
DPC Anr. v. HSCC (India) Ltd. fresh consideration as is
discernible from para 55 of the Judgment. In the light of these authorities
there is no hindrance in entertaining the instant application preferred by the Applicants.

24. It is also clear from the Clause in the instant case that no
special qualifications such as expertise in any technical field are required of
an arbitrator. This was fairly accepted by the learned Senior Counsel for the respondent.

25. In the aforesaid circumstances, in our view a case is made
out to entertain the instant application preferred by the Applicants. We,
therefore, accept the application, annul the effect of the letter dated
30.07.2019 issued by the respondent and of the appointment of the arbitrator. In
exercise of the power conferred by Section 11(6) of the Act, we appoint Dr.
Justice A.K. Sikri, former Judge of this Court as the sole arbitrator to decide
all the disputes arising out of the Agreement dated 22.05.2017,
between the parties, subject to the mandatory declaration made under the
amended Section 12 of the Act with respect to independence and impartiality and
the

ability to devote sufficient time to complete the arbitration
within the period as per Section 29A of the Act. A copy of the Order be
dispatched to Dr. Justice A. K. Sikri at 144, Sundar Nagar, New Delhi – 110003
(Tel. No.:- 011 – 41802321). The arbitrator shall be entitled to charge fees in
Arbitration
Application No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC
(India) Ltd. terms of the Fourth Schedule to the Act. The fees and other
expenses shall be shared by the parties equally.

26. Before we part, we must say that the appointment of an
arbitrator by this Court shall not be taken as any reflection on the competence
and standing of the arbitrator appointed by the respondent. We must place on record that not even a suggestion in that respect was made by
the learned counsel for the Applicants. The matter was argued and has been considered
purely from the legal perspective as discussed hereinabove.

27. This application is allowed in aforesaid terms. ARBITRATION
APPLICATION NO.34 OF 2019 Perkins Eastman Architects DPC Anr.
Applicants VERSUS HSCC (India) Ltd.Respondent

28. The basic facts in this application are more or less
identical except that the request for proposal in this case pertains to
“comprehensive planning and designing, including preparation and development of
concepts, master plan for the campus, preparation of all preliminary and working
drawings for various buildings/structures, including preparation of specifications
and schedule of quantities for the proposed All India Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd. Institute
of Medical Sciences at Kalyani, West Bengal.”.

Clause No.24 titled as “Dispute Resolution” in this case and
the communication addressed by the Applicants are also identical and the
response by the respondent was also similar. In this case also, appointment of
a sole arbitrator was made by the respondent vide communication dated 30.07.2019.
Since the facts are identical and the submissions are common, this application
is disposed of in terms similar to the main matter.

29. In the aforesaid circumstances, we accept the application,
annul the effect of the letter dated 30.07.2019 issued by the respondent and of
the appointment of the arbitrator. In exercise of the power conferred by Section 11(6) of the Act, we appoint Dr. Justice A.K. Sikri,
former Judge of this Court as the sole arbitrator to decide all the disputes
arising out of the Agreement dated 22.05.2017, between the parties, subject to
the mandatory declaration made under the amended Section 12 of the Act with
respect to independence and impartiality and the ability to devote sufficient
time to complete the arbitration within the period as per Section 29A of the
Act. A copy of the Order be dispatched to Dr. Justice A. K. Sikri at 144,
Sundar Nagar, New Delhi – 110003 (Tel. No.:- 011 – 1802321).

The arbitrator Arbitration Application
No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC (India) Ltd shall be entitled to charge fees in terms of the Fourth Schedule to the Act. The fees and other expenses shall be shared by the parties equally. ARBITRATION APPLICATION NO.35 OF 2019 Perkins Eastman Architects DPC Anr. Applicants VERSUS HSCC (India) Ltd. Respondent

30. The basic facts in this application are more or less
identical except that the request for proposal in this case pertains to
“comprehensive planning and designing, including preparation and development of
concepts, master plan for the campus, preparation of all preliminary and working
drawings for various buildings/structures, including preparation of specifications
and schedule of quantities for the proposed All India Institute of Medical
Sciences at Nagpur, Maharashtra.” Clause No.24 titled as “Dispute Resolution”
in this case and the communication addressed by the Applicants are also
identical and the response by the respondent was also similar. In this case
also, appointment of a sole arbitrator was made by the respondent vide
communication dated 30.07.2019. Since the facts are identical and the
submissions are common, this application is disposed of in terms similar to the
main matter. Arbitration
Application No.32 of 2019 Perkins Eastman Architects DPC Anr. v. HSCC
(India) Ltd.

31. In the aforesaid circumstances, we accept the application,
annul the effect of the letter dated 30.07.2019 issued by the respondent and of
the appointment of the arbitrator. In exercise of the power conferred by Section 11(6) of the Act, we appoint Dr. Justice A.K. Sikri,
former Judge of this Court as the sole arbitrator to decide all the disputes
arising out of the Agreement dated 22.05.2017, between the parties, subject to
the mandatory declaration made under the amended Section 12 of the Act with
respect to independence and impartiality and the ability to devote sufficient
time to complete the arbitration within the period as per Section 29A of the
Act. A copy of the Order be dispatched to Dr. Justice A. K. Sikri at
144, Sundar Nagar, New Delhi – 110003 (Tel. No.:- 011 – 41802321). The
arbitrator shall be entitled to charge fees in terms of the Fourth Schedule to
the Act. The fees and other expenses shall be shared by the parties
equally.

…………………J.(Uday Umesh Lalit)

………………….J.(Indu Malhotra)

New Delhi;

November 26, 2019.

1 The Arbitration and Conciliation Act, 1996

2 The Appointment of Arbitrators by the Chief Justice of India
Scheme, 1996

3 (2015) 3 SCC 800

4 (2017) 8 SCC 377

5 (2019) 2 SCC 271

6 (2008) 14 SCC 271

7 SCC 162

8 AIR 1963 SC 1503

9 (1997) 7 SCC 37

10 Indore Vikas Pradhikaran v. Pure Industrial Coke
Chemicals Ltd., (2007) 8 SCC 705

11 Pratapchand Nopaji v. Kotrike Venkata Setty Sons,
(1975) 2 SCC 208

12 (2009) 8 SCC 520

13 (2017) 4 SCC 665

14 (2019) 5 SCC 755

15 (2011) 1 WLR 1872; 2011 UKSC 40

16 (2014) 11 SCC 560

17 (2015) 4 SCC 177

18 (2000) 8 SCC 151

Section SectionBack

Leave a Reply

Your email address will not be published. Required fields are marked *


Not found ...?HOW TO WIN 498a, DV, DIVORCE; Search in Above link
MyNation Times Magzine


All Law documents and Judgment copies
Laws and Bare Acts of India
Landmark SC/HC Judgements
Rules and Regulations of India.

STUDY REPORTS

Copyright © 2024 SC and HC Judgments Online at MyNation
×

Free Legal Help, Just WhatsApp Away

MyNation HELP line

We are Not Lawyers, but No Lawyer will give you Advice like We do

Please read Group Rules – CLICK HERE, If You agree then Please Register CLICK HERE and after registration  JOIN WELCOME GROUP HERE

We handle Women Centric biased laws like False Sectioin 498A IPC, Domestic Violence(DV ACT), Divorce, Maintenance, Alimony, Child Custody, HMA 24, 125 CrPc, 307, 312, 313, 323, 354, 376, 377, 406, 420, 497, 506, 509; TEP, RTI and many more…

MyNation FoundationMyNation FoundationMyNation Foundation